Kohen Avocats, construction law in Paris
Construction lawyer in Paris: defects, warranties and disputes
As construction lawyers in Paris, we handle acceptance of works and reservations, the one-year completion warranty, the two-year and ten-year warranties, building defects insurance (dommages-ouvrage), delays and penalties, contracts for the construction of a private house, court-appointed expert assessments and litigation. The firm assists individuals, co-owned buildings and businesses having work built or renovated, as well as craftsmen and builders facing claims. Everything starts with acceptance of the works (réception), which sets the warranties running.
The firm can be reached 24/7. The completion warranty (garantie de parfait achèvement) lasts only one year from acceptance of the works (Article 1792-6 of the French Civil Code); the building defects insurer must notify its position within sixty days of receiving the claim notification (Article L. 242-1 of the French Insurance Code, Code des assurances).
4,9/5
Average Google rating270 reviews
I received very high-quality support from this criminal lawyer. His professionalism, his complete command of the case and his constant involvement at every stage of the proceedings deserve to be highlighted. Communication was clear, structured and responsive, with precise advice suited to my situation. I recommend this lawyer to anyone looking for a rigorous and effective criminal defence.
Mr Kohen handled my criminal case. I am very satisfied with the work he did and I recommend him to you without any hesitation.
Excellent criminal defence lawyer, he got me out of trouble in a case involving a protection order applied for abusively by my ex
Very satisfied with the solution provided for my defence before the court. All the best
Hassan Kohen is a young, seasoned and highly competent lawyer. He is an excellent listener, with a great deal of empathy and strong human sensitivity. Available and responsive, he has complete command of his profession.
I had a very good experience with Hassan Kohen. He took the time to listen to me carefully and to fully understand my situation. He is a lawyer who gives sound advice, caring and available, who knows how to steer his clients in the right direction. I recommend him without hesitation to anyone looking for an attentive and competent professional.
Mr Kohen advised and supported us well. I thank him for everything he has done.
Paris Bar
Emergencies 24/7
Preliminary case review
Send your documents. Receive an analysis.
Hassan Kohen
Avocat at the Paris Bar: construction law, acceptance of works and builders' warranties, construction insurance and court-appointed expert assessments.
Official profile in the directory of French lawyers (CNB) · 4.9/5 on Google (270 reviews)
Page updated on 31 October 2026.
Quick answer
Every builder of a structure is strictly liable (de plein droit) to the project owner or the purchaser of the structure for damage that compromises its soundness or makes it unfit for its intended purpose, unless there is an external cause (Article 1792 of the French Civil Code, Code civil). This liability runs for ten years from acceptance of the works (Article 1792-4-1), the act by which the project owner accepts the works with or without reservations, which also opens the one-year completion warranty (Article 1792-6) and the warranty of proper functioning of at least two years (Article 1792-3). Before work starts on site, the project owner must, save for exceptions provided by law, take out building defects insurance (assurance dommages-ouvrage), which pre-finances repairs without any prior determination of liability, and the builder must take out ten-year liability insurance (Articles L. 242-1 and L. 241-1 of the French Insurance Code). In the event of a dispute, a court-appointed expert assessment can be ordered in summary proceedings (référé) before any trial (Article 145 of the French Code of Civil Procedure), and the summons in summary proceedings interrupts the ten-year period for the defects it identifies. Kohen Avocats, in Paris 16th, acts for project owners as well as for builders and craftsmen. Contact: +33 6 89 11 34 45.
Defects after building work, an acceptance of works to prepare, an unpaid invoice?
Understanding your situation
Construction law in Paris, explained
Every builder is strictly liable for damage that compromises the soundness of the structure or makes it unfit for its intended purpose (Article 1792 of the French Civil Code). How acceptance of the works takes place, what the warranties and insurance policies cover, what each party can demand in the event of delay or non-payment, and how to conduct the expert assessment and the trial within the time limits.
Key points
Acceptance of the works (réception): the act that sets the warranties running
Four points to master before signing, or refusing to sign, the acceptance report.
An act of acceptance: "Acceptance is the act by which the project owner declares that he accepts the works with or without reservations" (Article 1792-6 of the French Civil Code, our translation).
An adversarial act: acceptance takes place at the request of the most diligent party, by agreement or, failing that, by the court, and in any event it is pronounced in the presence of both parties (Article 1792-6).
Acceptance is sometimes tacit: without a report, taking possession of the works and paying for them create a presumption of the intention to accept the works, a presumption that consistent objections can rebut.
Precise reservations: it is prudent to record every visible defect in the acceptance report. The completion warranty covers the defects subject to reservations and those revealed after acceptance and notified in writing (Article 1792-6).
Tacit acceptance rests on a presumption. According to the French Court of Cassation (Cour de cassation), "taking possession of the works and paying for them create a presumption of the project owner's unequivocal intention to accept them with or without reservations" (our translation) (Cass. 3e civ., 18 April 2019, No. 18-13.734). The presumption gives way to the facts: project owners who had "consistently disputed the quality of the work carried out and requested a court-appointed expert assessment to establish the contractor's failings" (our translation) had not tacitly accepted the works, their intention being held to be equivocal (Cass. 3e civ., 1 April 2021, No. 20-14.975). The date retained matters, since it sets the starting point of the warranties.
