Abandoned building work lawyer in Paris: formal notice, termination and remedies
A tradesman who stops turning up, a contractor who leaves the site after collecting deposits, a defaulting builder of a detached house (constructeur de maison individuelle): as abandoned building work lawyers, the firm assists project owners (maîtres de l'ouvrage), from the formal notice to completion by another contractor, and defends contractors accused of abandoning a site. Everything starts with a valid formal notice and a precise record of the work actually carried out.
The firm can be reached 24/7. Before handing over the completion of the work to another contractor, serve formal notice on the defaulting contractor: except in an emergency, termination by notification requires prior formal notice (Article 1226 of the French Civil Code, Code civil), and building damage insurance (assurance dommages-ouvrage) only covers damage arising before acceptance of the works after a formal notice that has gone unheeded, followed by termination of the contract (Article L. 242-1 of the French Insurance Code, Code des assurances).
4,9/5
Average Google review rating270 reviews
I received high-quality support from this criminal lawyer. His professionalism, his complete command of the case and his constant involvement at every stage of the proceedings deserve to be highlighted. Communication was clear, structured and responsive, with precise advice suited to my situation. I recommend this lawyer to anyone looking for a rigorous and effective criminal defence.
Mr Kohen handled my criminal case. I am very satisfied with the work he did and I recommend him without any hesitation.
Excellent criminal defence lawyer, he got me out of trouble in a protection order case brought abusively by my ex
Very satisfied with the outcome of my defence before the court. All the best
Hassan Kohen is a young, seasoned and highly competent lawyer. He is an excellent listener, shows great empathy and strong human sensitivity. Available and responsive, he has complete mastery of his profession.
I had a very good experience with Hassan Kohen. He took the time to listen to me carefully and fully understand my situation. He is a lawyer who gives sound advice, caring and available, who knows how to point his clients in the right direction. I recommend him without hesitation to anyone looking for an attentive and competent professional.
Mr Kohen advised and supported us well. I thank him for everything he has done.
Paris Bar
Emergencies 24/7
Preliminary case review
Send your documents. Receive an analysis.
Hassan Kohen
Lawyer (avocat) at the Paris Bar: building and construction contracts, abandoned building work, termination of construction contracts and non-performance disputes.
Official profile in the directory of French lawyers (CNB) · 4.9/5 on Google (270 reviews)
Page updated on 31 October 2026.
Quick answer
A contractor who stops work on site without a legitimate reason fails to perform its obligation. The project owner may then seek enforced performance, obtain a price reduction, bring about termination of the contract and claim damages (Article 1217 of the French Civil Code). After formal notice, the owner may also have the work carried out by a third party, within a reasonable time and at a reasonable cost, and claim the cost from the defaulting contractor (Article 1222). Termination by notification is at the owner's own risk, after a formal notice that expressly states this consequence (Article 1226). Under a contract to build a detached house (contrat de construction de maison individuelle), the completion guarantor takes over (Article L. 231-6 of the French Construction and Housing Code, Code de la construction et de l'habitation); before acceptance of the works, building damage insurance only applies after an unheeded formal notice and termination of the contract (Article L. 242-1 of the French Insurance Code). The judge hearing urgent applications (juge des référés) may order an expert assessment (Article 145 of the French Code of Civil Procedure) and award an interim payment where the obligation is not seriously disputable (Article 835). The contractor concerned may, for its part, rely on the project owner's sufficiently serious non-performance (Article 1219 of the French Civil Code). Kohen Avocats, in Paris 16th arrondissement, acts for project owners and for contractors alike. Contact the firm on +33 6 89 11 34 45.
Work stopped on site, deposits paid, a termination notice received?
Understanding your situation
Abandoned building work in Paris, explained
The party towards whom the obligation has not been performed may, among other things, seek enforced performance, obtain a price reduction, bring about termination of the contract and claim damages (Article 1217 of the French Civil Code). How to recognise and prove abandonment of a building site (abandon de chantier), which route to choose, what happens to deposits, which guarantees to call on, and how the contractor accused of abandonment defends itself.
Key points
Recognising abandonment, then proving it
The texts cited on this page do not define abandonment of a building site: the judge assesses the facts. Four elements make up the case file.
Non-performance: work stopped, staff and equipment removed, reminders left unanswered. The party towards whom the obligation has not been performed, or has been performed imperfectly, has the remedies set out in Article 1217 of the French Civil Code.
No force majeure: this requires an event beyond the debtor's control, which could not reasonably have been foreseen when the contract was concluded and whose effects cannot be avoided by appropriate measures. A temporary impediment only suspends performance, unless the resulting delay justifies termination (Article 1218).
A formal notice: unless non-performance is final, damages are only due after a formal notice to perform within a reasonable time (Article 1231), and termination by notification requires, except in an emergency, prior formal notice (Article 1226).
A precise record of the site: a report drawn up by a court commissioner (commissaire de justice), dated photographs, site meeting minutes, written exchanges. It establishes what has been done, what remains to be done and what has been paid.
