Miscellaneous United Kingdom

Amber Construction Services Limited v Ilyrian Construction Ltd

Official source

Neutral Citation Number: [2026] EWHC 2603 (BP)

Case No: CR-2025-008633 and CR-2025-008682

IN THE HIGH COURT OF JUSTICE

BUSINESS AND PROPERTY DIVISION

INSOLVENCY AND COMPANIES LIST

Royal Courts of Justice, Rolls Building

Fetter Lane, London, EC4A 1NL

Date: 16/10/2026

Before :

CHIEF INSOLVENCY AND COMPANIES COURT JUDGE BRIGGS

– – – – – – – – – – – – – – – – – – – – –

Between :

AMBER CONSTRUCTION SERVICES LIMITED Applicant
– and –
ILYRIAN CONSTRUCTION LTD Respondent

– – – – – – – – – – – – – – – – – – – – –

– – – – – – – – – – – – – – – – – – – – –

Mr Nicholas Towers (instructed by Lawrence Stephens Limited) for the Applicant

Mr Michael Woollcombe-Clarke (instructed by Direct Access) for the Respondent

Hearing date: 2 October 2026

– – – – – – – – – – – – – – – – – – – – –

Approved Judgment

This judgment was handed down remotely at 10.30am on 16 October 2026 by circulation to the parties or their representatives by e-mail and by release to the National Archives.

………………………..

CHIEF INSOLVENCY AND COMPANIES COURT JUDGE BRIGGS

Chief ICC Judge Briggs:

Introduction

1. Amber Construction Services Limited (“Amber”) applies under rule 7.24 of the Insolvency (England and Wales) Rules 2016 for final injunctions. The injunctions would restrain Ilyrian Construction Ltd (“Ilyrian”) from presenting winding-up petitions founded on two statutory demands dated 15 November 2025. One concerns works at the Alton Estate in 2019. The other concerns works at Mander Court in 2021. Presentation has been restrained by consent since 22 December 2025.

2. The Alton statutory demand claimed £117,818.08 was due. That sum included interest at 12%. Ilyrian now relies on only £27,119.90 in respect of Alton and £39,329.00 in respect of Mander. It does not rely on the interest claimed in either demand.

The legal test

3. There was little of substance between the parties on the legal test. The court will restrain presentation of a winding-up petition where the debt on which it is founded is disputed on genuine and substantial grounds. Where the debt is so disputed the petition is bound to fail and its presentation is an abuse: Seaton Management Ltd v Evans-Jones [2024] EWHC 1883 (Ch) at [52], adopting Hildyard J in Coilcolour v Camtrex [2015] EWHC 3202 (Ch) at [31]-[33].

4. In Elevate Estates Management Ltd v Fine Star Ltd [2026] EWHC 1831 (Ch) at [25], the court explained that:

“The term ‘substantial’ demands that the arguments possess weight, something that can bear scrutiny. The test would require a case to survive being probed and turned over.”

5. The court does not decline to decide whether there are substantial grounds. It has to take a view whether on the evidence there really is substance in the dispute: Re a Company (No 006685 of 1996) [1997] BCC 830; Elevate [27]. Nor will a “cloud of objections” contrived to justify a factual enquiry suffice: Coilcolour at [35], quoted in Seaton at [52].

6. The same discipline applies to a cross-claim. In Re Bayoil SA [1999] 1 WLR 147 at 155, Nourse LJ said that the cross-claim “must be genuine and serious or, if you prefer, one of substance”. It must also equal or exceed the debt that is not itself disputed: Elevate at [34]. It is pertinent to say that it has long been recognised that although there are differences, the principles applied to personal and corporate insolvency are always closely related. In the bankruptcy regime where a demand may be set aside if the debtor has a “counter-claim, set-off or cross demand which equals or exceeds the amount of debt” the courts have followed the principles in Re Bayoil. Similarly corporate insolvency has looked at bankruptcy as its close legal neighbour to advance its jurisprudence. As examples, in bankruptcy a successful application is not dependent on an application establishing a legal set-off so as to provide a defence to the claim; a cross-claim is a wide term which includes legal and equitable cross-claims; a cross-demand is arguably wider still; there remains a requirement that the cross-claim must be raised in the same legal character as that in which the creditors’ claim is asserted so as to impose a requirement of mutuality; and a debtor is entitled to raise a cross-claim even in the teeth of a “pay now sue later” clause. In Garrow v Society of Lloyd’s [1999] BPIR 885, Robert Walker LJ observed and later agreed with the approach taken by the first instance judge:

“In his judgment Jacob J did not attempt to quantify Mr Garrow’s prospects of success in his counterclaim. The judge regarded that as a futile exercise. Instead he asked himself, following the guidance given by Nourse LJ in Bayoil [1999] BCLC 62, 71, whether the cross-claim was “genuine or serious or, if you prefer, one of substance”. The judge was prepared to assume that if the cross-claim succeeded the damages would at least equal Mr Garrow’s liability.”

7. As a further matter of principle, relevant to this matter, it is agreed between the partis that applicant should not be kept out of a cross-claim by a failure to litigate the cross-claim, but the court is entitled to take into account “the fact that a company has not even attempted to litigate the cross-claim, or that there are reasons why it has not done so”: Dennis Rye Ltd v Bolsover DC [2009] EWCA Civ 372 at [19].