Reservations have a downside. The Paris Court of Appeal points out that "defects subject to reservations at acceptance do not fall within the builders' ten-year warranty", except those which "only became apparent later in their full extent and consequences" (our translation) (CA Paris, pôle 4, ch. 6, 19 December 2025, No. 23/06683). In that case, a bay opening whose planned lintel had not been installed, also subject to a reservation, was compensated under the ten-year warranty because its structural risk only emerged during the expert assessment; the parquet floor and the electrical panel, subject to reservations and known in their seriousness at acceptance, were not.
For a private house built under the regulated contract, the project owner may still report, by registered letter with acknowledgement of receipt within the eight days following the handover of the keys, visible defects not noted at acceptance, unless at acceptance he was assisted by a professional authorised under the law of 3 January 1977 on architecture or Articles L. 125-1 et seq., or by another construction professional holding insurance covering this type of assignment (Article L. 231-8 of the French Construction and Housing Code, Code de la construction et de l'habitation). See also our article on defects found after acceptance of the works.
The warranties
Completion, proper functioning, ten-year liability: who is liable for what, and for how long
Each warranty has its own scope and time limit, all counted from acceptance of the works.
One year
Completion warranty (garantie de parfait achèvement): the contractor repairs all defects subject to reservations or notified in writing; if he fails to do so, after a formal notice that has gone unheeded, the work may be carried out at his expense and risk. Normal wear and tear and use are excluded (Article 1792-6).
At least two years
Warranty of proper functioning (garantie biennale) for items of equipment that do not form an indissociable whole with the works of roads and services, foundations, framework, enclosure or roofing, for a minimum period of two years from acceptance (Article 1792-3).
Ten years
Ten-year liability (garantie décennale) for damage that compromises the soundness of the structure or makes it unfit for its intended purpose, and for damage affecting the soundness of indissociable items of equipment (Articles 1792 and 1792-2); the builder is released from it ten years after acceptance (Article 1792-4-1).
General law
Apart from actions governed by Articles 1792-3, 1792-4-1 and 1792-4-2, liability actions against builders and their subcontractors are time-barred ten years after acceptance (Article 1792-4-3), a foreclosure period (délai de forclusion) according to the Court of Cassation.
Who is liable
Any architect, contractor, technician or other person bound to the project owner by a works contract (contrat de louage d'ouvrage) is deemed a builder, as is anyone who sells, after completion, a structure they have built or had built (Article 1792-1).
Clauses
Any clause that excludes or limits these liabilities and warranties is deemed unwritten (Article 1792-5). Equipment whose sole function is to enable a professional activity to be carried out in the structure is excluded (Article 1792-7).
Equipment installed on an existing structure follows a restrictive rule. Since a judgment of 21 March 2024, the Court of Cassation has held that "where items of equipment installed as a replacement or an addition on an existing structure do not in themselves constitute a structure, they fall neither within the ten-year warranty nor within the two-year warranty of proper functioning, whatever the degree of seriousness of the defects, but within ordinary contractual liability, which is not subject to the builders' compulsory insurance" (our translation) (Cass. 3e civ., 21 March 2024, No. 22-18.694). The project owners, whose house had been destroyed by a fire caused by a fireplace insert, thus lost the benefit of the award based on the ten-year warranty, and the case was referred back to the Nîmes Court of Appeal.
Where the ten-year warranty applies, its coverage is broad: "all damage, material and non-material, resulting from the defects in the structure must be made good by the builder bound by the warranty" (our translation), including the costs of rehousing, furniture storage and removal (Cass. 3e civ., 3 April 2025, No. 23-16.055).
Classification is decided defect by defect, and the court-appointed expert assessment prepares it. See our article on construction defects, the ten-year warranty and building defects insurance, and on the liability of the architect acting as project manager.
Insurance
Building defects insurance and ten-year liability insurance: two obligations, two functions
One pre-finances the repairs, the other covers the builder's liability.
The owner, seller or agent who has construction work carried out takes out, before work starts on site, insurance guaranteeing, "without any determination of liability", payment for the repair of damage of a ten-year nature, save for exceptions provided by law (Article L. 242-1 of the French Insurance Code).
The building defects insurer notifies its decision on the principle of cover within a maximum of sixty days from receipt of the claim notification and then, if it accepts cover, presents a compensation offer within a maximum of ninety days running from the same receipt (Article L. 242-1).
If it fails to meet these time limits or makes a manifestly inadequate offer, the insured may, after notifying the insurer, incur the expenditure needed for the repairs; the compensation is then automatically increased by interest equal to twice the statutory interest rate (Article L. 242-1).
This insurance takes effect once the completion warranty has expired; however, after a formal notice that has gone unheeded, it covers repairs where the contract is terminated for non-performance before acceptance, or where the contractor fails to perform its obligations after acceptance (Article L. 242-1).
Anyone whose ten-year liability may be engaged must be insured and provide proof of this when any work starts on site; the policy is deemed to maintain cover for the duration of that liability (Article L. 241-1).
Failure to take out compulsory insurance is punishable by up to six months' imprisonment and a fine of 75,000 euros, or one of these two penalties, except for an individual who builds a dwelling to live in themselves or for occupation by their spouse, their ascendants or descendants or those of their spouse (Article L. 243-3).