None of the texts cited here sets a number of days beyond which a halt in the work becomes abandonment. Some contracts define it themselves: in a case decided by the Paris Court of Appeal, the special administrative terms and conditions of the contract deemed it abandonment where the volume of work carried out in the month preceding the formal notice was less than half the volume planned. The court held that the contractor “did not deploy the necessary staff on the site to carry out the work within the contractually agreed time limits” (our translation), found that the termination clause had taken effect and ordered the contractor to pay €19,140 incl. VAT in late-completion penalties (CA Paris, pôle 4, ch. 6, 2 December 2022, No. 20/11445). In that case, successive reports by a court commissioner showed that no progress had been made between two dates.
The time limit given in the formal notice must be reasonable in light of what is requested. For specific remedial works, the Grenoble Court of Appeal held that “The time limit of 8 days granted, in view of the requests, appears reasonable” (our translation) (CA Grenoble, chambre civile section B, 2 June 2026, No. 24/03842). See also our articles on the tradesman who does not finish the work and on photos and messages as evidence of abandonment.
Courses of action
Demanding resumption, having another contractor finish, or ending the contract
Each route has its own conditions, and compatible remedies can be combined (Article 1217).
Enforced performance
After formal notice, the project owner may seek performance in kind, unless this is impossible or there is a manifest disproportion between its cost to the debtor in good faith and its benefit to the creditor (Article 1221 of the French Civil Code).
Performance by a third party
After formal notice, the owner may have the obligation performed, “within a reasonable time and at a reasonable cost” (our translation), and then claim reimbursement from the debtor, or ask the court to order the debtor to advance the necessary sums (Article 1222).
Price reduction
In the event of imperfect performance, after formal notice, a project owner who has not yet paid in full may give notice of a proportionate price reduction; if the owner has already paid, it asks the judge for the reduction failing agreement (Article 1223).
Termination clause
If the contract contains one, termination requires an unheeded formal notice, unless the contract provides that it results from the mere fact of non-performance, and this formal notice only takes effect if it expressly refers to the clause (Article 1225).
Termination by notification
The creditor may terminate the contract at its own risk. Except in an emergency, it must first give the debtor formal notice to perform within a reasonable time, stating that failing this it will be entitled to terminate the contract, and then give notice of termination and the reasons for it. If the debtor challenges this before the court, the creditor must prove the seriousness of the non-performance (Article 1226).
Judicial termination
Termination may always be sought in court (Article 1227). The judge may record or order termination, order performance while granting additional time, or award damages only (Article 1228).
The seriousness of the breach may justify ending the contract, at the risk of the party that decides to do so. According to the Cour de cassation, “the seriousness of the conduct of one party to a contract may justify the other party terminating it unilaterally at its own risk” (our translation) (Cass. 3e civ., 25 June 2026, No. 24-18.064). Handed down on the basis of former Article 1184 of the French Civil Code and Article 1794, the same judgment adds that the project owner's right to terminate a fixed-price contract unilaterally “does not deprive the owner of the possibility of terminating the contract under the conditions of general law” (our translation) (Cass. 3e civ., 25 June 2026, No. 24-18.064). It thus quashes the judgment that had compensated the contractor's lost profit without examining the breaches relied on. For contracts governed by the law in force since 1 October 2016, the procedure for termination by notification is that of Article 1226.
Form matters. The Versailles Court of Appeal held to be abusive the termination decided, on unproven grievances, by a project owner who had “abruptly put an end to the site work in progress, moreover without the prior formal notice required by law” (our translation), and ordered the owner to compensate the contractor (CA Versailles, chambre civile 1-4, 21 October 2024, No. 22/07414). Late-completion penalties provided for in the contract can be combined with the other remedies, but for the loss caused by the delay the judge may award neither more nor less than the agreed sum, except to reduce or increase, even of its own motion, a penalty that is manifestly excessive or derisory, or to reduce it in proportion to the benefit of partial performance; unless non-performance is final, the penalty is only incurred after formal notice (Article 1231-5).
The money on site
Deposits, completion by a third party and compensation
What can be recovered depends on what has been done, paid and proven on the day the contract is ended.
Termination brings the contract to an end, on the date provided for by the termination clause, on receipt of the notification, or on the date set by the judge or, failing that, on the day of the writ of summons (Article 1229 of the French Civil Code).
Where the services have been of use progressively as the contract was performed, there is no restitution for the period before the last service that did not receive its counterpart: termination then takes effect only for the future (résiliation) (Article 1229).
Restitution of a service takes place by value, assessed on the date on which it was provided (Article 1352-8). Deposits exceeding the value of the work carried out can be claimed back.
The cost of completion by another contractor can be claimed from the defaulting contractor (Article 1222), together with the damages due for non-performance or delay (Article 1231-1).
The judge hearing urgent applications may award an interim payment where the existence of the obligation is not seriously disputable (Article 835 of the French Code of Civil Procedure).