8. Accordingly the term cross-claim is wide and the outcome of the cross-claim advanced in this case will be determined by an application of these principles.

9. Where part of the debt above the statutory minimum is indisputable, a petition may be presented even though the remainder is genuinely disputed: Re Tweeds Garages Ltd [1962] Ch 406, applied in Elevate at [30].

10. The Housing Grants, Construction and Regeneration Act 1996 does not alter these principles. An employer who has failed to serve a pay less notice may still raise a genuine and serious cross-claim in answer to a petition: Wilson and Sharp Investments Ltd v Harbour View Developments Ltd [2015] EWCA Civ 1030 at [65]-[66].

Alton

The Alton subcontract

11. By Order GN/6755 dated 10 September 2019, Amber engaged Ilyrian for pitched roof and roofline works at Alton Estate, Block C, London SW15. The fixed price was £9,370.81.

12. The order incorporated the JCT Standard Form of Domestic Sub-Contract 2011 and Amber’s Further Terms ref ACSL001. The anticipated commencement date was 12 September 2019 and the anticipated completion date 24 September 2019. There was some argument that as the contractual documents referred to “anticipated” the commencement date may have started later.

13. As Mr Towers rightly pointed out, the contract was to take 9 working days from the commencement which coincides with the “anticipated” dates. Further, a second and later document refers to the work starting on 12 September 2019. There is no contemporaneous or other evidence of any other date and, despite Mr Woollcombe-Clarke’s submissions that the work “may not have started” on that date, Mr Bokciu does not challenge the date in his written evidence.

14. It is common ground that Amber staff requested further work after 24 September 2019. The requests came from Lewis Brown (QS), Gary Nichol (assistant QS), Chris Bevan (site manager), Steve Mack and Colin Grainger (contracts managers). The items included additional mastic, labour, timber repairs, ceiling works at 5 Wanborough Drive, repositioning soil vent pipes and general snagging.

15. As an example of a small extra being requested, Amber wrote to Ilyrian on 6 January 2020:

“Could I please as (sic) you if you could send a cost through for the following… extend a soil vent pipe reposition of 2 number condense pipes and Installing a new hopper to the box gutter.”

16. In his first witness statement dated 19 December 2025 Mr Bokciu, a director of Ilyrian, refers to and accepts the contract and its terms. Mr Gunay, the Chief Executive and shareholder of Amber, refers to the contract and terms in his evidence.

17. The relevant terms are:

17.1. clause 6.1: the payment cycle;

17.2. clause 6.3: pay less notices, and deemed acceptance of a deduction not contested within 3 days;

17.3. clause 6.4: a valid application is a condition precedent to payment;

17.4. clause 9: only Mr Gunay may agree variations;

17.5. clause 14: within 3 days of notice of defects to attend site to carry out rectifications and failure may result in the subcontractor paying for such rectifications as are necessary;

The additional works

18. Given the contractual agreement to undertake the works in 9 working days there is on one view an overrun of 111 days, from 24 September 2019 to 13 January 2020. The cause of the overrun is disputed.

19. Ilyrian says it resulted from the additional instructions, the order value having nearly trebled.

20. In a witness statement carrying a non-compliant statement of truth and exhibited to the evidence of Mr Gunay, Mr Grainger (a contracts manager for Amber) says Ilyrian was under-resourced, its workmanship was poor and the delays were caused by the sub-contractor’s poor quality control.

21. The alleged poor workmanship gives rise to a major issue to be decided on these applications, namely a cross-claim raised by Amber.

22. On 14 November 2019 Mr Grainger served a Notice of Specified Default about the roof at 1-31 Norley Vale:

“Following on from my various e-mails regarding the works to the main roof of 1-31 Norley Vale, it has become apparent that you have defaulted under the terms of our agreed sub-contract ref GN/6755…This relates to the following: Clause 2.4.2 workmanship for the sub-contract works shall be of the standards described in the Sub-Contract Documents…We would also refer you to 2.17.1 that relates to the delays to the works surrounding this area and would also confirm that you are to proceed with the remedial works in a due diligent manner urgently”

23. It is apparent from the Notice of Specified Default that (i) the contract included works in respect of the main roof at 1-31 Norley Vale; (ii) Ilyrian’s works were not to the standards described in the Sub-Contract Documents; (iii) Amber contended that there had been delay under the contract, which commenced in September 2019; and (iv) a demand to carry out remedial works had been made. This is a contemporaneous document.

The payment applications

24. Ilyrian subsequently sent a payment application in December 2019 revised on 17 January 2020. This payment application is referred to using various dates in December and various different terms. I shall refer to the applications as a composite “Payment Application” in an attempt to reduce confusion.

25. It is common ground that it relates to works carried out at the Alton Estate that comprised additional works following the end of the initial contract period. The demand states:

“works carried out and completed in Application 1…Additional site manager, QS and contracts manager supplied outside of original order, 24 September 2019 to 13 January 2020.”

26. Ilyrian chased for payment on 27 January 2020 by e-mail:

“Hi Lewis/ Gary, Can you please advise when is this application being put for payment as it has been sent over to you on 19/12. Please advise as soon as you can, thank you.”

