Your company sold machinery, carried out works or supplied a production line to a French customer. To win the deal, you agreed to provide a bank guarantee payable on first demand: a performance guarantee (garantie de bonne fin or garantie de bonne exécution), an advance payment guarantee (garantie de restitution d’acompte) or a guarantee replacing a retention on your invoices. Today your bank, or the French bank that issued the guarantee against your bank’s counter-guarantee, tells you that the customer has called it. The customer says you are late, that the equipment is defective or that the advance was not used for the project. You disagree, and the amount is large. The question is whether anything can still stop the payment.
Under French law the answer is narrow but real. A first-demand guarantee is an autonomous guarantee (garantie autonome): the bank promises to pay a sum on request, and the Civil Code states that « Le garant ne peut opposer aucune exception tenant à l’obligation garantie » (the guarantor may not raise any defence relating to the guaranteed obligation) (article 2321 of the Civil Code). The same article sets the exception: « Le garant n’est pas tenu en cas d’abus ou de fraude manifestes du bénéficiaire ou de collusion de celui-ci avec le donneur d’ordre » (the guarantor is not bound in the event of manifest abuse or fraud by the beneficiary or collusion between the beneficiary and the party that ordered the guarantee). Your first steps are therefore practical: read the guarantee wording today, compare the call with it, gather the documents that show an obvious lack of right, and ask a French judge for an order forbidding payment before the bank pays. If the bank has already paid, the dispute moves to recovering the money from the customer. This article describes these steps in general terms; it does not assess any particular guarantee, bank or customer.
I. Before the bank pays: can a French first-demand guarantee still be stopped?
A. What does your guarantee actually say: is it truly autonomous, under which law, and was the call valid?
French law knows three personal guarantees, and the label on the document does not settle which one you gave. The Civil Code lists them: « Les sûretés personnelles régies par le présent titre sont le cautionnement, la garantie autonome et la lettre d’intention » (the personal guarantees governed by this title are the suretyship, the autonomous guarantee and the letter of intent) (article 2287-1 of the Civil Code). The autonomous guarantee is defined as « l’engagement par lequel le garant s’oblige, en considération d’une obligation souscrite par un tiers, à verser une somme soit à première demande, soit suivant des modalités convenues » (the undertaking by which the guarantor binds itself, in consideration of an obligation entered into by a third party, to pay a sum either on first demand or according to agreed terms) (article 2321 of the Civil Code). A suretyship (cautionnement) is different: « Le cautionnement est le contrat par lequel une caution s’oblige envers le créancier à payer la dette du débiteur en cas de défaillance de celui-ci » (suretyship is the contract by which a surety binds itself to the creditor to pay the debtor’s debt if the debtor fails to pay) (article 2288 of the Civil Code). The difference matters to you because a surety can, as a rule, rely on the defences of the underlying contract, whereas the guarantor of an autonomous guarantee cannot.
The Cour de cassation, France’s highest court for civil and commercial matters, looks at the substance. In a case where two companies had signed a document headed « garantie à première demande », undertaking to pay on request within the limit of the instalments a third company failed to pay under a court-approved rescue plan, it explained that under article 2321 « le garant s’oblige à payer la dette d’un tiers de manière autonome au regard du contrat de base et que son obligation a un objet distinct de celle du débiteur principal » (the guarantor undertakes to pay a third party’s debt autonomously from the underlying contract and its obligation has an object distinct from that of the principal debtor). Because the extent of the undertaking depended on whether the debtor honoured its own commitments, the Court held that it had the same object as the debtor’s obligation and quashed the decision that had treated it as an autonomous guarantee (Cass. com., 13 March 2024, No. 22-15.438). If your guarantee is drafted as a promise to pay whatever you owe under the contract, rather than a fixed sum on request, it may in fact be a suretyship, and the defences of your contract come back into play.
Do not count on that argument too quickly. The Paris Court of Appeal (cour d’appel de Paris) recently refused it for guarantees issued for the construction of a power plant in Niger, noting that « une simple référence au contrat de base ne saurait exclure la qualification de garantie autonome » (a mere reference to the underlying contract cannot exclude the classification as an autonomous guarantee). The guarantees there allowed the beneficiary to claim any sum up to a fixed ceiling on a simple statement of breach, expressly referred to article 2321 and to the ICC Uniform Rules for Demand Guarantees (URDG 758), and the court held that their classification as autonomous guarantees was not seriously disputable (CA Paris, 28 May 2026, No. 25/13362). Most bank guarantees used in export and construction contracts follow that model.
