You return to your house in France and find the extension next door already built. You never saw a planning notice. The town hall tells you the neighbour had a building permit (permis de construire) and points you toward the planning file. The first question is whether you can still ask a judge to cancel that particular permit. Request the permit, its approved drawings and the completion declaration, together with the record of when the town hall received it. If the town hall identifies more than one permit, ask which work each decision covers.
Check two dates in parallel. Proper, continuous on-site display can start the ordinary two-month court period on the first day of display. Separately, an application to annul the permit is inadmissible after six months from completion, with receipt of the completion declaration treated as the completion date unless there is evidence to the contrary. See Planning Code Article R. 600-2, Article A. 424-17 and Article R. 600-3. The date you returned is useful for your evidence timeline. It cannot answer either question by itself. If you are considering asking the town hall to reconsider, prepare the court route in parallel. Under the current rule a request for administrative reconsideration does not extend the court filing period. See Article L. 600-12-2.
I. Can I still challenge my neighbour’s French building permit after the work is finished?
A. What does it mean if I never saw a building permit notice?
Start with three separate facts, each of which deserves its own entry in your chronology. When did the town hall issue the planning decision? When does the permit holder say it was posted on the land? When did you or someone looking after your property first see the structure, the board or both? A planning decision downloaded from the municipality’s website identifies the authorisation. A photograph from the street can show where the board stood and what it said. The date you heard about the project helps explain how you came to look into it. Keep all three even if at first only the date of your return is certain.
The holder has the duty to display the permit on site, visibly from outside, throughout the works under Planning Code Article R. 424-15. The same article provides for publication at the town hall or on the municipality’s website. For the ordinary court time limit applicable to a third party, the provision to check is Article R. 600-2, which refers to « à compter du premier jour d’une période continue de deux mois d’affichage sur le terrain » (from the first day of a continuous period of two months of posting on the land). Article A. 424-17 sets out the notice of the two-month court period that the board is required to carry. Write down the claimed first day as well as the claimed span of continuous display. The end of the display period is not a new starting point under those provisions.
When someone says the board was present, ask where they stood and which parts they could read. The format and contents are laid down in Article A. 424-15 and Article A. 424-16. In a building project look for the holder’s name, permit number and date, the nature of the project, the site and floor areas, the height measured relative to natural ground level, and the town hall address where the file can be inspected. Article A. 424-18 requires that the information remain legible from a public road or a space open to the public during the works. A wide shot from the available public viewpoint tells you more about visibility than a close-up taken from beside the board. The close-up is useful for a different reason. It shows what the board actually says.
Evidence of display is assessed as a whole. In its 17 December 2018 decision, no. 411920, the Council of State (Conseil d’État), France’s highest administrative court, said « le juge doit apprécier la continuité de l’affichage en examinant l’ensemble des pièces qui figurent au dossier qui lui est soumis » (the judge must assess continuity of display by examining all the documents in the file submitted to them). The holder has to justify compliance with the display requirements, but a general assertion that continuous display has not been proved was insufficient in that case. The challengers had themselves supplied a photograph of the board and offered nothing concrete to call continuity into question. If you were abroad, say so plainly and ask people who were there which days and viewpoints they can account for. Avoid asking a witness to assert that a board was never there when their personal observations cover a few visits.
Separate a missing board from a board that was present but lacked the required text about the ordinary court deadline. In Council of State, 20 April 2023, no. 464606, paragraph 3, the court explained that where display was otherwise compliant but omitted the specified time limit, a reasonable period ran from the first day of the continuous two-month display. Generally, absent particular circumstances, more than a year is unreasonable in that situation. The same paragraph expressly confirms that the completion-based cutoff can bar an application even while that reasonable period is still open. Keep any photograph of the wording. A picture proving that something was posted is less helpful if you cannot tell which notice the board carried.
Where there was no display at all, the same case distinguishes learning about a permit from taking formal action against it. The lower court had used a meeting with the town hall as evidence that a two-month court period had started. The Council of State quashed the ruling and held that, absent any posting, an administrative or court challenge by a third party, revealing knowledge of the permit, can be capable of starting the court period against that party. See no. 464606, paragraph 4. Keep copies of any letter already sent by you or on your behalf. A request for the file and a letter expressly asking the authority to cancel the authorisation are different documents. The words you actually used matter more than the heading you gave the letter.