27. Amber says no application for payment of that date was received, only some schedules.

28. Amber argues that in any event the Payment Application is invalid under clause 6.4 of the contract. Mr Gunay, in his third witness statement, says:

“No valid application for payment has been submitted and no payment becomes due. There cannot be a notified sum as no valid application has been submitted.”

29. On Ilyrian's calculation the due date for payment under the Payment Application was 28 February 2020 and the final date for payment 11 March 2020. Mr Bokciu says:

“Even taking the 27 January 2020 as the payment application date, payment became due on the last business day of the month, following the application, which in this case was 28 February 2020. The final date for payment is contractually defined at clause 6.1 of the Supplemental Terms as 12 days after the payment due date, making the final date for payment 11 March 2020.”

30. It is common ground that the due date for payment is significant for the purposes of determining limitation under the Limitation Act 1980.

Amber’s notices and cross-claim

31. Amber pursues a cross-claim against Ilyrian. Its cross-claim, or its defence of equitable set off, as it was put, sounds in damages for delay. The claim did not emerge only after service of the statutory demand. It dates back to 2020. It was advanced with the notice of 6 April 2020. The attached schedule provided that Ilyrian owed £47,728.01 net of Amber’s valuation of Ilyrian’s account. The notice was sent again on 23 September 2020: “Mentor [Mr Bokciu] please see attached Alton Estate- Pay notice 23.9.20”. The schedule identifies scaffold hire (£15,624.04), replacement keys (£25), site management and quantity-surveying/contract-management time (£39,642.86), and overheads of £6,911.49.

32. Ilyrian relies upon emails in support of its argument that any delay was the result of additional instructions.

33. A letter written by Amber on 24 November 2025 refers to an e-mail sent by Ilyrian challenging the cross-claim, which Amber dates as 17 July 2020:

“On 17 July 2020 approximately three months after the contractually agreed deadline to dispute the set off your client sent an email raising various issues. Not only was your client’s notice out of time (not within three days) but it also lacked substantiation and detail. Further, your client’s application for payment is invalid and not compliant with Condition 6.4 of the sub-contract order.”

34. Mr Bokciu has much to say about the loss and expenses cross claim:

“52. Over the course of contract, several variations were instructed by Amber, bringing the total project cost to £27,119.90.

53. On 19 December 2019, Ilyrian submitted a payment application for that amount.

54. On 27 January 2020, Ilyrian chased for payment of that sum, re-attaching the same payment application.

55. On 06 April 2020, Amber issued a purported Payment Notice, with a purported claim for loss and expense of £62,203.39 (the “Loss & Expense Claim”).

56. Even taking the 27 January 2020 as the payment application date, payment became due on the last business day of the month, following the application, which in this case was 28 February 2020.

57. The final date for payment is contractually defined at clause 6.1 of the Supplemental Terms as 12 days after the payment due date, making the final date for payment 11 March 2020.

58. Amber was required to issue a Payment Notice no later than 5 days before the payment due date; i.e. by 23 February 2020.

59. The purported Payment Notice was, of course, far beyond the required 5 days to issue a Payment Notice under the contract and so was invalid.

60. In the absence of a valid Payment Notice or Pay Less Notice, the sum £27,119.90 became the “notified sum” and was required to be paid by the final date for payment: ss. 110B and 111(1) of the Housing Grants, Construction and Regeneration Act 1996 (the “Notified Sum”).

61. The £27,119.90 is, therefore, an undisputed liquidated sum that has been due since 11 March 2020.”

35. Amber does not deny this specifically. It says the cross-claim deduction was deemed accepted under clause 6.3. Mr Bokciu states in his written evidence:

“Hassan says that the Loss and Expense Claim was due to the works being completed over “three months beyond the anticipated completion date… That is a lie”

36. The position taken by Mr Gunay remains:

“The Alton Estate Works were completed over three months beyond the anticipated completion date, causing the Applicant financial loss. A loss and expense claim of £62,203.39 was subsequently made. The Respondent accepted this claim by way of its failure to dispute the same within the contractually prescribed period. The subsequent challenge, raised three months later, was both out of time and non-compliant with the form required under the contractually agreed terms.”

Alleged estoppel

37. Mr Woollcombe-Clarke submitted a proposition that a non-compliant notice is capable of being a good notice if an estoppel arises:

“An unequivocal acceptance of the particular application as valid, followed by a valuation and notice without reservation, can found an estoppel.”

38. Although an estoppel was mentioned in oral argument, Ilyrian’s written submissions make clear that it does not advance a separate estoppel case. No properly particularised representation, reliance or detriment has been identified. I therefore say no more about estoppel.

39. The arguments in summary are:

39.1. Whether there is a genuine and substantial cross-claim. The cross-claim is challenged for want of supporting documents and on the basis of an allegation that there was a representation made by Amber that the loss and expense claim had been wrongly issued. Amber says the deduction was deemed accepted by operation of clause 6.3.

39.2. Ilyrian claims the Payment Application is good whereas Amber says no compliant Payment Application; and

39.3. Amber raises an issue of limitation on the basis more than 6 years have elapsed since the Payment Application became due in March 2020.