The second question is which law governs the guarantee. Article 2321 is French law; it applies when the guarantee is governed by French law, which is common when a French bank issues it to a French beneficiary. A guarantee issued by a bank in another country may name another law. In a case concerning a completion guarantee equal to 10% of a subcontract on a building project, the Paris Court of Appeal began by noting: « Il résulte des stipulations de la garantie litigieuse que celle-ci est régie par le droit monégasque » (it follows from the terms of the disputed guarantee that it is governed by Monaco law), and it then applied the Monaco provision, which is worded like article 2321 (CA Paris, 12 December 2025, No. 25/03466). Look for the governing-law and jurisdiction clauses in the guarantee itself, not only in your sales contract: the two documents are separate and may point to different laws and courts. If the guarantee is governed by English, New York or Indian law, the test for stopping payment is the one set by that law, and the advice you need is a lawyer of that system.
Reference to the ICC rules does not displace French law when French law has been chosen. In a dispute involving a contractor on a road project in Gabon and guarantees governed by French law and by URDG 758, the Paris Court of Appeal refused to apply the United Nations Convention on Independent Guarantees and Stand-by Letters of Credit, observing that « cette Convention, non ratifiée par la France, ne peut être appliquée » (this Convention, not ratified by France, cannot be applied), and held that the ICC rules invoked did not override article 2321, which the parties had expressly chosen (CA Paris, 29 January 2026, No. 25/18950).
The third question is whether the call itself matches the guarantee. Autonomy protects the beneficiary against defences drawn from the contract; it does not allow the beneficiary to claim outside what the bank promised. The Cour de cassation approved a court of appeal that had stated that « la garantie autonome ne peut être appelée en dehors de l’objet en considération duquel elle a été consentie » (an autonomous guarantee cannot be called outside the purpose for which it was given), and that, when the guarantor argues that the call does not match that purpose, the contract in consideration of which the guarantee was given may be examined alongside the guarantee (Cass. com., 1 April 2026, No. 24-13.364). That case concerned a completion guarantee of EUR 47 million given in a concession contract, and the argument failed on the facts, but the principle is now set out in a decision published in the Court’s bulletin.
The Paris Court of Appeal applied the same logic in favour of a distributor. A bank guarantee covered a distribution contract signed in 2022; the parties later signed a new contract in 2024, and the beneficiary called the guarantee for sums owed under the new contract while presenting the call as relating to the old one. The court held that « Le seul fait de faire référence, à tort, à l’inexécution du seul contrat visé par la lettre d’engagement afin de mobiliser la garantie alors que l’inexécution concerne un autre contrat, non mentionné dans l’acte de garantie, est constitutif d’un appel abusif de ladite garantie » (merely referring, wrongly, to the non-performance of the only contract mentioned in the guarantee in order to call it, when the non-performance concerns another contract not mentioned in the guarantee, constitutes an abusive call). It added that autonomy « ne peut avoir pour conséquence de modifier l’étendue ou l’objet de la garantie tels qu’ils ont été déterminés par l’acte de garantie lui-même » (cannot have the effect of changing the extent or the purpose of the guarantee as fixed by the guarantee itself), and ordered the bank not to pay pending the decision on the merits (CA Paris, 26 March 2026, No. 25/19167). The same decision shows the bank’s own role: the bank had first rejected the call because, as it pointed out, the demand was not dated and was not signed by the authorised persons.
In practice, ask your bank immediately for a copy of the demand and of every document attached to it, and check it line by line against the guarantee: the amount, the currency, the reference of the contract, the statement of breach the guarantee requires, the signatories, the place of presentation and the expiry date. Guarantees often give the bank a very short time to pay. The guarantee examined in the Monaco-law case required the bank « à payer en vertu des présentes dans un délai de 7 jours à compter de la notification de l’entrepreneur principal » (to pay under the guarantee within seven days of the main contractor’s notification) (CA Paris, 12 December 2025, No. 25/03466). Read your own guarantee to know the period that applies to you; that period, not the pace of a negotiation with your customer, decides how long you have.
