Persimmon Homes Limited v Harding Estates (East Anglia) Limited & Anor

Official source

Neutral Citation Number: [2026] EWHC 2481(Ch)

Case No: PT-2026-000201

IN THE HIGH COURT OF JUSTICE

BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES

PROPERTY TRUSTS AND PROBATE LIST

Royal Courts of Justice, Rolls Building

Fetter Lane, London, EC4A 1NL

Date: 30 September 2026

Before :

MASTER TEVERSON

(sitting in retirement)

– – – – – – – – – – – – – – – – – – – – –

Between :

PERSIMMON HOMES LIMITED Claimant
– and –
(1)
HARDING ESTATES (EAST ANGLIA) LIMITED
(2)
HIM PROPERTIES LIMITED

Defendants

– – – – – – – – – – – – – – – – – – – – –

– – – – – – – – – – – – – – – – – – – – –

Jonathan Seitler KC and Samuel Cathro (instructed by Walker Morris LLP) for the Claimant

Paul Downes KC (instructed by Hill Dickinson LLP) for the Defendants

Hearing dates: 30 and 31 July 2026

– – – – – – – – – – – – – – – – – – – – –

APPROVED JUDGMENT

This Judgment was handed down at 10.30am on 30 September 2026 by email to the parties’ legal representatives and by release to the National Archives.

MASTER TEVERSON :

1. I have before me an application for summary judgment made by the Defendants pursuant to CPR 24 by application notice dated 17 April 2026. The application seeks summary judgment for damages to be assessed and an interim payment on account of damages of £15,150,000.00 or otherwise in a sum to be assessed by the Court.

2. The application was listed for a 2 day hearing. It became apparent during the course of the hearing that there would be insufficient time for me to hear submissions on the interim payment part of the application. It was agreed that I should hear submissions on and give judgment on the summary judgment part of the application first. This Judgment is my reserved judgment on the summary judgment part of the Defendants’ application.

3. The Claimant (“Persimmon”) is a UK-based housebuilding company and subsidiary of Persimmon plc, a publicly traded company listed on the stock exchange.

4. The Defendants are part of a group of companies controlled and directed by Mr Peter Williams and his company, Williams Group.

5. By a Sale and Purchase Agreement dated 17 September 2021 (“the SPA”) the First Defendant (“Harding”) agreed to sell part of the land registered in its name at HM Land Registry under title number EX921621 to Persimmon for the sum of £9,785,000.00 (“the Property”). The Property had outline planning permission for up to 297 dwellings. The remainder of the land in title number EX921621 (“the Retained Land”) had full approval for the creation of retail shop units, a food store and a petrol filling station. These planning permissions were contained in a hybrid planning permission dated 8 June 2016 granted by Tendring District Council as Local Planning Authority.

6. Under the terms of the SPA Harding was “the Seller” and Persimmon “the Buyer”. The Second Defendant (“HIM”) was also a party to the SPA as the owner of land to the north of the A120 being the land registered at HM Land Registry under title number EX936191 (“HIM Land”).

7. The SPA was amended by a supplemental agreement dated 14 March 2022. The Statements of Case proceed on the basis that the Completion Date was 14 March 2022, being the date when the transfer of the Property was completed. This is defined in the SPA as the Actual Completion Date.

8. The scheme of the SPA was that the Claimant would procure that “the Works” were carried out and completed. “The Works” involved the construction of infrastructure (“the Infrastructure Works”) and drainage (“the Drainage Works”)th. The Infrastructure Works included the construction of a new roundabout on the A120 and a road referred to in the SPA as the “Spine Road”. The Drainage Works involved the construction of surface water and foul water drains and a foul water pumping station. The Works were to serve both the Property and the Retained Land as well as the HIM Land.

9. Under the terms of the SPA the Claimant was required to procure that the Works were completed within two years of the Completion Date. The Completion Date was defined to mean the 10th working day after the Unconditional Date. As stated above, the Statements of Case proceed on the basis that the Completion Date was 14 March 2022 and that the deadline for completing the Works was 14 March 2024. It is however arguable that the Completion Date was on the 10th working day after the occurrence of the Unconditional Date from which it would follow that the deadline for completing the Works was 28 March 2024. On behalf of Persimmon it was agreed that little turned on that point for the purposes of the Summary Judgment Application.