40. As a general principle, the court must evaluate the available material sufficiently to determine whether the dispute is genuine and substantial. That necessarily requires scrutiny of the asserted grounds of dispute. It does not, however, permit the court summarily to resolve material conflicts of evidence which properly require disclosure, cross-examination or other incidents of a trial. The question is not which account is more likely to be correct, but whether Amber’s case has sufficient substance to cast doubt on the status of the creditor for the purpose of insolvency proceedings. Different considerations apply to a point of construction. Where a ground of dispute turns on the meaning and effect of a contractual term applied to documents whose content is not in issue, no evidence is required and the court can decide it on the application. That is the position with clause 6.4: the Payment Application either complied with it or it did not.

The Cross-Claim

41. The starting point is the default notice dated 14 November 2019. The evidence of Mr Grainger, to which I shall give the appropriate weight given the non-compliant statement of truth, is that he issued the default notice. There is no reason to doubt that he did so. His assertion that Ilyrian was resource poor and not managing the quality onsite together with the timing of the default notice supports the argument that it is genuine. In addition, there are the two notices of April and September 2020, and Amber’s letter of 24 November 2025 refers to Ilyrian’s e-mail of 17 July 2020 disputing the cross-claim. The cross-claim was therefore known by Ilyrian and live between the parties in 2020.

42. On the other hand, Amber has not given particulars of how the delay of 111 days was calculated, invoices or precise costing details in relation to the scaffold and management costs required to rectify Ilyrian’s alleged defaults.

43. In my judgment given the contemporaneous documents, the absence of detailed supporting materials does not deprive the cross-claim of substance. It is legitimate to have regard to why there has been a lack of documentation to support the cross-claim. What is known is that there has been a great lapse of time between early 2020 and service of the statutory demands. I infer from the lapse of time (over 6 years) since the events that documents may have been misplaced, servers changed, software updated, and employees and directors may have died, retired or moved to different employers. The inference goes to the supporting detail, not to the existence of the claim. The existence of the claim, its heads and the period of delay are established by documents created at the time.

44. Amber’s cross-claim is not established merely by the assertion of a figure of £62,203.39. It is supported by a contemporaneous notice of default, evidence alleging deficient workmanship and under-resourcing, and payment notices recording the deduction well before the statutory demands were served. The absence of a fully particularised allocation of the 111 days is a material weakness, but it does not render the cross-claim insubstantial. The cross-claim survived being probed: Elevate [25]. It cannot be said that represents a ‘cloud of objections’ contrived to justify an enquiry: Coilcolour [35]. The competing accounts of responsibility for delay and of what was subsequently said by Amber’s representatives cannot fairly be resolved on these applications. I therefore conclude that the cross-claim is genuine and serious or one of substance. At £62,203.39 it exceeds the £27,119.90 relied upon in respect of Alton.

45. Nor is the cross-claim displaced by the payment machinery of the 1996 Act. Mr Bokciu’s evidence is that, in the absence of a timely payment notice or pay less notice from Amber, £27,119.90 became the notified sum and is therefore undisputed. Even if that were right, it would not follow that the debt is one on which a petition may properly be founded. An employer who has not served a pay less notice may still raise a genuine and serious cross-claim in answer to a petition: Wilson and Sharp at [65]-[66]. Amber’s cross-claim is such a cross-claim, and it exceeds the sum claimed. It provides an answer to the Alton debt independently of my conclusions on clause 6.4 and limitation.

46. Amber has not litigated its cross-claim. The court is entitled to take that into account: Dennis Rye at [19]. Here the reasons are apparent. The cross-claim was signalled by the notice of specified default in November 2019 and quantified in the notices of April and September 2020. Ilyrian, for its part, did not pursue the Payment Application by claim or adjudication. The circumstances suggest a stand-off in which neither party was prepared to litigate and a status quo was reached. In that context Amber’s failure to sue casts no doubt on whether the cross-claim is genuine.

47. I should add that the assertion that Lewis Brown told Ilyrian that Amber’s cross claim had been wrongly issued can only be resolved in a different forum. It does not deprive the cross-claim of substance. Similarly, the assertion that Mr Gunay represented it would be disregarded is just an assertion and Mr Bokciu’s accusation of the “lie” supports the finding of substantial dispute: one that can only be determined using the full machinery of a trial.

The Payment Application

48. In my judgment the Payment Application was not a valid application under clause 6.4 and was not capable of becoming a default payment notice. The question is one of construction applied to documents whose content is not in dispute. It requires no evidence and I decide it.

49. Clause 6.4 renders invalid any payment notice that fails to comply with its terms. It reads:

“It is a condition precedent to payment that an application for payment has first been submitted by the sub-contractor at least 28 days before the payment becomes due. In order for the application to be a valid application it must be addressed to the contractor, quote the order number, job title, site address, detailed description of the work applied for and a full build-up of the sums claimed.”

50. A “full build-up” is reflected in condition 3 of the contract namely, that works beyond the order value will not be paid for unless an addendum order is issued. I would need to hear further argument as to whether this represents a separate ground for finding a genuine and substantial dispute however, it is not necessary for the purpose of this judgment nor will it affect the outcome.