Keep one distinction in mind. A defect of form in the demand is a matter for the bank, which may reject a non-compliant call. It is not, by itself, a reason for a judge to forbid payment: in the Gabon road case, the Paris Court of Appeal held that « une irrégularité formelle de l’appel des garanties est sans lien avec le caractère abusif de celui-ci, seul élément susceptible de faire échec au paiement » (a formal irregularity in the call of the guarantees has no bearing on whether it is abusive, which is the only element capable of preventing payment) (CA Paris, 29 January 2026, No. 25/18950). Point out any defect to the bank in writing, and build your court application on abuse or fraud. Because each of these steps depends on the wording of your guarantee and of your contract, many foreign companies ask a business lawyer in Paris to read both documents with them the day the call arrives.
B. Manifest abuse or fraud: what French judges accept as a reason to block payment
The only ground on which a French judge will forbid a bank to pay an autonomous guarantee governed by French law is the one in article 2321: manifest abuse or fraud by the beneficiary, or collusion between the beneficiary and the party that ordered the guarantee (article 2321 of the Civil Code). The word manifest is decisive. The Paris Court of Appeal put it this way: « Il ne suffit pas que l’abus, la fraude ou la mauvaise foi puissent être démontrés, il faut en outre qu’ils soient manifestes » (it is not enough that the abuse, fraud or bad faith can be shown; they must also be manifest). It continued: « L’appel à la garantie est manifestement abusif en raison de la mauvaise foi évidente de l’appelant, c’est à dire sa conscience de l’absence de droit » (the call is manifestly abusive because of the obvious bad faith of the party calling it, that is, its awareness that it has no right), and « Cette absence de droit peut être caractérisée lorsque l’inexécution relève, à l’évidence, du fait de celui qui invoque la garantie ou d’une cause étrangère aux parties » (this lack of right may be established where the non-performance obviously results from the conduct of the party calling the guarantee or from a cause external to the parties) (CA Paris, 28 May 2026, No. 25/13362).
That decision is a useful example for exporters. A consortium building a hybrid solar and diesel power plant in Niger had terminated the contract for force majeure after the coup d’état of 26 July 2023. Seven months later, the project owner called the performance guarantees and the advance payment guarantees issued by a bank registered in Paris; the bank refused to pay, and the owner asked the emergency judge of the Paris commercial court to order payment. The court found that the termination resulted obviously from a cause external to the parties and that the call of the performance guarantees was tainted by manifest bad faith; it also observed that the owner did not even claim to have referred the question of who was responsible for the termination to the competent court. As for the advance payment guarantees, the activity reports showed that the advances had financed the real progress of the project, and the court concluded that these guarantees too had been called in a manifestly abusive way, the beneficiary having no right to claim repayment, « ce qu’elle ne pouvait ignorer » (which it could not have been unaware of). The request for payment was rejected (CA Paris, 28 May 2026, No. 25/13362). The lesson is that the evidence must be documentary and obvious: dated reports, certificates of progress, acceptance documents, the customer’s own letters.
The other side of the line is just as clear, and it is where most applications fail. A genuine dispute about performance does not make a call abusive. In the Monaco-law case, the subcontractor argued that only 460 tiles out of 15,000 sounded hollow and that the main contractor had decided on a complete replacement without a joint survey. The court answered that it was not for it to rule on the alleged non-conformity or on whether the remedial works were justified, and that such disputes « sont sans effet sur l’exécution par le garant de son engagement unilatéral dès lors qu’il n’est pas démontré d’abus manifeste » (have no effect on the guarantor’s performance of its unilateral undertaking as long as no manifest abuse is shown). Since part of the work, even a small part, showed an anomaly that could reveal defective performance, the call was not abusive (CA Paris, 12 December 2025, No. 25/03466). The court also held that terminating the underlying contract did not, by itself, prevent the guarantee from being called afterwards.