10. It was common ground before me that the Works were not completed by the contractual deadline whether that was 14 March 2024 or 28 March 2024. It is Persimmon’s case that it is entitled to an extension of time on the basis that the Defendants have unreasonably withheld their approval to what are claimed by Persimmon to have been requests made to move the Attenuation Pond as defined in the Particulars of Claim to a different location on the Site.

11. By clauses 3.1. and 3.1.3 of the SPA on the Completion Date the provisions of Schedule 2 (Infrastructure Works) should apply (but not further or otherwise).

12. Paragraph 2.1.1 of Schedule 2 provided:-

The Buyer shall at its own expense apply for and use all reasonable endeavours to obtain all Requisite Consents for the Works from time to time as may be appropriate before and throughout the course of the Works”

Paragraph 2.1.2 of Schedule 2 provided:-

“The Buyer shall keep the Seller informed of progress in obtaining any such Requisite Consents and on receipt shall provide copies of any Requisite Consents relating to the Works to the Seller (together with any relevant drawings)

Paragraph 2.1.4 of Schedule 2 provided:-

“Where the Highway Authority shall reasonably require the provision of Attenuation Ponds to be provided as part of the Infrastructure Works in order for the Buyer to secure the Requisite Consents for the Infrastructure Works then the Buyer shall use reasonable endeavours to limit the extent of the HIM Land and/or the Retained Land as may be required for any such Attenuation Ponds and shall not agree to the location of any such Attenuation Pond without the same having been previously approved by the Seller Provided That the Seller shall not withhold such approval where such location is reasonably required by any Relevant Body and there is no viable or reasonable alternative location.”

13. Paragraph 2.2.1 of Schedule 2 provided:-

“The Buyer will procure that the Works are carried out and completed:

(e) with due diligence and (subject to paragraph 8(delays) of this Schedule) to procure that Practical Completion of all the Works shall occur on or before the date 2 years from the Completion Date.”

Paragraph 2.2.4 of Schedule 2 provided:-

“The Buyer shall as soon as reasonably practicable following the Completion Date use all its reasonable endeavours to enter into an agreement with the Highway Authority pursuant to Section 38 and/or Section 278 of the Highways Act 1980 in relation to the future adoption of the Spine Road as a highway maintainable at the public expense and shall keep the Seller fully informed in relation to its progress in connection with the same and upon entry into such Planning Agreement the Buyer shall observe and perform it obligations contained in the same and shall use all reasonable endeavours to procure that the Highway Authority shall observe its obligations contained in the same”

Paragraph 8.2 of Schedule 2 Schedule provided:-

“The Buyer shall be entitled to an extension of time for completion of the relevant Works where it is delayed from carrying out and completing the same by reason of the Seller unreasonably withholding or delaying its approval to any matter which requires the Seller’s approval (including but not limited to the location of any Attenuation Ponds…”

14. There is a degree of overlap between paragraph 2.1.4 of Schedule 2 and the definition of “Attenuation Pond(s)” in clause 1.1 of the SPA. Attenuation Pond(s):-

“means such surface attenuation pond or ponds swales ditches and other like and ancillary or related facilities for the attenuation or storage of surface water as the local highway authority shall reasonably require in connection with the granting of any Requisite Consent in connection with the provision of the Infrastructure Provided That where any such ponds shall be required by the local highway authority then they shall be provided in such locations as the Buyer shall reasonably specify (having regard to the requirements of the local planning authority pursuant to Condition 13 of the Planning Permission) and which the Seller shall previously approve acting promptly and reasonably Provided That the Seller shall not withhold such approval where such location is reasonably required by any such authority and there is no viable or reasonable alternative location Provided Further That nothing in this Agreement shall infer an obligation on the Buyer to install any attenuation pond required or associated with any flood compensation scheme;”

15. Clause 1.3.1 of the SPA provided:-

“Unless otherwise expressly stated where a consent or approval is required from any party that consent or approval shall not be unreasonably withheld or delayed.”