The sixty-day time limit is a real constraint for the insurer. The Court of Cassation holds that "the building defects insurer is required to respond within the sixty-day time limit to any claim notification, including where it considers that the defects are identical to those previously reported, and that, failing this, it can no longer rely on the two-year limitation period that would have expired by the date of the second notification" (our translation) (Cass. 3e civ., 30 September 2021, No. 20-18.883). Its agreement also binds it: "the insurer which has accepted, within the sixty-day time limit, that the cover is triggered can no longer dispute it on the ground that the defects are not of a ten-year nature" (our translation) (Cass. 3e civ., 3 April 2025, No. 23-16.055).
Where the business is uninsured, its manager may be pursued personally. The Court of Cassation overturned a court of appeal judgment that had dismissed the project owners' claims without examining whether the manager "had not committed faults separable from his corporate duties, engaging his personal liability, by failing to conclude a contract for the construction of a private house and to take out ten-year liability insurance" (our translation) (Cass. 3e civ., 7 June 2018, No. 16-27.680). Where the business is insured, the injured third party has a direct action against its liability insurer (Article L. 124-3); this action "is, in principle, subject to the same limitation period as its action against the liable party" (our translation) (Cass. 3e civ., 14 September 2023, No. 22-21.493).
The insured's action against its own insurer is time-barred two years after the event giving rise to it (Article L. 114-1). See our articles on the statutory time limits of the building defects insurer, on a refusal by the building defects insurer and on craftsmen without ten-year liability insurance.
Both sides
You are having work built, or you are the builder: two positions, the same rules
Delays, penalties, unpaid balance, private houses: what each party can demand.
You are the project owner
- Check, before signing, the contract, the insurance certificates and, for a private house, the refund and completion guarantees.
- Serve formal notice on the contractor, have the defects and the delay formally recorded, and claim the agreed penalties.
- Keep any withholding of the price proportionate to the seriousness of the failings, then act within the warranty time limits.
You are a builder or craftsman
- Have amendments and additional work signed; obtain the payment guarantee where the law requires it.
- Initiate acceptance, by agreement or through the court, and clear the reservations within the agreed time limits.
- Challenge the classification of the defects, rely on external cause, foreclosure and the costing.
Late-completion penalties are a penalty clause. The court may, even of its own motion, reduce or increase the agreed penalty if it is manifestly excessive or derisory and, except in the case of definitive non-performance, the penalty is only incurred after formal notice (Article 1231-5 of the French Civil Code). The Rennes Court of Appeal held that a roofing company "cannot rely on force majeure to explain this delay" (our translation), since difficulties in obtaining materials had to be anticipated, but also found that the penalty was "manifestly disproportionate since it corresponds to 30% of the contract price" (our translation): it was reduced from 175,789.10 euros to 27,044.47 euros (CA Rennes, 4e ch., 20 November 2025, No. 24/03749).
Withholding the price is a regulated right. A party may refuse to perform its obligation if the other party does not perform its own and if this non-performance is sufficiently serious (Article 1219 of the French Civil Code). According to the Bordeaux Court of Appeal, this defence "must remain proportionate to the failing on which it is based, so that a project owner who withholds the entire price when the works can be used does so at their own risk" (our translation); it ordered the company that was withholding half the price for defects costed at 960 euros to pay the balance (CA Bordeaux, 4e ch. com., 1 July 2026, No. 24/04144). For their part, contractors under a private works contract may, where the project owner has provided no payment guarantee, suspend performance for as long as they remain unpaid, after a formal notice that has gone unheeded for fifteen days, unless the project owner is contracting on their own behalf to meet needs unrelated to a professional activity connected with the contract (Article 1799-1 of the French Civil Code).
Private houses are governed by mandatory rules of public policy (Article L. 230-1 of the French Construction and Housing Code). The contract states, among other things, the price, the completion time, the late-completion penalties and the refund and completion guarantees (Article L. 231-2); the penalties may not be less than 1/3,000 of the agreed price per day of delay (Article R. 231-14), and the completion guarantor bears those corresponding to a delay exceeding thirty days (Article L. 231-6). Where the contract is set aside and demolition is sought, the court "must examine whether demolition of the structure built is a sanction proportionate to the seriousness of the defects and non-conformities affecting it", and "it is for the builder to prove the facts capable of establishing that the sanction is disproportionate" (our translation) (Cass. 3e civ., 27 May 2021, No. 20-13.204).
The points the firm examines in every case:
Abandoned building sites, off-plan sales (VEFA), latent defects and neighbourhood nuisance are covered on separate pages. Work carried out without planning permission is dealt with on our page on building without a permit. See also our article on late builders and the completion guarantee.
Litigation
Court-appointed expert assessment, action on the merits and time limits for bringing a claim
A construction case is won first on the technical evidence and on the timetable.
Formal record and formal notice
Record the defects in writing, with photographs and a formal report, then serve formal notice on the contractor: formal notice is a precondition for having the work carried out at the expense of the defaulting contractor (Article 1792-6) and, except in the case of definitive non-performance, for the penalties to become payable (Article 1231-5).
Expert assessment in summary proceedings
If there is a legitimate reason to preserve or establish, before any trial, evidence of facts on which the resolution of a dispute may depend, an investigative measure may be ordered in summary proceedings; where it concerns a property, the court of the place where the property is located has sole jurisdiction (Article 145 of the French Code of Civil Procedure).