The Gabon road case shows the cost of a weak file. The contractor had given an advance payment bond and a performance bond, each capped at EUR 11.3 million, for a road project. It argued that the delays came from the employer, that the advance had been repaid in kind by work done, and that a government minister had asked the employer to withdraw the call. The court relied on an independent engineer’s report listing delays and non-conformities, held that the call was linked to the breaches alleged against the contractor, and concluded: « Dans ces circonstances, l’appel des garanties n’est pas manifestement abusif » (in these circumstances, the call of the guarantees is not manifestly abusive). It also refused to order the sums to be held in escrow while the arbitration was pending, stating that the alleged risk of not recovering the money from the beneficiary « est sans incidence sur l’exécution de l’obligation du garant » (has no bearing on the guarantor’s performance of its obligation). The contractor was ordered to pay EUR 10,000 for the first instance and EUR 40,000 on appeal towards the other side’s legal costs (CA Paris, 29 January 2026, No. 25/18950).
The Cour de cassation applies the same standard. In the EUR 47 million case, the guarantor argued that the beneficiary had abandoned the project the guarantee was meant to secure and that the alleged delays were not real. The court of appeal had noted that the validity of the forfeiture of the concession was being challenged before the administrative court, which alone could assess whether the beneficiary had committed a manifest fault, and the Cour de cassation approved it for finding that it had not been shown that « la garantie avait été appelée en dehors des prévisions contractuelles convenues entre le garant et le bénéficiaire, ou que son appel procédait d’une fraude ou d’un abus manifestes » (the guarantee had been called outside the contractual terms agreed between the guarantor and the beneficiary, or that its call resulted from manifest fraud or abuse) (Cass. com., 1 April 2026, No. 24-13.364). An older decision makes the same point in the international context: grievances about how the contract was performed, even if established, « n’étaient pas susceptibles d’apporter la preuve d’une fraude ou d’un abus manifeste dans l’appel de la contre-garantie » (were not capable of proving manifest fraud or abuse in the call of the counter-guarantee) (Cass. com., 19 February 1991, No. 89-19.637).
From these decisions, the situations in which French judges have accepted a request to block payment share a feature: the absence of right appears from the documents without a trial on the merits. The call relates to a contract or an obligation the guarantee does not cover; the beneficiary itself caused the non-performance or an external event obviously did; the advance the guarantee secures was demonstrably used for the project. Situations in which they refused share the opposite feature: the parties disagree on delays, defects or responsibility, and the answer requires an expert, an arbitrator or a judge of the merits. Before you go to court, sort your arguments into these two categories honestly. A file built only on the second category exposes you to an adverse costs order without stopping the payment.
II. Going to court in France, and recovering the money if the bank has paid
A. The emergency route: which French judge, which procedure, and what about arbitration and counter-guarantees?
Guarantee disputes between companies are usually brought before the president of the commercial court (président du tribunal de commerce), acting as emergency judge (juge des référés); in Paris, the decisions cited in this article refer to the court as the tribunal des activités économiques de Paris. The Code of Civil Procedure gives that judge two powers. First: « Dans tous les cas d’urgence, le président du tribunal de commerce peut, dans les limites de la compétence du tribunal, ordonner en référé toutes les mesures qui ne se heurtent à aucune contestation sérieuse ou que justifie l’existence d’un différend » (in all cases of urgency, the president of the commercial court may, within the limits of the court’s jurisdiction, order in summary proceedings any measures that do not meet any serious challenge or that are justified by the existence of a dispute) (article 872 of the Code of Civil Procedure). Second, he may, « même en présence d’une contestation sérieuse, prescrire en référé les mesures conservatoires ou de remise en état qui s’imposent, soit pour prévenir un dommage imminent, soit pour faire cesser un trouble manifestement illicite » (even where there is a serious challenge, order the protective or restorative measures required either to prevent imminent damage or to put an end to a manifestly unlawful disturbance) (article 873 of the Code of Civil Procedure). The order you seek is an injunction forbidding the bank to pay (interdiction de payer), usually until the court or the arbitral tribunal deciding the merits has ruled.