51. The letter referred to above dated 25 November 2025 stated that Ilyrian’s Payment Application was invalid as it was not compliant with condition 6.4. The clause is in mandatory terms. A valid application is a condition precedent to payment, and the clause itself defines what a valid application must contain. The timing requirement is met: the application was submitted in December 2019 and revised on 17 January 2020, more than 28 days before 28 February 2020. The content requirements are not. The Payment Application itself was not addressed to Amber, did not quote the order number GN/6755, and did not state the job title, or site address (although it did refer to 1-32 Norley Vale).

52. Mr Woollcombe-Clarke submits that clause 6.4 was satisfied in substance because the intended surveyor received a named Alton application that included the work location, Norley Vale.

53. Mr Towers referred to Mannai Investment Co Ltd v Eagle Star Life Assurance Co Ltd [1977] AC 749 and the “pink paper” requirement, that if formal requirements for a notice are not met, it is invalid. The case was only mentioned in oral argument. It was not one of the 16 authorities in the authorities bundle nor was it one of the two cases passed to me during the hearing. In short, it was not produced for the court or for Mr Woollcombe-Clarke. Mr Woollcombe-Clarke had no opportunity to respond to the argument. I therefore say no more about it.

54. In his written submission Mr Woollcombe-Clarke stated:

“19. A payment notice must comply with statutory and any more restrictive contractual requirements in substance and form; omission of contractually required work identifiers and a corresponding purchase-order reference defeated a default application in Netomnia Ltd v MJ Quinn Integrated Services Ltd [2026] EWHC 1824 (TCC).”

55. The Netomnia case concerned a claimant that operated a fibre-optic network and the defendant was a contractor engaged under a master agreement. The defendant submitted an application for payment for £3,770.84 but omitted the purchase order number, Polygon ID, and Feature IDs. An adjudicator found the application for payment valid, but the claimant challenged this decision. The court held, among other things, that the application for payment failed to satisfy clause 6.5.4 because the Polygon ID and Feature IDs were reasonably required information to verify accuracy given the nationwide operation involving multiple exchanges, polygons, features, and contractors, with numerous low-value applications requiring rapid processing.

56. Netomnia Limited is authority for the proposition that where there is a written agreement between parties with an agreed payment regime including content requirements in payment notices, the courts will enforce it as written. Content requirements cannot be disregarded simply because the recipient understands that payment is being sought.

57. Context supports that construction. The evidence indicates that Amber is and was a substantial contractor operating numerous projects simultaneously. In that operational context, requirements identifying the purchase order, project and site were capable of serving a real verification function.

58. In my judgment the Payment Application was invalid because (i) it failed to comply with the mandatory requirements of clause 6.4 and (ii) read objectively and in context, those requirements (including that the application be addressed to the contractor) mandated information that was reasonably required.

59. A payment application that failed to be addressed to Amber may easily have been overlooked or not passed on. A payment application that failed to quote an order number has the potential of preventing Amber from carrying out a verification process: verifying the order, cross-checking payments made against the order and raising timely objections if objections were needed. A failure to provide the job title, site address or provide a “detailed” description of the work similarly affects the verification process.

60. In Mr Woollcombe-Clarke’s written submissions he submitted that the correspondence of Amber did not “expressly invoke clause 6.4” and:

“47. Amber’s assessment is evidence that it understood an Alton payment account; Ilyrian relies on that contemporary treatment to construe clause 6.4 objectively, without asking the Court to infer a separate estoppel in the absence of evidence that Ilyrian changed position in reliance on a communicated acceptance of the 17 January application.”

61. I have found that the requirements of clause 6.4 are mandatory and, in context, reasonably required. Amber’s assessment of the account does not alter the meaning of the clause. Post-contractual conduct is not admissible as an aid to construing a written contract. Absent an estoppel, which Ilyrian disclaims, a valuation by the payer cannot convert an invalid application into a valid one.

62. In his written submission Mr Woollcombe-Clarke argues:

“55.If the Court finds that the received package complied with clause 6.4 and unambiguously related to the 28 February due date, it should hold that the application became the default notice under section 110B(4) and that £27,119.90 was the “Notified Sum” payable under section 111(1) and (2)(c) of the Act.”

63. Given the failure to comply with clause 6.4 I find that the sum of £27,119.90 did not become due.

Limitation

64. If, contrary to my conclusion above, the Payment Application was valid and £27,119.90 became payable under the contractual payment machinery, Amber submits that the claim is now statute-barred: Limitation Act 1980, section 5.

65. Ilyrian’s evidence identifies 11 March 2020 as the final date for payment. A different date, 4 March 2020, appears in its written submissions, while December 2020 was mentioned in oral argument without supporting analysis. For present purposes I adopt 11 March 2020 because it is the latest date supported by Ilyrian’s evidence and therefore the date most favourable to Ilyrian on limitation.

66. Any contractual claim on the interim payment application therefore became statute-barred at the expiry of 11 March 2026 at the latest.