A contractor that has left the site keeps the right to be paid for what it has done. The Rennes Court of Appeal, which upheld termination against a contractor that had left without reason, held that it “is entitled to claim payment for the work actually carried out, provided it proves its extent” (our translation) (CA Rennes, 4e ch., 17 September 2026, No. 25/02248). Conversely, a project owner claiming the additional cost must be able to establish the exact state of the site on the day the contract was ended: having failed to have the work done recorded in the presence of both parties, as the general terms of the contract required, a property developer “fails to prove an additional cost of completion at the contractor's expense” (our translation) and saw its payment claims dismissed, even though the abandonment was attributable to the contractor (CA Paris, pôle 4, ch. 5, 6 November 2024, No. 21/17165).
Acceptance of a completed lot remains possible when the site as a whole is not completed. It takes place at the request of the more diligent party, amicably or by court order (Article 1792-6), and the Cour de cassation holds that “completion of the entire structure is not a condition for taking possession of a lot and for its acceptance” (our translation) (Cass. 3e civ., 30 January 2019, No. 18-10.197). Defects that appear afterwards fall under the guarantee of perfect completion and the ten-year builder's liability (garantie décennale), or, for the others, under contractual liability (Article 1792-4-3), covered on our page construction law lawyer.
Before acceptance, the contractual liability action against the contractor is time-barred after five years (Article 2224). The Cour de cassation so held, recalling that “only an initiative by the creditor of the obligation can interrupt the limitation period” (our translation): urgent proceedings brought by others did not benefit the project owner, whose claims were declared inadmissible (Cass. 3e civ., 19 March 2020, No. 19-13.459). After acceptance, liability actions against builders are time-barred ten years after acceptance, apart from the actions governed by Articles 1792-3, 1792-4-1 and 1792-4-2 (Article 1792-4-3). See our article on the deposit paid to a tradesman who abandons the site.
The guarantees
Completion guarantee, building damage insurance, insolvency proceedings
When the contractor will not pay, you need to know who else is liable, and on what conditions.
Detached house
Under a contract to build a detached house, whose rules are mandatory public policy (Article L. 230-1 of the French Construction and Housing Code), the completion guarantee (garantie de livraison) covers the project owner, from the opening of the site, against non-performance or defective performance of the planned work, at the agreed price and within the agreed time (Article L. 231-6).
What the guarantor pays
If the builder defaults, the guarantor bears the price overruns needed for completion, subject to an excess of no more than 5% of the agreed price, the consequences of an early payment or a price supplement, and the fixed late-delivery penalties beyond thirty days (Article L. 231-6, I). These penalties may not be lower than 1/3,000 of the price per day of delay (Article R. 231-14).
How it works
Where the delivery deadline is not met, the guarantor, who notes this or is informed of it by the project owner, gives the builder formal notice to deliver or to carry out the work; fifteen days after an unheeded formal notice, it appoints the person who will complete the construction. If the building is watertight (hors d'eau), it may offer the project owner the option of concluding the completion contracts itself (Article L. 231-6, II and III).
Building damage insurance
Before acceptance, building damage insurance guarantees payment for the necessary repairs where, after an unheeded formal notice, the contract concluded with the contractor is terminated for failure to perform its obligations (Article L. 242-1 of the French Insurance Code).
Safeguard, receivership
The opening of the proceedings does not terminate the contract. Only the administrator may require its performance; the contract is terminated automatically after a formal notice to take a position that has remained unanswered for more than one month (Article L. 622-13 of the French Commercial Code, applicable to receivership under Article L. 631-14).
Liquidation
Only the liquidator may require performance of the current contract, which is terminated automatically after a formal notice to take a position that has remained unanswered for more than one month (Article L. 641-11-1). The claim for restitution or compensation must be filed with the creditors' representative, or with the liquidator in liquidation, within two months of the publication of the opening judgment in the BODACC, a time limit extended by two months for creditors who do not reside in metropolitan France (Articles L. 622-24, L. 641-3, R. 622-24 and R. 641-25).
The completion guarantee covers what is needed to complete the house, even outside the specification: the Cour de cassation overturned the judgment that refused to make the guarantor bear the cost of an essential access ramp to the garage, when it followed that “this work was necessary for the completion of the construction” (our translation) (Cass. 3e civ., 27 June 2019, No. 17-25.949). It does not cover everything, however: unless the guarantee contract provides otherwise, “the guarantor is not bound to bear the damages owed by the builder as compensation for losses distinct from the cost of completing the structure” (our translation), which excludes removal costs and the cost of renting alternative accommodation (Cass. 3e civ., 13 April 2023, No. 21-21.106). In the 2019 judgment, the Court also approved the refusal to make the guarantor bear the cost of other works, which were absent from the contract and from the descriptive notice.
Building damage insurance before acceptance does not fund the completion of an abandoned site: it covers damage of the kind for which builders are liable under the ten-year liability, and requires the formal notice followed by termination. This formal notice must come from the project owner or its agent, and the Cour de cassation specifies that “The project owner may dispense with this formality only where it proves impossible or pointless” (our translation), for example in the event of a compulsory liquidation entailing termination of the contract, before upholding the refusal of cover against a project owner who had terminated without formal notice (Cass. 3e civ., 7 September 2022, No. 21-21.382). See our articles on the completion guarantee under a detached-house building contract, on the builder who is late or abandons the site and on building work without building damage insurance.