Because the bank’s payment period may be short, ordinary summary proceedings may be too slow. Two faster routes exist. The emergency judge may allow you to summon the other parties for a fixed hour: « Si, néanmoins, le cas requiert célérité, le juge des référés peut permettre d’assigner, à heure indiquée, même les jours fériés ou chômés » (if the case nevertheless requires speed, the summary judge may allow a summons for a stated hour, even on public holidays or non-working days) (article 485 of the Code of Civil Procedure). The subcontractor in the Monaco-law case used this route, having been authorised to summon the bank for a stated hour (CA Paris, 12 December 2025, No. 25/03466). When even that is too slow, you may apply without notice to the other side (ordonnance sur requête): « Le président peut ordonner sur requête, dans les limites de la compétence du tribunal, toutes mesures urgentes lorsque les circonstances exigent qu’elles ne soient pas prises contradictoirement » (the president may order on application, within the limits of the court’s jurisdiction, any urgent measures where the circumstances require that they not be taken in the presence of both parties) (article 875 of the Code of Civil Procedure). In the distribution case, the bank refused the second call precisely because it had received a prohibition to pay from the judge of applications of the Paris court (CA Paris, 26 March 2026, No. 25/19167).
An order made without notice is provisional by nature: the code defines it as « une décision provisoire rendue non contradictoirement dans les cas où le requérant est fondé à ne pas appeler de partie adverse » (a provisional decision made without hearing the other side in cases where the applicant is justified in not summoning an opposing party) (article 493 of the Code of Civil Procedure). The beneficiary will challenge it: « S’il est fait droit à la requête, tout intéressé peut en référer au juge qui a rendu l’ordonnance » (if the application is granted, any interested party may refer the matter back to the judge who made the order) (article 496 of the Code of Civil Procedure), and « Le juge a la faculté de modifier ou de rétracter son ordonnance, même si le juge du fond est saisi de l’affaire » (the judge may modify or withdraw the order, even if the judge of the merits has been seized) (article 497 of the Code of Civil Procedure). An application without notice must also be complete and fair. In the Gabon road case, the beneficiary accused the contractor of having omitted many documents when obtaining two such orders; the court rejected that objection to admissibility, but the contractor lost on the merits (CA Paris, 29 January 2026, No. 25/18950). Present the documents that do not help you as well as those that do.
Summary orders can be appealed: an emergency order « peut être frappée d’appel » (may be appealed) unless it was made by the first president of the court of appeal or in last resort, and « Le délai d’appel ou d’opposition est de quinze jours » (the time limit for an appeal or an objection is fifteen days) (article 490 of the Code of Civil Procedure). If your application without notice is refused, the code provides that « appel peut être interjeté » (an appeal may be lodged) unless the order was made by the first president of the court of appeal, and that « Le délai d’appel est de quinze jours » (the time limit for appeal is fifteen days) (article 496 of the Code of Civil Procedure). The decisions cited in this article show that the stakes of these appeals are high in both directions: the distributor obtained an injunction on appeal after losing at first instance (CA Paris, 26 March 2026, No. 25/19167), while the contractor in the Gabon road case lost at both levels (CA Paris, 29 January 2026, No. 25/18950).
Many international supply and construction contracts provide for arbitration. That clause does not, by itself, close the door of the French emergency judge. The Code of Civil Procedure states that « L’existence d’une convention d’arbitrage ne fait pas obstacle, tant que le tribunal arbitral n’est pas constitué, à ce qu’une partie saisisse une juridiction de l’Etat aux fins d’obtenir une mesure d’instruction ou une mesure provisoire ou conservatoire » (the existence of an arbitration agreement does not prevent a party, as long as the arbitral tribunal has not been constituted, from applying to a State court for an investigative, provisional or protective measure) (article 1449 of the Code of Civil Procedure), and that rule is applied to international arbitration by the list of articles in article 1506 of the Code of Civil Procedure, which Légifrance shows as in force with a deferred repeal on 1 January 2027. More importantly for guarantees, the arbitration clause is usually in your contract with the customer, not in the guarantee. In the Gabon road case, where the arbitral tribunal had already been constituted, the Paris Court of Appeal held that « Les arbitres ne pouvant étendre leur compétence à un contrat autre que celui contenant la clause d’arbitrage, ne pourront connaître du litige relatif aux garanties à première demande dont l’objet est distinct du contrat sous-jacent soumis à leur appréciation » (since the arbitrators cannot extend their jurisdiction to a contract other than the one containing the arbitration clause, they cannot hear the dispute concerning the first-demand guarantees, whose subject matter is distinct from the underlying contract submitted to them), and it accepted the jurisdiction of the Paris emergency judge on the basis of the jurisdiction clause in the guarantees (CA Paris, 29 January 2026, No. 25/18950).