67. In oral submissions Mr Woollcombe-Clarke handed up a single page containing the final payment provisions of the JCT subcontract. Mr Towers did not object to its use. Clause 4.12.2 provides:

“Not later than 5 days after the due date, the contractor shall send the Final Payment Notice to the Sub-Contractor. The Final Payment Notice shall show the Final Sub-Contract Sum, calculated in accordance with whichever of clause 4.3 or 4.4 applies, less the total amount previously due as interim payments under this subcontract and (without affecting the rights of the subcontractor in respect of any interim payment not paid in full by the contractor by its final date for payment) the final payment shall be the difference (if any) between the two sums. The difference shall be shown in the final payment notice as a balance due from the contractor to the subcontractor or from the subcontract to the contractor as the case may be, and the final payment notice shall state the basis on which the amount has been calculated”

68. Ilyrian submits that a failure to pay an interim payment postpones the start of the limitation period until the Final Payment Notice is served. No authority was cited for that proposition. It therefore turns on the construction of the clause. I shall use the usual tools of construction, the reasonable reader, paying close attention to the text as the JCT contract is drafted by a body representing the industry and has been revised over many editions by professionals: Arnold v Britton [2015] UKSC 36, [2015] AC 1619 at [15], [20] and Wood v Capita Insurance Services Ltd [2017] UKSC 24 at [10] to [13].

69. As I mooted at the hearing without demur, a cause of action is “simply a factual situation the existence of which entitles one person to obtain from the court a remedy against another person”: Letang v Cooper [1965] 1 QB 232 at 242, per Diplock LJ. A claim to an interim payment is a claim in debt. The cause of action accrues when the sum falls due and is not paid. Each interim payment is a debt distinct from the final payment.

70. I prefer the submission of Mr Towers for three reasons. First, nothing in clause 4.12 suspends or defers a cause of action that has already accrued. A reasonable reader would expect clear words before giving a payment mechanism that effect, and there are none. Secondly, the words “without affecting the rights of the subcontractor in respect of any interim payment not paid in full by the contractor by its final date for payment” preserve the right to an unpaid interim payment on its existing terms. They do not postpone it. Lastly, the Final Payment Notice shows the Final Sub-Contract Sum “less the total amount previously due as interim payments”. An interim payment that was due but unpaid is deducted in arriving at the final balance; it is not carried into it. Such a sum is recoverable only as an interim debt. Once that claim is statute-barred, the final account does not revive it.

71. No proceedings or adjudication were commenced before expiry of that period and no acknowledgment argument advanced. The consent order of 22 December 2025 restrained only the presentation of a petition. Nothing prevented Ilyrian from issuing a claim or referring the dispute to adjudication in the eleven weeks before the period expired. Service of a statutory demand is not the bringing of an action and did not stop time running.

72. Accordingly, on the assumption that the evidence of Mr Bokciu that the cause of action accrued no later than 11 March 2020 is correct, Ilyrian has no enforceable debt upon which it may found a petition presented after 11 March 2026.

Conclusion on Alton

73. Ilyrian has no debt of £27,119.90 capable of supporting a winding-up petition. The reasons are, firstly, that the Payment Application failed to comply with the mandatory requirements of clause 6.4. It was not a valid application and did not give rise to a notified sum payable under the contractual and statutory payment machinery.

74. Secondly, and independently, Amber has established a genuine and serious cross-claim arising from alleged delay, under-resourcing and defective workmanship. That claim is supported by contemporaneous material, including the notice of specified default served in November 2019. Although its quantification is open to criticism, the cross-claim cannot fairly be rejected on an application to restrain presentation of a winding up petition.

75. Thirdly, even assuming in Ilyrian’s favour that its cause of action accrued when Mr Bokciu says it did, Amber has a substantial limitation defence. No proceedings were commenced by 11 March 2026, and Ilyrian has not identified a later accrual date supported by the contractual payment provisions.

76. I therefore grant a final injunction restraining Ilyrian from presenting a winding-up petition founded upon the Alton statutory demand.

Mander Court

77. Amber employed Ilyrian as a sub-contractor for works to be undertaken at Mander Court in 2021. The contract was made orally.

78. So far as relevant, the Mander statutory demand states:

“The debt is a result of works carried out on Mander Court which remain unpaid to date. These works were certified on 26 April 2021 and payment of £39,329.00 was to have been paid in full by 31 October 2025…”

79. The demand also claimed interest at 12%, which Ilyrian no longer pursues.

The Mander Application

80. Mr Bokciu’s evidence is that Ilyrian submitted a payment application for £39,834.00 “On, or prior to, 08 April 2025”. In context the year must be 2021. On 14 April 2021 Mr Dean Hall, a Senior Quantity Surveyor at Amber, “provided his assessment of the amount due and asked Ilyrian to submit a revision, reflecting his adjustments, so that it would withstand client scrutiny”.

81. The revision was submitted on 26 April 2021 (“the Mander Application”). On 27 April 2021 Ilyrian asked whether it could be paid that week. Mr Hall replied:

“It’s very unlikely as we generally have to have payments in the tray for sign off the week before. But will ask the question and advise”

82. Mr Bokciu concludes:

“In other words, it is clear that by (at least) 26 April 2021, the parties had agreed the valuation of the works at £39,329.00, following Amber’s assessment and Ilyrian’s revised payment application.”

83. Mr Gunay disputes both the validity of the Mander Application and the agreement Mr Bokciu describes. He says the application “is not addressed to ACSL, it incorrectly refers to ‘Catherine House’, and it claims VAT without providing a VAT number”, and that “There is no agreement as to the quantum and value of the work done”. Mr Gunay dates the application 26 April 2021 in one passage and 24 April 2021 in another; Mr Bokciu dates it 26 April 2021.