Expert assessment
The court appoints a technical expert to inform it on a question of fact (Article 232 of the French Code of Civil Procedure); the expert's findings then form the basis for classifying the defects and costing the repairs.
Interim payment
Where the obligation is not seriously disputable, the president of the judicial court (tribunal judiciaire), ruling in summary proceedings, may grant the creditor an interim payment (provision) (Article 835 of the French Code of Civil Procedure).
Interruption
A claim brought before the court, even in summary proceedings, interrupts the limitation period as well as the foreclosure period (Article 2241 of the French Civil Code), until the proceedings come to an end (Article 2242).
Action on the merits
Against the builders, their insurers and the building defects insurer, on the legal basis suited to each defect, using the expert's conclusions.
An expert assessment in summary proceedings protects the ten-year period. In a judgment of 22 October 2026, whose publication status was not yet indicated by Judilibre as at 31 October 2026, the Court of Cassation held that the ten-year foreclosure period for an action based on Article 1792 of the French Civil Code "is interrupted by a summons in summary proceedings for an expert assessment, and starts running again for a full period of ten years from the order granting the investigative measure", and that "Article 2239 of the Civil Code on the suspension of limitation during the investigative measure does not apply to it" (our translation) (Cass. 3e civ., 22 October 2026, No. 24-22.203). The period therefore starts again from the order, not from the filing of the expert's report.
The summons must, however, identify each defect. "The interruptive effect attached to a summons applies only to the defects expressly identified in it" (our translation), and an application to extend the expert assessment to other defects has no effect on the action relating to the defects within the original remit (Cass. 3e civ., 2 May 2024, No. 22-23.004). The ten-year period for ordinary contractual liability is also a foreclosure period: "acknowledgement by the debtor of the right of the person against whom time was running does not interrupt the foreclosure period" (our translation) (Cass. 3e civ., 10 June 2021, No. 20-16.837). In that case, the agreement reached with the contractor did not save the project owners' action against the insurer.
The firm assists its clients at expert meetings, drafts written submissions to the expert (dires) and prepares the action on the merits or the defence. See our article on proving building defects and the expert assessment.
FAQ
Frequently asked questions
Fourteen detailed answers, based on the texts in force and on verified court decisions.
When should I hire a construction lawyer in France?
Before the work, during the building project and as soon as a defect appears. Before you sign, the lawyer reviews the works contract, the quote or the contract for the construction of a private house, and checks the contractors' insurance certificates and that building defects insurance has been taken out, which an owner having construction work carried out must take out before work starts on site, save for exceptions provided by law (Article L. 242-1 of the French Insurance Code). During the project, the lawyer manages delays, amendments, additional work and unpaid sums.
At acceptance, the lawyer helps draft the reservations, because this act sets the starting point of the warranties: acceptance is the act by which the project owner declares that he accepts the works with or without reservations (Article 1792-6 of the French Civil Code). After acceptance, the lawyer chooses the legal basis suited to each defect: completion warranty, warranty of proper functioning, ten-year liability or ordinary contractual liability. The choice is not theoretical: the Court of Cassation holds that items of equipment installed on an existing structure, where they do not in themselves constitute a structure, fall neither within the ten-year warranty nor within the two-year warranty, but within ordinary contractual liability (Cass. 3e civ., 21 March 2024, No. 22-18.694).
The firm acts for individuals, co-owners' associations (syndicats de copropriétaires) and businesses having work built or renovated, as well as for craftsmen, general contractors and builders facing claims. Abandoned building sites, off-plan sales (VEFA), latent defects and neighbourhood nuisance are covered on separate pages, and work without authorisation is dealt with on the page on building without a permit.
How does acceptance of building works work in France, and should I record reservations?
Acceptance is the act by which the project owner declares that he accepts the works with or without reservations. It takes place at the request of the most diligent party, by agreement or, failing that, by the court, and it is always pronounced in the presence of both parties (Article 1792-6 of the French Civil Code). In practice, a report is signed after an inspection of the premises, in the presence of the contractor.
Without a report, acceptance may be tacit: "taking possession of the works and paying for them create a presumption of the project owner's unequivocal intention to accept them with or without reservations" (our translation) (Cass. 3e civ., 18 April 2019, No. 18-13.734). The presumption has been set aside where the project owner had consistently disputed the quality of the work and requested an expert assessment: the court of appeal, within its sovereign assessment, held that the intention to accept was equivocal (Cass. 3e civ., 1 April 2021, No. 20-14.975).
It is better to record every visible defect as a reservation. The completion warranty covers the defects noted in the report, or notified in writing if they appear later (Article 1792-6). Conversely, "defects subject to reservations at acceptance do not fall within the builders' ten-year warranty" (our translation), unless they only became apparent later in their full extent; in a case decided by the Paris Court of Appeal, the parquet floor and the electrical panel subject to reservations were excluded from the ten-year warranty (CA Paris, pôle 4, ch. 6, 19 December 2025, No. 23/06683). For a private house under the regulated contract, a project owner who was not assisted by an authorised professional, or by one insured for this assignment, has eight days after the handover of the keys to report overlooked visible defects by registered letter (Article L. 231-8 of the French Construction and Housing Code). The firm can assist you at the acceptance inspection.
What does the one-year completion warranty cover in France?