Both sides
You are the project owner, or the contractor accused of abandoning the site
A halt in the work is not always a wrongful abandonment: everything depends on what each party has performed.
You are the project owner
- Give formal notice in writing, with a reasonable time limit and, if you are considering ending the contract, an express reference to termination.
- Have the state of the site recorded, if possible in the presence of both parties, before another contractor steps in.
- Check that your own payments are up to date, then quantify the additional cost, the delay and the loss, document by document.
You are the contractor accused
- Establish the project owner's failures: unpaid deposit, unpaid progress invoice, missing payment guarantee, access refused.
- Give written notice of the suspension and its reasons, rather than leaving the site in silence.
- Claim payment for the work carried out and challenge any termination made without formal notice.
The contractor may refuse to perform its obligation if the project owner fails to perform its own and if that non-performance is sufficiently serious (Article 1219 of the French Civil Code), or suspend performance where it is manifest that the owner will not perform and the consequences are sufficiently serious, provided it gives notice as soon as possible (Article 1220). In a private works contract, the project owner must guarantee payment of the sums due above a threshold set by decree; as long as no guarantee has been provided, a contractor that has not been paid for work carried out may suspend performance after a formal notice that has remained without effect for fifteen days (Article 1799-1). The text excludes part of these rules where the project owner contracts on its own account and for non-professional needs related to the contract: when dealing with a private individual, the contractor relies first on Articles 1219 and 1220. The Cour de cassation has held that the opening of insolvency proceedings against the project owner “cannot have the effect of compelling a contractor that, before such opening, duly gave notice of the suspension of its work, to resume it without obtaining the financial guarantee laid down by Article 1799-1 of the Civil Code” (our translation) (Cass. com., 10 October 2018, No. 17-18.547).
An interim payment sought in urgent proceedings is not automatic. The Cour de cassation recalls that “the judge hearing urgent applications may only award an interim payment to the creditor if the obligation is not seriously disputable” (our translation) (Cass. 3e civ., 22 October 2026, No. 24-13.737). It quashed the judgment ordering a contractor to repay, by way of interim payment, a deposit of more than €50,000, because the court had not examined, as it had been asked to, whether the project owner had paid the second deposit due when the work started. The argument has its limits: where the project owner had provided an effective bank guarantee, the Paris Court of Appeal held that “the contractor was not entitled to rely on the irregularity of the guarantee provided in order to suspend performance of the work” (our translation) (CA Paris, pôle 4, ch. 5, 6 November 2024, No. 21/17165).
Termination by the project owner can also be challenged. Under a fixed-price contract, the owner may terminate at will, compensating the contractor for its expenses, its work and what it could have earned (Article 1794); but where the fixed-price nature of the contract is not established, the Cour de cassation, which quashed a judgment that had applied this text without finding it, recalls that “a party cannot claim performance of a terminated contract, but only damages compensating the loss caused by the wrongful termination” (our translation) (Cass. 3e civ., 26 June 2025, No. 23-23.942). If the accusation of abandonment is circulating online, see our article on the building company accused of abandoning a site in online reviews.
The arguments the firm examines in every case, on either side:
FAQ
Frequently asked questions
Fourteen detailed answers, based on the texts in force and on verified court decisions.
When does a builder stopping work count as abandonment of the site in France?
None of the texts cited on this page sets a duration. Abandonment is inferred from a set of facts: work stopped without explanation, staff and equipment removed, reminders left unanswered, completion date passed. Legally, it is non-performance of the contract, which gives the project owner the remedies of Article 1217 of the French Civil Code: enforced performance, price reduction, termination, damages.
The contractor may escape liability if the stoppage results from force majeure, that is, an event beyond its control, unforeseeable when the contract was concluded and whose effects could not be avoided. A merely temporary impediment suspends performance, unless the delay justifies termination (Article 1218). It may also rely on the project owner's sufficiently serious non-performance, for example an unpaid deposit, if that breach is sufficiently serious (Article 1219).
The contract matters. Some contracts define abandonment. In a case decided by the Paris Court of Appeal, the special administrative terms and conditions referred to a volume of work below half of that planned in the month preceding the formal notice. The court found that the termination clause had taken effect against a contractor that “did not deploy the necessary staff on the site to carry out the work within the contractually agreed time limits” (our translation) (CA Paris, pôle 4, ch. 6, 2 December 2022, No. 20/11445). The firm first rereads the quote or the contract, then the agreed schedule, before characterising the situation.
The builder no longer comes back to the site: what should I do first?
Three steps, in this order. First, record the state of the site: dated photographs, written exchanges, and preferably a report by a court commissioner describing what has been done and what is missing. Next, send a written formal notice requiring the work to resume within a reasonable time: unless non-performance is final, damages are only due after a formal notice to perform (Article 1231 of the French Civil Code). Finally, suspend payments that do not correspond to any work carried out, which the contractor's sufficiently serious non-performance allows (Article 1219).