B. When does the six-month cutoff after completion start?
Planning Code Article R. 600-3 states « Sauf preuve contraire, la date de cet achèvement est celle de la réception de la déclaration d’achèvement » (unless there is evidence to the contrary, the completion date is the date on which the completion declaration was received). It sets a six-month cutoff after completion for an action seeking annulment of a building or development permit or a decision not to oppose a prior works declaration (déclaration préalable). This is the first rule to check when the site looks finished and you have no reliable display history. The completion declaration has a date written by the person who prepared it. The administrative record may carry a separate receipt date. Obtain both and record which one you are looking at.
Ask for the declaration certifying completion and conformity of the work (déclaration attestant l’achèvement et la conformité des travaux, or DAACT). Under the current Planning Code Article R. 462-1, the declaration is drawn up by the authorisation holder or by the architect or approved architectural professional if they supervised the work. It is sent to the mayor by registered post with a request for acknowledgement of receipt, or lodged at the town hall against a receipt. Ask for a copy of the received document and the proof of receipt associated with it. A forwarded PDF signed by the neighbour, a builder’s handover note and a town hall stamp each prove different things. If what you have is an extract or a scan without its first page, note what is missing before treating any date as established.
Compare the declaration with the decision you are considering challenging. In Lyon Administrative Court of Appeal, 3 February 2026, no. 23LY02509, paragraph 3, the file included a declaration received in 2017 about works for a pool and associated structures. The earlier authorisations had been annulled. The court found that the declaration concerned those earlier authorisations and that the file did not show a declaration sent for the work authorised by the later regularising permit and amending permit. It rejected the objection that the challenge to those later decisions was out of time under Article R. 600-3. The key check is which authorisation the declaration relates to. If you receive two forms for the same address, compare their permit numbers, scope and dates against the decisions rather than assuming the older form covers the later project.
A genuine mismatch in scope is different from a clerical error. In Douai Administrative Court of Appeal, 13 October 2020, no. 19DA01243, paragraphs 2–7, a declaration contained errors in the reference number. The court treated those errors as formal and had no evidence rebutting the completion date. It used the date the declaration was lodged. The version of Article R. 600-3 applicable to that old dispute set a one-year cutoff. The current Article R. 600-3 provides six months. The distinction worth carrying into a current file is between an error in a form that still identifies the relevant work and a declaration that actually refers to different work. Highlight the conflicting entries and attach the pages that make the difference apparent.
Check whether the form concerns the entire project or a phase. Article R. 462-2 expressly calls for that distinction. Ask what is shown as complete in the declaration, then compare it with the approved drawings and what was observed. If workers came back after the declaration arrived, record the actual activity and location. A witness who saw work on the disputed exterior stair can say so. A witness who saw a van outside cannot tell you from that alone whether it was working on the stair or repainting another part of the house. Give the person assessing your case the original observations as well as your own explanation of why they matter.
There may also be a certificate of non-contestation of conformity (attestation de non-contestation de la conformité). Article R. 462-10 provides for a certificate stating that conformity was not contested by the authority, in the circumstances laid down in that provision. Article R. 462-6 concerns the authority’s own period to contest conformity. Record that process separately from the cutoff governing your application to annul the permit under Article R. 600-3. In particular, ask whether the certificate itself recites the original receipt date. Do not enter the date the certificate was issued in the column for receipt of the completion declaration.
II. How do I get the evidence and file a challenge from abroad?
A. What should I ask the town hall for, and what should I photograph?
Write to the planning department (service urbanisme) with the street address and, if available, the land registry plot reference (référence cadastrale). Ask it to identify the decision for the work you describe, for example the extension on the side facing your property. Request the written decision (arrêté), the approved drawings showing that side, and any amending or regularising decision (permis modificatif or permis de régularisation). Request each completion declaration relating to those decisions and its receipt record. Article L. 311-1 of the Code governing relations between the public and the administration provides for communication of administrative documents the authority holds, subject to the statutory exceptions. Ask for electronic copies and identify the documents by name so the department can see what you need. A response about publication of the permit at the town hall leaves open the factual question of display on the land.
Use the French document names in your request so the planning department can identify each item. Identify the property, describe the structure, then request the permit, approved plans, amendments, the DAACT and proof of its date of receipt. If the department replies that it has no declaration for that permit, save the complete message with its date and the permit reference in your request. Finding no record in the documents supplied tells you exactly what to follow up. It does not tell you which other records exist or what a court will find on the full evidence. Where the permit only covers part of the building, ask the department to identify all the authorisations it finds for the relevant works instead of choosing one solely because it is the most recent.