Many foreign suppliers do not give a guarantee directly. Their French customer insists on a guarantee from a French bank, which issues it (first-rank guarantee) against a counter-guarantee from the supplier’s own bank. That chain changes the strategy. Each undertaking stands alone: the Cour de cassation has held that « les engagements de garantie et de contre-garantie à première demande sont indépendants les uns des autres » (first-demand guarantees and counter-guarantees are independent of one another) (Cass. com., 8 November 1994, No. 92-14.542). Once the French bank has paid the French customer, blocking the counter-guarantee is much harder: « le caractère manifestement abusif de l’appel de la contre-garantie ne peut résulter du seul caractère manifestement abusif de l’appel de la garantie de premier rang, mais suppose de démontrer l’existence, au moment de l’appel de la contre-garantie, d’une collusion entre le garant de premier rang, bénéficiaire de la contre-garantie, et le bénéficiaire de la garantie de premier rang » (the manifestly abusive nature of the call of the counter-guarantee cannot result solely from the manifestly abusive nature of the call of the first-rank guarantee, but requires proof of collusion, at the time of the call of the counter-guarantee, between the first-rank guarantor and the beneficiary of the first-rank guarantee) (Cass. com., 3 May 2016, No. 14-28.962). The useful target is therefore the first payment, by the French bank to the French customer, and the French court is the natural place to seek it.
French courts have accepted jurisdiction over emergency measures concerning guarantees issued by French banks even where the other parties were abroad. In a case brought by a French contractor concerning a counter-guarantee issued by a French bank in favour of a Kenyan bank, the Paris Court of Appeal relied on article 35 of the European Union’s Brussels I bis Regulation, on provisional measures, and held that the connection with France was obvious, « la contre-garantie dont le non-paiement est sollicité émanant d’une banque française » (the counter-guarantee whose non-payment was sought having been issued by a French bank). The same decision shows the limit of the counter-guarantee route: the court stayed its ruling because, in its words, « pour que son appel à la contre-garantie soit jugé abusif ou frauduleux, il faut que la banque garante de premier rang ait eu connaissance du caractère abusif de l’appel de la garantie de premier rang » (for the first-rank guarantor’s call of the counter-guarantee to be held abusive or fraudulent, the first-rank guarantor must have known that the call of the first-rank guarantee was abusive), a question pending before the Kenyan court (CA Paris, 15 December 2022, No. 22/08300). If your structure is the mirror image of that one, with the French bank as first-rank guarantor and the French customer as beneficiary, the dispute over the first payment is entirely in France.
B. If the bank has paid: recovering the money from the French customer
Payment of the guarantee does not settle who was right under the contract. The Cour de cassation has stated: « Après paiement d’une garantie (ou contre-garantie) autonome, le donneur d’ordre est recevable à exercer un recours contre le bénéficiaire pour faire juger que celui-ci a perçu indûment le montant de la garantie, sans avoir à justifier du remboursement préalable du garant » (after payment of an autonomous guarantee or counter-guarantee, the party that ordered the guarantee may bring a claim against the beneficiary to have it ruled that the beneficiary received the amount without being entitled to it, without having to prove that it first reimbursed the guarantor). The Court approved the reasoning that this party must establish that the beneficiary was not entitled to the payment, « par la preuve de l’exécution de ses propres obligations contractuelles, ou par celle de l’imputabilité de l’inexécution du contrat à la faute du cocontractant bénéficiaire de la garantie » (by proving that it performed its own contractual obligations, or that the non-performance of the contract was due to the fault of the other contracting party, the beneficiary of the guarantee). In that case, the guarantee had been given by a separate company for the obligations of the operator of a hotel business, and the operator, treated as the party that ordered the guarantee, was allowed to claim the sums back from the beneficiary (Cass. com., 14 June 2023, No. 21-23.864).