The time limit given must be proportionate to what is requested. For specific remedial works, the Grenoble Court of Appeal found that “The time limit of 8 days granted, in view of the requests, appears reasonable” (our translation), then upheld termination against the contractor alone, which had never responded to the complaints (CA Grenoble, chambre civile section B, 2 June 2026, No. 24/03842).
Do not bring in another contractor before this time limit expires: the Versailles Court of Appeal held to be abusive, and sanctioned with damages, the termination decided by a project owner on unproven grievances and, moreover, without prior formal notice (CA Versailles, chambre civile 1-4, 21 October 2024, No. 22/07414). The firm drafts the formal notice, arranges the inspection report and decides with you on the next step: resumption, completion by a third party or termination. See our article on the tradesman who abandons the site.
What must the formal notice contain to terminate a building contract in France?
If you are considering ending the contract without going to court, the formal notice must announce this consequence. Article 1226 of the French Civil Code allows the creditor to terminate the contract by notification, at its own risk; except in an emergency, it must first give the debtor formal notice to perform its obligation within a reasonable time, and this formal notice expressly states that, failing this, the creditor will be entitled to terminate the contract. If the non-performance continues, it gives notice of termination and the reasons for it. The contractor may challenge this before the court, and the project owner must then prove the seriousness of the non-performance.
If the contract contains a termination clause, termination requires an unheeded formal notice, unless the contract provides that it results from the mere fact of non-performance, and this formal notice must expressly refer to the clause to take effect (Article 1225). It must also come from the right person: to call on building damage insurance before acceptance, the Cour de cassation approved the court of appeal which held that the formal notice sent to the contractor “had to come from the project owner or its agent” (our translation), and not from the project manager (maître d'œuvre) without an express mandate (Cass. 3e civ., 7 September 2022, No. 21-21.382).
The firm drafts a formal notice that lists the breaches, sets the time limit, refers to the clause or to Article 1226 and prepares proof of its receipt.
Can I have the work finished by another contractor?
Yes. After formal notice, the creditor may, “within a reasonable time and at a reasonable cost” (our translation), have the obligation performed and claim reimbursement of the sums spent from the debtor; it may also ask the court to order the debtor to advance the necessary sums (Article 1222 of the French Civil Code). The court's prior authorisation is only required to destroy what has been done in breach of the obligation. The project owner may also first terminate the contract, by notification after formal notice (Article 1226) or through the court (Article 1227), and then sign with a new contractor.
Proof of the additional cost is prepared before the replacement arrives. The Paris Court of Appeal dismissed a project owner's claims, even though the abandonment was attributable to the contractor, because, having failed to have the work done recorded on the day of termination, it “fails to prove an additional cost of completion at the contractor's expense” (our translation) (CA Paris, pôle 4, ch. 5, 6 November 2024, No. 21/17165). In that case, the general terms of the contract provided for acceptance or a joint inspection of the work in the event of termination.
The firm checks that the termination is valid, has the state of the site recorded and quantifies the difference between the initial price, the work carried out and the cost of completion. See our article on the deposit paid and the completion of the work.
How can I get back deposits paid to a builder who abandoned the job?
By comparing what has been paid with the value of what has been done. Termination brings the contract to an end and gives rise to restitution (Article 1229 of the French Civil Code). Where the services have been of use progressively as the contract was performed, there is no restitution for the period before the last service that did not receive its counterpart; a service is restored by value, assessed on the date on which it was provided (Article 1352-8).
Both parties must provide proof. The Rennes Court of Appeal ordered termination against a contractor that had left the site, while holding that it “is entitled to claim payment for the work actually carried out, provided it proves its extent” (our translation), the court commissioner's inspection report establishing that work (CA Rennes, 4e ch., 17 September 2026, No. 25/02248).
Where the overpayment is obvious, the judge hearing urgent applications may award an interim payment if the obligation is not seriously disputable (Article 835 of the French Code of Civil Procedure). If the contractor is subject to insolvency proceedings, the claim must be filed with the creditors' representative, or with the liquidator in liquidation, within two months of the publication of the opening judgment in the BODACC (Articles L. 622-24, R. 622-24 and R. 641-25 of the French Commercial Code). See our article on deposits collected by a defaulting builder and the criminal route.
What compensation can I obtain after a builder abandons the work?
The debtor is ordered, where appropriate, to pay damages for non-performance or delay, unless there is force majeure (Article 1231-1 of the French Civil Code). The cost of completion by another contractor can also be claimed from the defaulting contractor (Article 1222).
If the contract provides for late-completion penalties, they apply as a penalty clause: the judge may, even of its own motion, reduce or increase the penalty if it is manifestly excessive or derisory, and reduce it in proportion to the benefit of partial performance. Unless non-performance is final, the penalty is only incurred after formal notice (Article 1231-5). The Paris Court of Appeal ordered a contractor to pay €19,140 incl. VAT in contractual late-completion penalties, capped by the contract at 5% of the contract price, holding that they were due independently of the termination (CA Paris, pôle 4, ch. 6, 2 December 2022, No. 20/11445).