Ask a caretaker or neighbour with lawful access to take dated photographs from the public side of the site, and from your own property if they have permission. Get a view showing the street or gate, a separate view showing the physical works, and a readable photograph of any board that remains. Keep the original files. If the photograph arrives as a screenshot in a messaging app, ask for the original and record the location, date and circumstances in which it was taken. A French judicial officer (commissaire de justice) can also document what is visible on a specified visit. Explain which viewpoint matters and what you need recorded. If the board was already removed when work ended, look for contemporaneous photographs or firsthand accounts. Give each item its actual date and avoid presenting today’s photograph as proof of what was visible months earlier.
Suppose the town hall sends you a permit for a ground-floor extension, a later decision changing the roof and a completion form that lists only the original permit. The first useful question is which drawing authorises the feature you are worried about. Put a copy of the original elevation and the amended elevation side by side. Mark the window, balcony or roofline in question on a separate copy and keep both originals as supplied. Write down whether the receipt record is linked to the same form. This makes it possible to explain the discrepancy in two sentences and point to documents that another person can check. Keep a copy of your written request and the town hall’s answer with the file so it is clear which source supplied each drawing.
Build a short evidence index. Put the permit and any amendment first, then the completion declaration and its receipt, then the display evidence. For each item write what it proves and what it leaves open. For example, a wide photograph of an empty gate may show no board at that gate on a particular date. It may tell you nothing about the other street frontage. An approved elevation may show a blank wall where an elevated window now appears. That calls for a check of the amending plans before you decide whether your objection concerns the authorised design, the way it was built, or both. An electronic folder with dates in the filenames helps if other people are handling your French affairs while you are away. If the same authority has sent you property tax correspondence, keep that in a separate folder. A French property tax lawyer for non-resident owners can assess the tax file separately from the planning decision you are considering challenging.
B. Which court do I use, and what must I send after filing?
You must be able to explain why the authorised project directly affects the occupation, use or enjoyment of your property. Planning Code Article L. 600-1-2 sets that test. Ownership of a second home gives you a document to produce, and the plans and site evidence help explain the effect of the particular project. Show, for example, the position of a new elevated terrace relative to the rooms or outside area it would overlook. Under Article L. 600-1-3, standing is assessed as of the date the application was posted at the town hall, unless you establish particular circumstances. If you inherited or bought the property, record that date and include the title documents so the chronology can be examined. Bring evidence of lawful ownership or occupation in line with Article R. 600-4.
File in the administrative court (tribunal administratif) for the place where the property at issue is located, under Administrative Justice Code Article R. 312-7. Individuals acting without a lawyer can file electronically using the designated court service, Article R. 414-2. Identify the decision by its date and reference. Include the facts, the legal grounds and what you ask the judge to order, as required by Article R. 411-1. Attach the challenged decision subject to the justified-impossibility exception in Article R. 412-1. If you have yet to obtain the full decision, preserve the correspondence showing what you requested and how the authority replied. Build your chronology around the receipts you actually have, with a separate line for any contested date.
There is a further step after court filing. Planning Code Article R. 600-1 requires notification of the application to the authority that made the decision and to the holder of the permit, by registered letter with acknowledgement of receipt, within fifteen clear days of filing. The article treats the notification as made on dispatch and identifies the postal deposit certificate as proof of the date. Save the full application as filed, the court acknowledgement, the copies sent to both recipients and the postal receipts. A filing confirmation from the court is the proof of one step. It leaves you to organise and document the two notifications. If you are overseas, decide how those letters will be sent and who will retain the postal evidence before you file.
If the court case is still possible, articulate the outcome you seek. Put the disputed part of the permit alongside the approved drawing and the specific planning rule you say the authority misapplied. A judge may limit annulment to a part affected by a curable defect under Article L. 600-5, or pause the proceedings to allow a curable defect to be put right under Article L. 600-5-1, including after work is complete under the terms of those articles. An existing window, wall or platform also raises a factual question about whether what was built matches what was approved. Keep that question visible in the file even if your immediate request concerns annulment. It helps the person reviewing your case see why the decision, the drawings and photographs each have a role.
Conclusion
Ask the town hall for the specific permit that covers the work, any later decisions, and the completion declaration with proof of receipt. Collect any evidence about where and when notice was posted. The ordinary on-site display rule and the completion-based cutoff answer different questions under Article R. 600-2 and Article R. 600-3. If you can still file, set out the effect on your property, identify the decision and retain the postal proof that you notified both recipients under Article R. 600-1. Your strongest starting point from abroad is a dated record that links each document and each observation to the particular work you want the court to examine.