This is the main difference between the two stages. Before payment, you must show manifest abuse or fraud. After payment, you return to the ordinary questions of the contract: did you perform, did the customer cause the failure, was the amount due. The general rule of restitution in the Civil Code supports that claim: « Celui qui reçoit par erreur ou sciemment ce qui ne lui est pas dû doit le restituer à celui de qui il l’a indûment reçu » (anyone who receives, by mistake or knowingly, what is not owed to them must return it to the person from whom it was unduly received) (article 1302-1 of the Civil Code). The claim is brought before the court or the arbitral tribunal designated by your contract, which is where the evidence you gathered for the emergency stage, the reports, acceptance records and correspondence, will be used again in full.
The difficulty for a foreign company is often less the law than the customer’s solvency once it has received the money. French law allows a creditor to freeze assets before obtaining judgment: « Toute personne dont la créance paraît fondée en son principe peut solliciter du juge l’autorisation de pratiquer une mesure conservatoire sur les biens de son débiteur, sans commandement préalable, si elle justifie de circonstances susceptibles d’en menacer le recouvrement » (anyone whose claim appears well founded in principle may ask the judge for permission to carry out a protective measure on the debtor’s assets, without prior formal demand, if it shows circumstances likely to threaten its recovery) (article L511-1 of the Code of Civil Enforcement Procedures). The application is made by request and, outside the cases where a court decision or certain instruments already exist, prior permission from the judge is required (article R511-1 of the Code of Civil Enforcement Procedures; article L511-2 of the Code of Civil Enforcement Procedures). Whether your restitution claim appears well founded in principle will depend on the same documents as the merits.
Your relationship with your own bank also deserves attention. After paying, the issuing bank will normally debit your account or call on your counter-indemnity, and the decision of 14 June 2023 confirms that your claim against the beneficiary does not depend on reimbursing the bank first (Cass. com., 14 June 2023, No. 21-23.864). Your written objection to the bank at the time of the call can matter later. In a case concerning a guarantee issued for the supply of equipment to a foreign buyer, the principal had firmly opposed the call as abusive, and the bank had refrained from paying; when the bank was forced, four years later, to pay through a set-off made by another bank, the Cour de cassation upheld the decision that the principal owed no reimbursement, since « l’appel abusif de la garantie ne pouvait justifier le paiement forcé effectué quatre ans plus tard » (the abusive call of the guarantee could not justify the forced payment made four years later) (Cass. com., 6 February 1990, No. 88-18.481). That case turned on its own facts, but it illustrates why the objection you send to your bank on the day of the call should be precise, dated and supported by documents.
Finally, think about the next guarantee while you deal with this one. The disputes described above were decided on the wording of the guarantees: the contract they referred to, the statement the beneficiary had to make, the governing law, the jurisdiction clause and the expiry date. A guarantee that names the exact contract it secures, requires a statement identifying the breach, sets a firm expiry date and chooses a law and a court you can work with gives you arguments that a generic text does not. The Civil Code itself adds that « Sauf convention contraire, cette sûreté ne suit pas l’obligation garantie » (unless otherwise agreed, this guarantee does not follow the guaranteed obligation) (article 2321 of the Civil Code), which is one more reason to state in the guarantee itself what happens if the contract is assigned, amended or replaced, as the distribution case showed when a new contract was signed without the guarantee being extended to it (CA Paris, 26 March 2026, No. 25/19167).
Conclusion
A call on a first-demand guarantee by a French customer is designed to be paid, and French courts protect that design. The Civil Code bars the bank from raising defences drawn from your contract, and the recent decisions of the Paris Court of Appeal and the Cour de cassation show that a disagreement about delays, defects or responsibility, however sincere, does not stop the payment. What can stop it is narrower: a call that falls outside the guarantee, a guarantee that is in truth a suretyship, or an absence of right so obvious that the documents prove it without a trial, as in the cases where the guarantee was used for another contract or where the failure obviously came from an external event. Those arguments are made quickly, before the French emergency judge, by summons for a fixed hour or by application without notice, with a complete and honest file, and with the guarantee’s own law and jurisdiction clause checked first. If the bank pays, the contract dispute is not lost: the money can be claimed back from the customer by proving your own performance or the customer’s fault, and protective measures can secure that claim. In every scenario, the decisive material is the same: the exact wording of the guarantee, the call and the documents that show what really happened on the project.