Each head of loss must be proven. In another case, the same court dismissed the project owner's claim for penalties because it did not produce the work schedule, and its claim for additional cost because there was no joint record of the work on the day of termination, even though the abandonment was attributable to the contractor (CA Paris, pôle 4, ch. 5, 6 November 2024, No. 21/17165). The firm quantifies the claim head by head, with the invoices, quotes and reports that support it.
Our house builder abandoned the site: what does the completion guarantee cover?
Under a contract to build a detached house, the completion guarantee covers the project owner, from the opening of the site, against non-performance or defective performance of the work provided for in the contract, at the agreed price and within the agreed time (Article L. 231-6 of the French Construction and Housing Code). If the builder defaults, the guarantor bears the price overruns needed for completion, subject to an excess of no more than 5%, the consequences of an early payment or a price supplement, and the fixed late-delivery penalties beyond thirty days, which may not be lower than 1/3,000 of the price per day (Article R. 231-14).
Where the delivery deadline is not met, the guarantor, who notes this or is informed of it by the project owner, gives the builder formal notice; fifteen days after an unheeded formal notice, it appoints the person who will complete the work. It covers what is needed for completion, even if absent from the specification: the Cour de cassation overturned the refusal to make it bear the cost of an essential access ramp to the garage, when “this work was necessary for the completion of the construction” (our translation) (Cass. 3e civ., 27 June 2019, No. 17-25.949). On the other hand, unless the contract provides otherwise, it does not compensate losses distinct from the cost of completion, such as removal costs and renting other accommodation (Cass. 3e civ., 13 April 2023, No. 21-21.106). These costs are claimed from the builder.
The firm refers the matter to the guarantor, follows the appointment of the completion contractor and quantifies the penalties. See our article on the obligations of the completion guarantor.
Does building damage insurance (dommages-ouvrage) cover an abandoned building site?
Not the completion itself. Building damage insurance guarantees payment for the repair of damage of the kind for which builders are liable under the ten-year liability, and normally takes effect after the guarantee of perfect completion has expired (Article L. 242-1 of the French Insurance Code). The same text provides for an exception: it guarantees payment for the necessary repairs where, before acceptance, after an unheeded formal notice, the contract concluded with the contractor is terminated for failure to perform its obligations.
The condition is applied strictly. In a judgment of 7 September 2022, the Cour de cassation holds that cover is only due before acceptance if this formal notice preceded the termination, and adds that “The project owner may dispense with this formality only where it proves impossible or pointless” (our translation), in particular in the event of cessation of business or of a compulsory liquidation entailing termination of the contract; the project owner who had terminated without formal notice, several months before the contractor's liquidation, lost the cover (Cass. 3e civ., 7 September 2022, No. 21-21.382).
The insurer must give notice of its position on the principle of cover within sixty days of the claim notification (Article L. 242-1). The firm checks the policy and the chronology of the formal notice and termination, then prepares the claim notification. Defects that appear after acceptance are covered on our page construction law lawyer.
The contractor is in receivership or compulsory liquidation: what happens to the building site?
The opening of the proceedings does not by itself terminate the contract. In safeguard and receivership proceedings, only the administrator may require performance of current contracts; the contract is terminated automatically after a formal notice to take a position that has remained unanswered for more than one month (Article L. 622-13 of the French Commercial Code, applicable to receivership under Article L. 631-14). In liquidation, only the liquidator has this power, with the same one-month formal notice mechanism (Article L. 641-11-1). The supervising judge (juge-commissaire) may shorten this time limit or extend it by up to two months.
Claims that arose before the judgment, such as the repayment of a deposit, must be filed with the creditors' representative (Article L. 622-24), within two months of the publication of the opening judgment in the BODACC (Article R. 622-24), and with the liquidator in liquidation, within the same time limit (Articles L. 641-3 and R. 641-25). For a detached house, in safeguard or receivership proceedings, the completion guarantor may give the administrator formal notice to decide whether the contract will continue and, failing a reply within one month, it performs its obligations (Article L. 231-6 of the French Construction and Housing Code).
Liquidation may also make unnecessary the formal notice required for building damage insurance before acceptance: according to the Cour de cassation, the project owner may dispense with it “only where it proves impossible or pointless” (our translation), in particular in the event of a compulsory liquidation entailing termination of the contract (Cass. 3e civ., 7 September 2022, No. 21-21.382). The firm sends the formal notice to the competent officeholder, files the claim and calls on the guarantees.
Urgent application (référé) or full proceedings: which route should I choose?
The two can be combined. Urgent proceedings first make it possible to establish evidence, with no urgency requirement for an expert assessment: if there is a legitimate reason to establish, before any trial, proof of facts on which the outcome of the dispute depends, an expert assessment may be ordered, and where it concerns a building, the court for the place where the building is located has exclusive jurisdiction (Article 145 of the French Code of Civil Procedure). The president of the judicial court (tribunal judiciaire) may also order the protective measures needed to prevent imminent damage, and award an interim payment or order the performance of an obligation to do something where the obligation is not seriously disputable (Articles 834 and 835).