The repair of all defects reported by the project owner, either by reservations recorded in the acceptance report, or by written notification for those revealed after acceptance. The contractor is bound by it for one year from acceptance (Article 1792-6 of the French Civil Code). It makes no distinction according to seriousness: a finishing defect is covered just as a water leak is.
The time limits for carrying out the remedial work are set by mutual agreement. If there is no agreement, or if the contractor does not meet them, the work may, after a formal notice that has gone unheeded, be carried out at the expense and risk of the defaulting contractor. Its completion is recorded by mutual agreement or, failing that, by the court. The warranty does not extend to work needed to remedy the effects of normal wear and tear or use (Article 1792-6).
Building defects insurance can take over from this warranty: it takes effect once the warranty has expired, but also covers payment for repairs where, after acceptance and a formal notice that has gone unheeded, the contractor has not performed its obligations (Article L. 242-1 of the French Insurance Code). Defects subject to reservations do not, in principle, fall within the ten-year warranty: the Paris Court of Appeal rejected the claims brought against the insurer for a parquet floor and an electrical panel subject to reservations at acceptance (CA Paris, pôle 4, ch. 6, 19 December 2025, No. 23/06683). Their repair falls under the completion warranty, within the year. The firm drafts the formal notice, sets the timetable for the remedial work and, failing that, arranges for the work to be carried out at the contractor's expense.
Two-year or ten-year warranty in France: what is the difference?
The seriousness of the damage and the nature of the item affected. The ten-year warranty covers damage that compromises the soundness of the structure or which, affecting it in one of its constituent elements or items of equipment, makes it unfit for its intended purpose (Article 1792 of the French Civil Code). It extends to damage affecting the soundness of items of equipment that form an indissociable whole with the works of roads and services, foundations, framework, enclosure or roofing, that is to say those which cannot be removed, dismantled or replaced without damaging or removing material from the structure (Article 1792-2).
Other items of equipment fall under the warranty of proper functioning, for a minimum period of two years from acceptance (Article 1792-3). The builder is released from the ten-year warranty ten years after acceptance, and from the warranty of proper functioning when its period expires (Article 1792-4-1). Equipment whose sole function is to enable a professional activity to be carried out in the structure falls outside these warranties (Article 1792-7).
Equipment installed on an existing structure now follows its own rule. According to the Court of Cassation, "where items of equipment installed as a replacement or an addition on an existing structure do not in themselves constitute a structure, they fall neither within the ten-year warranty nor within the two-year warranty of proper functioning, whatever the degree of seriousness of the defects, but within ordinary contractual liability, which is not subject to the builders' compulsory insurance" (our translation) (Cass. 3e civ., 21 March 2024, No. 22-18.694). Equipment added to an existing house, such as the fireplace insert in that case, is therefore not treated like original equipment. The firm classifies each defect before choosing the legal basis for the action.
Which building defects are covered by the ten-year warranty (garantie décennale)?
Those that compromise the soundness of the structure, or make it unfit for its intended purpose by affecting one of its constituent elements or items of equipment, even where they result from a defect in the ground. Liability is strict: the project owner does not have to prove fault, and the builder is only exonerated by proving that the damage results from an external cause (Article 1792 of the French Civil Code).
A mere departure from the contract is not enough. According to the Paris Court of Appeal, "mere contractual non-conformity does not fall within the scope of Article 1792 of the Civil Code unless it undermines the soundness of the structure or makes it unfit for its intended purpose" (our translation) (CA Paris, pôle 4, ch. 6, 19 December 2025, No. 23/06683). In the same case, it applied the ten-year warranty to a sliding bay window installed without the planned lintel, because of the structural risk identified by the expert.
Compensation covers the consequences of the defect: "all damage, material and non-material, resulting from the defects in the structure must be made good by the builder bound by the warranty" (our translation), including the costs of rehousing, furniture storage and removal (Cass. 3e civ., 3 April 2025, No. 23-16.055). Any clause that excludes or limits this liability is deemed unwritten (Article 1792-5). The builder is released from this liability ten years after acceptance (Article 1792-4-1). The firm relies on the expert assessment to establish how serious the defect is. See our article on construction defects and the ten-year warranty.
How do I make a claim on building defects insurance (dommages-ouvrage)?
By sending the insurer a claim notification, which starts strict time limits running. The insurer has a maximum of sixty days from receipt of the notification to notify its decision on the principle of cover. If it accepts, it presents a compensation offer within a maximum of ninety days, also running from receipt of the notification, payable within fifteen days of its acceptance by the insured. If it fails to meet these time limits or makes a manifestly inadequate offer, the insured may, after notifying the insurer, incur the expenditure needed for the repairs, and the compensation is automatically increased by interest equal to twice the statutory interest rate (Article L. 242-1 of the French Insurance Code).
Case law gives weight to these time limits. The insurer must respond within sixty days to any claim notification, even if it considers that the defects have already been reported, failing which it can no longer rely on the two-year limitation period (Cass. 3e civ., 30 September 2021, No. 20-18.883). If it has accepted cover within that time limit, it can no longer dispute it on the ground that the defects are not of a ten-year nature, and must fund the work needed to remedy them (Cass. 3e civ., 3 April 2025, No. 23-16.055).