16. Clause 1.3.2 of the SPA provided:-

“Unless otherwise expressly stated:

(a) if any one party shall seek the consent or approval of the other party pursuant to the terms of this Agreement such other party shall respond to any such request for consent or approval as to whether or not it shall give its consent or approval within 5 Working Days of such request being made;

(b) if the party to whom a request has been made for their consent or approval pursuant to the terms of this Agreement shall not provide such response within 5 Working Days the party requesting the other party's request or approval shall be entitled to serve a further request upon the other party requesting their consent or approval in relation to any matter included in the previous unanswered request and in respect of which consent or approval is required pursuant to the terms of this Agreement;

(c) if the party to whom a request for consent or approval shall have been made shall not respond within 5 Working Days of such further notice their consent or approval to the matter in respect of which a consent or approval has been requested pursuant to the terms of this Agreement shall be deemed to have been given;

(d) and for the avoidance of doubt requests for consent and responses to such requests may be sent by email in accordance with the provisions of this Agreement 1.3.3

Time shall be of the essence for the purposes of this Clause 1.3.2.”

17. It is convenient to set out the factual background by reference to the 1st witness statement of Peter Leslie Williams dated 17 April 2026 made in support of the Application and the 1st witness statement of Matthew Atton, Land Director of the Claimant’s Essex Division dated 29 June 2026 made in answer to the application . In so doing, I am not to be understood as making any findings of fact.

18. Harding acquired the Property in 2015 on a conditional basis subject to planning permission. Mr Williams then decided to fund the purchase himself on an unconditional basis. Planning permission was obtained in June 2016. This was a hybrid permission granted for the site as a whole. Mr Williams says this was for 590,000 sq. ft. Gross Internal Area (GIA) of commercial use, and in addition, 297 residential dwellings. He says the permission was “implemented” in June 2019.

19. Mr Atton says that Persimmon was contacted out of the blue by Mr Williams in April 2020. After a period of negotiation, heads of terms, including a purchase price were agreed on 17 June 2021. Mr Atton says the SPA was eventually entered into on 17 September 2021.

20. Mr Atton in paragraph 3.20 of his 1st witness statement summarises the infrastructure provision under the terms of the SPA that the Claimant was required to provide in the following terms:-

“(a) the creation of a new roundabout on the A120;

(b) a road including a further roundabout, linking the A120 to Stour Close at the southernmost point of the South Land;

(c) A Foul Pumping Station (although this is no longer required as Persimmon has relocated this onto the Persimmon Site, although a rising main is still required across the South Land to connect to the existing foul drainage network);

(d) Foul water drainage apparatus required to drain foul water from the Persimmon Site to the Foul Pumping Station (as set out above this is no longer required);

(e) Surface water drainage apparatus required to drain surface water from the Persimmon Site to the watercourse known as Ramsey Creek; and

(f) A surface water attenuation pond and ancillary or related facilities for the attenuation of surface water i.e., the Attenuation Pond.”

21. In paragraph 3.21 Mr Atton explains that as well as including obligations to carry out works in respect of this Infrastructure, Persimmon was also required to obtain the Requisite Consents for completing those works which included the entering into of appropriate adoption agreements. These included a Section 38 Agreement which relates to the construction of new roads and a Section 278 Agreement which relates to the construction and alteration of existing highway. The latter was required for the construction of the new roundabout on the A120; the former for the construction of the Spine Road.

22. In paragraph 4.6 of his 1st witness statement Mr Atton confirms that the hybrid planning permission and the drainage strategy approved as part of it provided for an attenuation pond on the Defendants’ land to the east of the proposed spine road and to the north of the consented filling station. In paragraph 4.7 Mr Atton says that the attenuation pond was to serve both the retail area on the Defendants’ land and part of the spine road to be constructed as part of the Section 38 Agreement.

23. It is apparent from the emails exchanged between Mr Doran, the Claimant’s technical coordinator, and Mr Tom Wilson of Stomor, Persimmon’s retained engineer, that as part of preparing the drawings for the new roads, Mr Wilson alerted Mr Doran to the need to relocate the attenuation pond. Mr Wilson issued a full set of drawings on 17 January 2022 and concluded that the only viable location for the attenuation pond was to the east of the petrol filling station. It was appreciated this would have some impact on the Retained Land.