This last condition limits applications for an interim payment. The Cour de cassation quashed the judgment ordering a contractor to repay a deposit by way of interim payment, without examining whether the project owner had itself paid the second deposit provided for in the contract, recalling that “the judge hearing urgent applications may only award an interim payment to the creditor if the obligation is not seriously disputable” (our translation) (Cass. 3e civ., 22 October 2026, No. 24-13.737).
The full proceedings decide termination, restitution and damages. The expert assessment serves both: the expert describes the progress of the work, the defects and the cost of completion. The firm brings urgent proceedings when the evidence is at risk of disappearing or when the debt is not disputable, and full proceedings in other cases. See our article on expert assessment of defective work and evidence.
What is the time limit to take action against a contractor who abandoned the site?
As long as the works have not been accepted, the project owner's contractual liability action against the contractor is time-barred after five years from the day on which the owner knew or should have known the facts enabling it to act (Article 2224 of the French Civil Code). The Cour de cassation so held for defects revealed in the absence of acceptance, adding that “only an initiative by the creditor of the obligation can interrupt the limitation period” (our translation): the application for an expert assessment brought by others had not interrupted the time limit for the benefit of the project owner, whose claims were declared inadmissible (Cass. 3e civ., 19 March 2020, No. 19-13.459).
After acceptance, liability actions against builders are time-barred ten years after acceptance, apart from the actions governed by Articles 1792-3, 1792-4-1 and 1792-4-2, which have their own time limits (Article 1792-4-3). Acceptance may also relate to only part of an unfinished site: the Cour de cassation holds that “completion of the entire structure is not a condition for taking possession of a lot and for its acceptance” (our translation) (Cass. 3e civ., 30 January 2019, No. 18-10.197). It takes place amicably or, failing that, by court order, at the request of the more diligent party (Article 1792-6).
The firm dates each fact, checks whether there has been acceptance, even tacit, and issues proceedings itself when the time limit requires it, rather than relying on someone else's proceedings.
We are the contractor accused of abandoning the site: how can we defend ourselves?
By showing that the stoppage was not wrongful. The contractor may refuse to perform if the project owner does not perform its obligation and if that non-performance is sufficiently serious (Article 1219 of the French Civil Code), or suspend performance where it is manifest that the owner will not perform and the consequences are sufficiently serious, giving notice as soon as possible (Article 1220). In a private works contract, as long as the project owner has not provided the payment guarantee required above a threshold set by decree, an unpaid contractor may suspend performance after a formal notice that has remained without effect for fifteen days, a rule the text partly excludes for a private individual contracting for non-professional needs (Article 1799-1). The Cour de cassation has held that the opening of insolvency proceedings against the project owner “cannot have the effect of compelling a contractor that, before such opening, duly gave notice of the suspension of its work, to resume it without obtaining the financial guarantee laid down by Article 1799-1 of the Civil Code” (our translation) (Cass. com., 10 October 2018, No. 17-18.547).
This defence has its limits: where the guarantee provided was effective, the Paris Court of Appeal held that “the contractor was not entitled to rely on the irregularity of the guarantee provided in order to suspend performance of the work” (our translation) (CA Paris, pôle 4, ch. 5, 6 November 2024, No. 21/17165). In a case decided by the Rennes Court of Appeal, mere questions raised by the project owner about the performance of the work were not held to amount to a sufficiently serious loss of trust, and the court found that “the termination of the contract at the initiative of the appellant is not justified” (our translation), while awarding the contractor payment for the work carried out (CA Rennes, 4e ch., 17 September 2026, No. 25/02248).
The firm reconstructs the chronology of payments and exchanges, challenges the interim payment sought in urgent proceedings where the project owner has not paid itself (Cass. 3e civ., 22 October 2026, No. 24-13.737), and claims the price of the work carried out.
Can the project owner end the contract without any fault by the contractor?
Yes, for a fixed-price contract. The owner may terminate a fixed-price contract at will, even once the work has started, by compensating the contractor for all its expenses, all its work and everything it could have earned from the job (Article 1794 of the French Civil Code). Outside this framework, ending the contract without serious fault by the contractor makes the owner liable. The Cour de cassation specifies that “a party cannot claim performance of a terminated contract, but only damages compensating the loss caused by the wrongful termination” (our translation), and overturned the judgment that had applied Article 1794 without finding that the contract was a fixed-price one (Cass. 3e civ., 26 June 2025, No. 23-23.942).
Article 1794 does not, however, prevent the project owner from relying on the contractor's fault. The Cour de cassation holds that the project owner's right to terminate a fixed-price contract unilaterally “does not deprive the owner of the possibility of terminating the contract under the conditions of general law” (our translation), by relying on the seriousness of the contractor's breaches, and quashed the judgment that had ordered the owner to compensate the contractor's lost profit without examining those grievances (Cass. 3e civ., 25 June 2026, No. 24-18.064). Procedure matters: the Versailles Court of Appeal held to be abusive the termination by a project owner who, on unproven grievances, had “abruptly put an end to the site work in progress, moreover without the prior formal notice required by law” (our translation), and ordered the owner to compensate the contractor (CA Versailles, chambre civile 1-4, 21 October 2024, No. 22/07414).