The insured's action against the building defects insurer is time-barred two years after the event giving rise to it (Article L. 114-1 of the French Insurance Code): a late notification or a summons served too slowly can jeopardise everything. The firm drafts the notification, checks the insurer's response dates and challenges refusals in court. See our article on the statutory time limits of the building defects insurer.
The contractor had no ten-year liability insurance: what are my options?
The obligation is clear: anyone whose ten-year liability may be engaged must be covered by insurance and provide proof of this when any work starts on site, and the policy is deemed to include a clause ensuring "that cover is maintained for the duration of the ten-year liability" (our translation) (Article L. 241-1 of the French Insurance Code). Failure to take out insurance is punishable by up to six months' imprisonment and a fine of 75,000 euros, or one of these two penalties, except for an individual who builds a dwelling to live in themselves or for occupation by their spouse, their ascendants or descendants or those of their spouse (Article L. 243-3).
Several routes are available. Building defects insurance, if it was taken out, pre-finances repairs of damage of a ten-year nature without any determination of liability (Article L. 242-1). The contractor remains liable, but it may be insolvent or may have disappeared. The manager can then be pursued: the Court of Cassation overturned a court of appeal judgment that had not examined whether the manager "had not committed faults separable from his corporate duties, engaging his personal liability, by failing to conclude a contract for the construction of a private house and to take out ten-year liability insurance" (our translation) (Cass. 3e civ., 7 June 2018, No. 16-27.680). The judgment did not find the fault established: it requires the court to examine it.
If a certificate exists, it must be checked that it covered the activity carried out and the date work started on site, and then the direct action against the liability insurer must be brought (Article L. 124-3). The firm gathers this information before issuing a summons. See our article on craftsmen without ten-year liability insurance.
The building work is running late: can I claim late-completion penalties?
Yes, if the contract provides for them, and damages if it does not. The debtor is ordered to pay damages for delay in performance, unless it proves force majeure (Article 1231-1 of the French Civil Code). A clause setting a penalty per day of delay is a penalty clause: the court may, even of its own motion, reduce or increase it if it is manifestly excessive or derisory and, except in the case of definitive non-performance, it is only incurred after formal notice (Article 1231-5 of the French Civil Code). Formal notice is therefore the first step to take.
The Rennes Court of Appeal illustrates the two stages of the reasoning. It held that a roofing company "cannot rely on force majeure to explain this delay" (our translation), since it had not anticipated the difficulties in obtaining materials, then found the penalty "manifestly disproportionate since it corresponds to 30% of the contract price" (our translation) and reduced it from 175,789.10 euros to 27,044.47 euros (CA Rennes, 4e ch., 20 November 2025, No. 24/03749). The level retained is a matter for the court's assessment in each case.
For a private house under the regulated contract, the contract must state the date work starts on site, the completion time and the late-completion penalties (Article L. 231-2 of the French Construction and Housing Code); they may not be less than 1/3,000 of the agreed price per day of delay (Article R. 231-14), and the completion guarantor bears those corresponding to a delay exceeding thirty days (Article L. 231-6). The firm calculates the penalties, and claims or challenges them. See our article on late builders and the completion guarantee.
Contract for the construction of a private house (CCMI): what protections do I have?
This contract is mandatory for anyone who undertakes to build a residential building, or a building for combined professional and residential use, comprising no more than two dwellings intended for the same project owner, according to a plan they have proposed or had proposed (Article L. 231-1 of the French Construction and Housing Code). Its rules are mandatory rules of public policy (Article L. 230-1). The contract must, among other things, identify the plot of land, describe the substance and technical characteristics of the building, set a fixed and final price subject to any agreed revision, provide for the completion time and the late-completion penalties, and evidence the refund and completion guarantees (Article L. 231-2).
The completion guarantee covers the project owner, from the date work starts on site, against the risk of the work not being performed or being performed badly at the agreed price and within the agreed time. If the builder defaults, the guarantor bears the price overruns needed for completion, with an excess that may not exceed 5% of the agreed price, and the fixed penalties for a delay in handover exceeding thirty days (Article L. 231-6).
Where the contract is set aside, the question of demolition arises. According to the Court of Cassation, the court hearing an application for the land to be restored to its former state "must examine whether demolition of the structure built is a sanction proportionate to the seriousness of the defects and non-conformities affecting it", and "it is for the builder to prove the facts capable of establishing that the sanction is disproportionate" (our translation) (Cass. 3e civ., 27 May 2021, No. 20-13.204). In that case, the project owners' other claims, linked to the delay under a contract they had themselves withdrawn from, were rejected. The firm reviews the contract before signature and calls on the guarantees if the builder defaults.
Can I refuse to pay a contractor for defective work in France?
Partially, and in proportion to the failings. A party may refuse to perform its obligation, even where it is due, if the other party does not perform its own and if this non-performance is sufficiently serious (Article 1219 of the French Civil Code). The creditor of an obligation that has been poorly performed may also seek enforced performance, obtain a price reduction, bring about termination of the contract or claim compensation (Article 1217 of the French Civil Code).
Excessive withholding backfires on the party who resorts to it. According to the Bordeaux Court of Appeal, the defence of non-performance "must remain proportionate to the failing on which it is based, so that a project owner who withholds the entire price when the works can be used does so at their own risk" (our translation) (CA Bordeaux, 4e ch. com., 1 July 2026, No. 24/04144). In the same case, it held that "withholding half the price, i.e. 21,292.20 euros including all taxes, in addition to penalties, for defects whose remedial cost attributable to the contractor amounts to 960 euros, is manifestly disproportionate" (our translation), declared judicial acceptance of the works and ordered the project owner to pay the balance (CA Bordeaux, 4e ch. com., 1 July 2026, No. 24/04144).