24. In paragraphs 3.22 of his 1st witness statement Mr Atton says that he was told by Mr Williams that Mr Ed Saunders would be his contact at the Defendants with responsibility for the Harwich site. Mr Saunders was described as “Head of Asset Management” in his email signature. Mr Atton started to communicate with Mr Saunders by email in August 2021. Mr Williams says in paragraph 48 of his 1st witness statement that Mr Saunders “may well have been the appropriate person for Persimmon to deal with over the relocation of the Attenuation Ponds”. Mr Williams says that Mr Saunders left the First Defendant shortly after the SPA was signed, on 17 December 2021.

25. Mr Atton says in paragraph 3.29 of his 1st witness statement that at no point did Mr Saunders or Mr Williams inform him that Mr Saunders was leaving the Defendants’ employment before or after he had actually left. Mr Atton says that on 11 February 2022 being unaware that Mr Saunders had left the Defendants, he emailed his details to his colleague Jamie Doran to allow Mr Doran to take over conduct of the Works, as these were more suited to his role of technical coordinator and they were approaching the SPA completion date. In paragraph 6.7 of his 2nd witness statement dated 22 July 2026 Mr Williams says his memory is that he told Mr Atton at their meeting on 15 March 2022 that Mr Saunders had left the employment of Williams Group and that all future correspondence should be sent to him. Mr Williams accepts this is not an issue that can be resolved at this application.

26. In paragraph 3.31 of his 1st witness statement Mr Atton says that from then on, he is aware that Mr Doran sent Mr Saunders four separate emails, on 9 March 2022, 6 October 2022, 10 March 2023 and 18 October 2023, updating him on the progress of the Works and asking for his comments on the documents being produced.

27. The first email from Mr Doran to Mr Saunders sent on 9 March 2022 at 10.54 subject “Harwich A120 Roundabout and Link Road” stated:-

“Hi Edward,

I am the Technical Coordinator at Persimmon working on Harwich and just wanted to keep you in the loop with the progress on the A120 roundabout and Link Road.

The Link road has been submitted to Essex Highways and an Engineer assigned.

Highways England are progressing with the A120 roundabout and we have fortnightly meetings if you want to be involved.

I have included a link to all the working drawings, although please be aware these are subject to change throughout the technical approval process.

https://we.tl/t-6vXNQfL7Ae

If you have any questions, or want to be involved in the design meetings, just let me know.”

28. The second email from Mr Doran to Mr Saunders sent on 6 October 2022 at 09.31 subject “Harwich A120 Roundabout and Link Road” stated:-

“Hi Edward,

Just wanted to update you on the Harwich A120 roundabout and link road designs.

Please find links below to both the S278 and S38 link road designs.

https://we.tl/t-CjSoXRjzjm

These are both going through the Technical Approval process and have had a couple of sets of comments.

Let me know if you have any queries.”

29. The third email from Mr Doran to Mr Saunders sent on 10 March 2023 at 12.32 subject “Harwich A120 Roundabout” stated:-

“Hi Edward,

Just wanted to update you on the National Highways A120 roundabout in Harwich.

We are nearing technical approval and the legal agreements are being drafted.

As Harding Estates own land to be dedicated, they will need to be party to the agreement and so solicitors will be in contact shortly.

In the meantime, please find the latest pack of drawings below and if you have any queries, let me know.

https://we.tl/t-zdNBgS5kVP”

30. The fourth email from Mr Doran to Mr Saunders sent on 18 October 2023 at 10.05 subject “Harwich A120 Roundabout and Link Road” stated:-

“Hi Edward,

As an update, please find the link below to the latest Harwich A120 roundabout and link road designs for the development off Stour Close.

Both packages have now gone through multiple sets of comments and we are nearing technical approval.

S278

https://we.tl/t-57ogD7eCEx

S38 Link Road

https://we.tl/t-3XnKgU4RKg

Please let me know if you have any comments.”