The firm checks the nature of the contract, the reality and seriousness of the breaches relied on, then the validity of the formal notice and of the notification (Article 1226), before advising on ending the contract or challenging the termination.
What are the fees of an abandoned building work lawyer in Paris?
Except in an emergency, in cases of force majeure or under full legal aid, fees are set out in a written fee agreement, in accordance with Article 10 of the Law of 31 December 1971: before committing, you know what the engagement covers and what it costs. The agreement specifies the amount or the method of determining the fees covering the foreseeable work, as well as the expected costs and disbursements. Fees take into account, according to custom, in particular the difficulty of the case, the costs incurred and the work carried out; a fee set solely on the basis of the court outcome is prohibited, but an additional fee linked to the result obtained may be added to the remuneration for the services (same article).
The firm favours a fixed fee per stage: analysis of the contract and formal notice, arranging the inspection report, referral to the guarantor or insurer, filing of the claim, urgent application for an expert assessment or an interim payment, full proceedings, appeal. Court commissioner and expert assessment costs are added to the fees. Any new engagement gives rise to an amendment, with no unexpected invoicing.
For a first opinion on the documents, the preliminary case review at €80 incl. VAT, through the form on this page, leads to a written analysis within 24 working hours. First contact on +33 6 89 11 34 45.
References
Official texts and related pages
The sources of this page, verified on 31 October 2026, and the firm's related areas of practice.
Official texts
- Articles 1217 of the French Civil Code, 1218 and 1231: remedies for non-performance, force majeure, formal notice
- Articles 1219 and 1220: defence of non-performance and suspension
- Articles 1221, 1222 and 1223: enforced performance, performance by a third party, price reduction
- Articles 1225, 1226, 1227, 1228 and 1229: termination of the contract and its effects
- Articles 1231-1, 1231-5 and 1352-8: damages, penalty clause, restitution by value
- Articles 1792-6, 1792-4-3, 1794 and 1799-1: acceptance of the works, limitation after acceptance, termination of a fixed-price contract, payment guarantee
- Article 2224: five-year limitation period
- Articles 145 of the French Code of Civil Procedure, 834 and 835: pre-trial expert assessment, urgent proceedings, interim payment
- Article L. 242-1 of the French Insurance Code: building damage insurance, cover before acceptance
- Articles L. 230-1 of the French Construction and Housing Code, L. 231-6 and R. 231-14: contract to build a detached house, completion guarantee, penalties
- Articles L. 622-13 of the French Commercial Code, L. 631-14 and L. 641-11-1: current contracts in safeguard, receivership and liquidation proceedings
- Articles L. 622-24, L. 641-3, R. 622-24 and R. 641-25: filing of claims
- Article 10 of Law No. 71-1130 of 31 December 1971: fee agreement
Decisions cited
- Cass. 3e civ., 25 June 2026, No. 24-18.064: seriousness of the breaches and termination of a fixed-price contract
- Cass. 3e civ., 26 June 2025, No. 23-23.942: wrongful termination and Article 1794
- Cass. 3e civ., 7 September 2022, No. 21-21.382: building damage insurance before acceptance, prior formal notice
- Cass. 3e civ., 19 March 2020, No. 19-13.459: five-year limitation period in the absence of acceptance
- Cass. 3e civ., 30 January 2019, No. 18-10.197: acceptance of a lot in an unfinished structure
- Cass. 3e civ., 27 June 2019, No. 17-25.949: completion guarantor and work necessary for completion
- Cass. 3e civ., 13 April 2023, No. 21-21.106: completion guarantor and distinct losses
- Cass. 3e civ., 22 October 2026, No. 24-13.737: interim payment in urgent proceedings and deposit unpaid by the project owner
- Cass. com., 10 October 2018, No. 17-18.547: contractor's suspension of work for lack of a payment guarantee
- CA Paris, pôle 4, ch. 6, 2 December 2022, No. 20/11445: termination clause and penalties for abandonment
- CA Paris, pôle 4, ch. 5, 6 November 2024, No. 21/17165: unjustified suspension, proof of additional cost
- CA Versailles, chambre civile 1-4, 21 October 2024, No. 22/07414: abusive termination, unproven grievances and no formal notice
- CA Grenoble, chambre civile section B, 2 June 2026, No. 24/03842: reasonable time limit in the formal notice
- CA Rennes, 4e ch., 17 September 2026, No. 25/02248: unjustified abandonment and payment for work carried out
Further reading
Builder abandoned the work, deposits paid, a termination disputed?
The firm can be reached 24/7. Send the quote or contract, the invoices and proof of payment, your exchanges with the contractor and photographs of the site: Hassan Kohen, avocat at the Paris Bar, reviews the progress of the work, the time limits and the guarantees, then tells you which route suits your case: formal notice, inspection report, termination, completion by a third party, referral to the guarantor or insurer, urgent application or full proceedings, or defence of the contractor accused.