84. There was communication between Ilyrian and Dean Hall of Amber in early April, and on or about 26 April 2021, Ilyrian applied for payment of £39,329 plus VAT for works. There is a distinction between valuing the works and expressly releasing any claim for defective works or breaches identified later.

85. Ilyrian’s suggestion that the defects were only invented by Amber in November 2025 in response to the claims is contradicted by contemporaneous documents. On 25 June 2021, Steve Mack of Amber wrote to Ilyrian, reporting that Amber’s client’s contractors had inspected Ilyrian’s works and said that they were “non-compliant”, such that any further payments to Ilyrian would be suspended pending investigation. A further email from Mr Mack dated 4 October 2021 explained the issue to Ilyrian:

“Mentor [Mr Bokciu] As explained I do not have a full report. There has been a report of poor workmanship at Mander Court which needs to be investigated. The most practical way to resolve this is to get FIRAS to attend so please provide a date.”

86. The key deficiencies now identified by Amber are the lack of fire certification (costing Amber £10,000), poor workmanship requiring rectification by third parties (costing £9,470) and causing additional overhead costs (£2,920.50). The total deductions by Amber were £22,390.50. The calculations being placed by Mr Gunay on an earlier version of the spreadsheet change the final figure, but the three deductions were all added at the end, rather than being amendments to the existing spreadsheet cells. Mr Gunay’s spreadsheet assessed the total sum due to Ilyrian at £11,765.50, but if the later version of the spreadsheet with a total of £39,329 is used, the net amount would be slightly higher, at £16,938.50.

87. The figures differ. The original application was for £39,834.00. The demand and Mr Bokciu put the sum at £39,329.00. Mr Gunay says that Ilyrian “claims the sum of £41,828 is due”, a figure which appears in neither the demand nor Mr Bokciu’s evidence. Amber accepts that some sum is due. It puts it at £11,765.50, “conditional upon the Respondent submitting a valid application and providing FIRAS certification evidencing compliance”.

88. Amber’s later assessment sheet arrives at £11,765.50 by taking measured work of £34,156.00 and deducting £10,000.00 for “No fire certification provided”, £9,470.00 for rectification and £2,920.50 for overhead and profit. The rectification figure is supported by an “Application for Payment” from Conarg Ltd which runs to two lines and bears a blank job number.

Payment put on hold

89. Both witnesses say that payment was put on hold. They differ as to why, and by whom. Mr Bokciu says that Ilyrian chased payment on 20 May and 7 June 2021, and that:

“With no engagement, this was effectively put on hold, as we sought to find a pragmatic, commercial solution”.

90. On his account Amber was silent and the hold was Ilyrian’s choice. The letter of 7 June 2021 to Mr Motley is curious in that it demonstrates that payment was chased, it acted as a threat to take legal proceedings and Mr Bokciu was absent:

“Can I please have an update on some payments/ final accounts as I haven’t heard nothing from yourself and no payments has been made. Please note that Mentor was not available for couple of weeks but he authorised me to deal with this matter and contact solicitors to get involved again. Obviously I would like to avoid going this route but as you know preparations has been made to get legal steps in order to recover the outstanding amounts.”

91. Mr Gunay’s account is that Amber engaged and that the hold was Amber’s decision, taken because of defects. On 25 June 2021 Mr Steve Mack of Amber e-mailed Ilyrian:

“confirming that the client had identified the works carried out by the Respondent as non-compliant. On this basis, payment was put on hold.”

92. On 4 October 2021 Mr Mack e-mailed twice more, “requesting that he provide evidence by way of FIRAS certification, confirmation that the defects were resolved and a compliance certificate”. Mr Gunay says that FIRAS certification has never been provided. Mr Bokciu does not mention the e-mails of June and October 2021.

93. Three matters are common ground. First, Mr Gunay accepts that “some works were carried out at Mander Court”. Secondly, no sum has been paid by Amber. Lastly, neither party took any further step on the Mander account between October 2021 and the statutory demand of 15 November 2025.

The Ilyrian Construction & Everest Scaffolding Summary

94. Mr Bokciu says that in 2022 and 2023 he met Mr Robert Motley of Amber to discuss outstanding debts on various projects, and that this produced a document headed “Ilyrian Construction & Everest Scaffolding Summary – 09/08/2022”. He says that it records of Mander Court that payment was due as the “works were carried out”.

95. The summary also records that FIRAS certification had recently been supplied:

“No order in place but works were carried out and FIRAS certification recently provided”

96. Mr Gunay had not seen the document before. He is “unaware of its origins and [has] no knowledge as to where the comments have come from”. He notes that it is dated August 2022 although meetings are said to have taken place in 2023, and says that “there is no agreement as to the costs stated therein”.

Mr Gunay’s position

97. Mr Gunay says that regardless of the challenge made to the application for payment, given Amber’s assessment of £11,765.50 Ilyrian is not a creditor of Amber as any sum owed by Amber to Ilyrian in relation to Mander Court:

“is offset by the sum due from the Respondent to the Applicant in respect of the Alton Estate in the sum of £47,728.01”.