Contractors have their own protections. Under a private works contract, the project owner must guarantee payment to them above a threshold set by decree; failing a guarantee, an unpaid contractor may suspend performance after a formal notice that has gone unheeded for fifteen days, except where the project owner is contracting on their own behalf to meet needs unrelated to a professional activity connected with the contract (Article 1799-1 of the French Civil Code). An architect or contractor who has undertaken, for a fixed price, to construct a building according to a plan settled and agreed with the landowner may not claim any price increase, either for a rise in the cost of labour or materials, or for changes not authorised in writing and whose price has not been agreed (Article 1793). The firm calculates the justified withholding or recovers the balance due.
How do I obtain a court-appointed expert assessment in summary proceedings (référé-expertise)?
By applying to the judge hearing summary applications before any trial. If there is a legitimate reason to preserve or establish evidence of facts on which the resolution of a dispute may depend, legally admissible investigative measures may be ordered at the request of any interested party, on an ex parte application or in summary proceedings. Where the measure concerns a property, the court of the place where it is located has sole jurisdiction (Article 145 of the French Code of Civil Procedure). The judge then appoints an expert to inform the court on questions of fact that require a technician's expertise (Article 232 of the same code).
The summons has a decisive effect on time limits. A claim brought before the court, even in summary proceedings, interrupts the limitation period as well as the foreclosure period (Article 2241 of the French Civil Code). On 22 October 2026, the Court of Cassation specified that the ten-year period "is interrupted by a summons in summary proceedings for an expert assessment, and starts running again for a full period of ten years from the order granting the investigative measure" (our translation) (Cass. 3e civ., 22 October 2026, No. 24-22.203).
The document must be complete. "The interruptive effect attached to a summons applies only to the defects expressly identified in it" (our translation), and a later application to extend the expert assessment to other defects interrupts nothing for the defects within the original remit (Cass. 3e civ., 2 May 2024, No. 22-23.004). Each defect must therefore be identified from the outset. The firm drafts the summons, proposes the expert's remit, attends the meetings and drafts the written submissions to the expert. See our article on proving building defects and the expert assessment.
What are the time limits for bringing a construction claim in France?
Almost all of them run from acceptance. Completion warranty: one year (Article 1792-6 of the French Civil Code). Warranty of proper functioning: at least two years (Article 1792-3). Ten-year warranty: ten years (Article 1792-4-1). Ordinary contractual liability against builders and their subcontractors: ten years (Article 1792-4-3). Against a subcontractor, the action is time-barred after ten years for damage falling under Articles 1792 and 1792-2, and after two years for the items of equipment covered by Article 1792-3 (Article 1792-4-2). Action by the insured against its own insurer, including the building defects insurer: two years from the event giving rise to it (Article L. 114-1 of the French Insurance Code). The victim's direct action against the builder's liability insurer "is, in principle, subject to the same limitation period as its action against the liable party" (our translation) and may be brought as long as the insurer remains exposed to a claim by its insured (Cass. 3e civ., 14 September 2023, No. 22-21.493).
These ten-year periods are foreclosure periods, which are stricter than a limitation period. According to the Court of Cassation, "the ten-year period for bringing an action against builders on the basis of Article 1792-4-3 of the Civil Code is a foreclosure period which, save as otherwise provided, is not governed by the provisions on limitation, and acknowledgement by the debtor of the right of the person against whom time was running does not interrupt the foreclosure period" (our translation) (Cass. 3e civ., 10 June 2021, No. 20-16.837). A promise by the contractor to redo the work therefore does not protect the project owner.
A claim brought before the court, even in summary proceedings, interrupts the foreclosure period (Article 2241 of the French Civil Code). Suspension during the expert assessment under Article 2239 does not apply to the ten-year period, but a summons in summary proceedings for an expert assessment starts a new ten-year period running from the order (Cass. 3e civ., 22 October 2026, No. 24-22.203). The firm draws up the timetable for each case from the first appointment.
Builder or contractor facing a claim: how can I defend myself?
First by checking the legal basis relied on. Ten-year liability does not arise if the builder proves that the damage results from an external cause (Article 1792 of the French Civil Code), and it covers neither defects subject to reservations at acceptance, unless they later become apparent in their full extent, nor mere non-conformity that affects neither the soundness nor the intended purpose of the structure (CA Paris, pôle 4, ch. 6, 19 December 2025, No. 23/06683). Equipment installed on an existing structure, where it does not in itself constitute a structure, falls only within ordinary contractual liability, which is not subject to the builders' compulsory insurance (Cass. 3e civ., 21 March 2024, No. 22-18.694).
A promise to redo the work does not extend the time limit. According to the Court of Cassation, "acknowledgement by the debtor of the right of the person against whom time was running does not interrupt the foreclosure period" (our translation) (Cass. 3e civ., 10 June 2021, No. 20-16.837); in that case, the agreement between the project owners and the contractor did not make their action against the insurer admissible.
Time limits are a serious line of defence: the action is foreclosed ten years after acceptance (Articles 1792-4-1 and 1792-4-3), and the summons only interrupts the period for the defects it identifies (Cass. 3e civ., 2 May 2024, No. 22-23.004). On the payment side, the contractor may demand the payment guarantee provided for by Article 1799-1 of the French Civil Code, and a project owner who unilaterally terminates a fixed-price contract must compensate the contractor for its expenses, its work and what it could have earned (Article 1794 of the French Civil Code). The firm defends businesses, their managers and project managers before the expert and the court, and calculates counterclaims for payment.
What are a construction lawyer's fees in Paris?
Fees are set out in a written fee agreement, in accordance with Article 10 of the law of 31 December 1971: before committing, you know what the assignment covers and what it costs. The agreement specifies the amount or the method of determining the fees covering the foreseeable work, as well as the anticipated costs and disbursements. The fixed fee is set after reading the relevant documents: works contract or quote, acceptance report, insurance certificates, correspondence with the contractor or the insurer.
The firm favours a fixed fee per stage: review of a works contract or a contract for the construction of a private house, assistance at acceptance, formal notice or reply, claim notification and follow-up with the building defects insurer, expert assessment in summary proceedings, attendance at expert meetings, proceedings on the merits, appeal. The costs of formal reports and expert assessments are added to the fees. Any new assignment gives rise to an amendment to the agreement, with no unexpected invoicing.
For a first opinion on documents, the preliminary case review at €80 incl. VAT, through the form on this page, leads to a written analysis within 24 working hours. First contact on +33 6 89 11 34 45.
References
Official texts and related pages
The sources for this page, checked on 31 October 2026, and the firm's related areas of practice.
Official texts
- Articles 1792, 1792-1 and 1792-2 of the French Civil Code: ten-year liability, builders, indissociable items of equipment
- Articles 1792-3, 1792-5 and 1792-7 of the French Civil Code: warranty of proper functioning, clauses deemed unwritten, professional equipment
- Article 1792-6 of the French Civil Code: acceptance of the works, completion warranty
- Articles 1792-4-1, 1792-4-2 and 1792-4-3 of the French Civil Code: time limits for actions against builders and subcontractors
- Articles 1217, 1219, 1231-1 and 1231-5 of the French Civil Code: remedies for non-performance, defence of non-performance, damages, penalty clause
- Articles 1793, 1794 and 1799-1 of the French Civil Code: fixed-price contracts, termination, contractor's payment guarantee
- Articles 2239, 2241 and 2242 of the French Civil Code: suspension and interruption of time limits
- Articles L. 241-1 and L. 243-3 of the French Insurance Code: compulsory ten-year liability insurance, criminal penalty
- Article L. 242-1 of the French Insurance Code: building defects insurance, insurer's time limits
- Articles L. 114-1 and L. 124-3 of the French Insurance Code: two-year limitation period, direct action against the insurer
- Articles L. 230-1, L. 231-1, L. 231-2, L. 231-6, L. 231-8 and R. 231-14 of the French Construction and Housing Code: contract for the construction of a private house, completion guarantee, late-completion penalties
- Articles 145, 232 and 835 of the French Code of Civil Procedure: investigative measure before any trial, expert assessment, interim payment in summary proceedings
- Article 10 of Law No. 71-1130 of 31 December 1971: fee agreement
Decisions cited
- Cass. 3e civ., 18 April 2019, No. 18-13.734: presumption of tacit acceptance
- Cass. 3e civ., 1 April 2021, No. 20-14.975: tacit acceptance ruled out where objections are consistent
- Cass. 3e civ., 21 March 2024, No. 22-18.694: equipment installed on an existing structure
- Cass. 3e civ., 30 September 2021, No. 20-18.883: sixty-day time limit of the building defects insurer
- Cass. 3e civ., 3 April 2025, No. 23-16.055: building defects insurer bound by its agreement, non-material damage
- Cass. 3e civ., 14 September 2023, No. 22-21.493: direct action against the liability insurer and time limit
- Cass. 3e civ., 7 June 2018, No. 16-27.680: manager, lack of ten-year liability insurance and separable fault
- Cass. 3e civ., 27 May 2021, No. 20-13.204: private house, demolition and proportionality
- Cass. 3e civ., 10 June 2021, No. 20-16.837: foreclosure period under Article 1792-4-3
- Cass. 3e civ., 2 May 2024, No. 22-23.004: interruption limited to the defects identified
- Cass. 3e civ., 22 October 2026, No. 24-22.203: expert assessment in summary proceedings and new ten-year period
- CA Paris, pôle 4, ch. 6, 19 December 2025, No. 23/06683: defects subject to reservations, non-conformity and ten-year warranty
- CA Rennes, 4e ch., 20 November 2025, No. 24/03749: manifestly excessive late-completion penalties
- CA Bordeaux, 4e ch. com., 1 July 2026, No. 24/04144: proportionate defence of non-performance and contract balance
Further reading
Building defects, an acceptance of works to prepare, a construction dispute under way?
The firm can be reached 24/7. Send the works contract or agreement, the acceptance report, the insurance certificates, photographs and your correspondence with the contractor or the project owner: Hassan Kohen reviews the acceptance, the nature of the defects and the time limits, then tells you the appropriate route: formal notice, claim notification, expert assessment in summary proceedings, legal action or defence.