Discussion

98. Three questions arise. First, whether Amber’s deductions have any substance. Second, if only in part, whether the undisputed balance exceeds the statutory minimum. Third, whether the Alton cross-claim exceeds the Mander debt.

99. In my judgment Amber’s deductions do not bear scrutiny, save to a limited extent in respect of fire certification. A substantial part of the Mander debt is therefore not genuinely disputed. The cross-claim nonetheless exceeds the whole of it.

100. The reasons in respect of fire certification are these. Firstly, “No fire certification provided” conflicts with the record in the 2022 summary that FIRAS certification had recently been supplied. Mr Gunay says he does not know the document’s origins, but he does not say that Mr Motley as agent of Amber, did not write it. Secondly, the e-mails of June and October 2021 show a genuine concern about compliance, but Amber does not reconcile them with the later record. Thirdly, Ilyrian has not produced the certificate in these proceedings and Amber says that it does not have it. There is, however, nothing in the evidence to explain or support a deduction of £10,000.00 which contradicts the 2022 summary. I have regard to the argument that Mr Gunay says he has not seen the certificate, however that does not mean that Amber did not receive the certificate as stated in the summary.

101. The deduction of £9,470.00 for rectification rests on Conarg Ltd’s two-line application with a blank job number. It may relate to Mander Court, but Amber does not connect those lines to any identified defective installation. An unexplained third-party figure does not survive being probed. Mr Gunay’s evidence is general where specificity is required. Although events are some time ago the basis of the reduction should be available if it is to be relied upon.

102. I should mention that I draw a distinction between the evidence produced to oppose the Alton statutory demand and the Mander demand. The opposition to the Alton statutory demand was supported by various contemporaneous documents that demonstrated a genuine claim. In respect of the Mander demand no contemporaneous document records or quantifies the deductions for rectification or overhead and profit, and an inference cannot provide a connection that Amber has not itself asserted. Ilyrian has provided contemporaneous documents such as the e-mails of June, October 2021 and the 2022 summary concerning fire certification. The absence of documents produced to support deduction in the teeth of documents supporting Ilyrian’s claim leads to a finding that the purported deductions are not justified.

103. The deduction of £2,920.50 for overhead and profit is unparticularised and lacks substance.

104. Amber accepts that a sum is due but it is expressed to be conditional on a valid application. The acceptance is evidence that a valid application was made. I do not therefore accept that Ilyrian need remake a further application before payment is due.

105. In my judgment the Mander debt is not disputed on genuine and substantial grounds. The whole debt claimed in the Mander statutory demand is due and owing.

106. The cross-claim is genuine and serious for the reasons given above. On Mr Gunay’s own evidence the net Alton figure is £47,728.01. That exceeds the whole of the Mander debt of £39,329.00 by £8,399.01, and any lower undisputed balance by more. No part of the cross-claim is consumed by Alton, because the Alton debt is not due.

107. In his closing remarks Mr Woollcombe-Clarke stated that a valid cross-claim arising under the Alton statutory demand will not prejudice the Mander statutory demand. No authority was cited. The cross-claim need not arise under the same contract. It lies between the same parties in the same capacities. Neither party has litigated the Mander account. On Mr Bokciu’s evidence Ilyrian put it on hold; on Mr Gunay’s, Amber did so in June 2021. On either account it forms part of the stand-off, and Amber’s failure to sue on the cross-claim casts no doubt on it: Dennis Rye at [19]. Applying Re Bayoil, presentation of a petition should be restrained unless there are special circumstances. There are none.

108. I therefore grant a final injunction restraining Ilyrian from presenting a winding-up petition founded upon the Mander statutory demand.

109. I invite counsel to agree a draft order and seek to agree costs.

Our business lawyer in Paris assists clients in matters of this kind.


Open Justice Licence (The National Archives).

Neighbouring decisions

Preliminary case review

Send your documents. Receive an analysis.

Send us the documents in your case. Hassan KOHEN reviews them personally and sends you a first written analysis of your situation within 24 working hours.

  • Written analysis by the lawyer, €80 incl. VAT
  • Personal reply within 24 working hours
  • 100% confidential, legal professional privilege guaranteed
  • Up to 1 GB of documents in total, folders and sub-folders accepted
80 €incl. VAT

Preliminary review of your case. Review of your documents and a first written analysis by Hassan KOHEN within 24 working hours. Payment is made online after this form is submitted.

  • Up to 1 GB of documents in total, folders and sub-folders accepted
  • Secure payment, no card details stored
  • Terms and fee agreement

Click or drag your files here
All formats accepted (PDF, Word, images, etc.)

Sending...

Payment constitutes a request for immediate performance of your analysis. Your data is used solely to process your request.
Terms · Privacy policy.

IA juridique gratuite

Une question de droit ? Demandez à Judith.

Judith cherche dans les codes, la Constitution, la Convention européenne des droits de l’homme et les décisions des juges, puis vous montre les textes et les passages d’arrêts qui pourraient répondre à votre question, avec leur source officielle. Gratuite, sans compte, elle ne rédige rien à votre place. Découvrir Judith, l’IA juridique gratuite du cabinet.

Trois recherches par jour, sans compte. Votre question est enregistrée et relue par le cabinet pour améliorer l’outil : n’y mettez ni nom ni information sensible.