31. In paragraph 49 of his 1st witness statement Mr Williams says that he made enquiries and understands that an automatic response email was set up by their IT provider (Total Group) at around the time that Mr Saunders left their employment with any emails being forwarded to a different account. Mr Williams says that the response email would inform the sender that their email had been forwarded on to the email address [email protected].

32. Persimmon contests this. It relies on the witness statement dated 29 June 2026 of Mr Paul Wright, an IT Infrastructure Services Manager at Persimmon’s head office in Fulford, York. Mr Wright sets out the email searches he has made. He confirms that he found no evidence of any response being received by Mr Doran to the Emails from any address ending in “@williamsgrp.co.uk”. Mr Williams in his 2nd witness statement dated 22 July 2026 at paragraph 6.7 accepts that the issue of whether there were ‘bounce back’ emails cannot be resolved at this application.

33. For the purposes of this application I must proceed on the basis that Mr Doran received no automatic response emails and that Persimmon did not know that Mr Saunders had left the Defendants’ employment. Mr Williams says that the Emails were forwarded internally to [email protected]. Mr Williams described this as an inactive account in an email to Mr Atton sent on 18 March 2024 at 5.10pm. However, an email using that account [1497] was sent by Mr Williams to Mr Atton on 4 May 2022 at 11.06 am. I must therefore proceed on the basis that at the time of at least the first email the account was in use and emails sent to it were in the inbox of that account and available to be read.

34. The Emails contained links to plans or drawings. Those links are no longer active. Mr Atton says in paragraph 4.22(d) of his 1st witness statement that the revised position of the attenuation pond was shown in the plans submitted to Essex County Council and also sent to Mr Saunders for comment and approval on 2 March 2022. This appears to be a mistaken reference to the email sent to Mr Saunders on 9 March 2022.

35. In February 2023 Mr Atton and Mr Williams exchanged emails in anticipation of Reserved Matters Approval being granted.

36. In an email sent on 14 July 2023 Mr Atton informed Mr Williams:

“As discussed yesterday, we are close to getting technical approval for the new roundabout on the A120 however, Highways England have last minute insisted on a requirement to undertake a substantial design change to require us to provide granulated fill across a wider area beyond the roundabout that has had significant cost implications.

Having acquired the site back early last year, we are keen to begin development and whilst we were hoping that we would begin development in September this is likely to not begin until October now.”

37. On 18 October 2023 Mr Atton emailed Mr Williams saying that they had been trying to get Highways England’s technical approval for the Section 278 works, the proposed new roundabout on the A120. In the fourth paragraph of the email Mr Atton stated:-

“We are aware of our contractual obligations to get this installed and fully appreciate that if we are to default on the timescales that this is likely to [be] met with an application of costs.”

38. In an email sent on 19 October 2023 to Mr Atton Mr Williams asked Mr Atton to liaise with his Board with a view to agreeing and documenting a pre-emptive basis of moving forward.

39. In an email sent on 20 October 2023 to Mr Atton Mt Williams suggested that an extension for the completion of the Infrastructure Works be made from 13 March 2024 to 14 September 2024 in consideration of a sum of £2m plus VAT, payable immediately. He suggested that in the event the Works were not completed by 14 September 2024 that a further payment should be made of £1m plus VAT, due and payable on 14 September 2024.

40. Correspondence then followed in November 2023 between solicitors with Winckworth Sherwood (“Winckworths”) acting on behalf of the Defendants and Howes Percival (“HP”) on behalf of the Claimant. In their letter dated 13 November 2023 HP acknowledged that no construction work had yet taken place in connection with the Infrastructure Works. They said:-

“Our client has provided details about the progress of the works directly to your client but, for clarity, the delay lies with the Highways Agency not having provided technical approval of the drawings for the works required to the A120 roundabout to enable a s.278 agreement to be finalised and works to begin, despite our client endeavouring to expedite that consent.”

The letter continued in numbered paragraph 4:-

“Notwithstanding the above, our client does not agree that the construction period for the works is circa 9 to 12 months and this is not aligned with the contractors our client has contacted to undertake the work, who are experienced in works of this nature. Further (and even if the estimated period for the works was 9 to 12 months) your assertion that our client is in breach of the Agreement is incorrect. A breach will only arise if the 14 March 2024 date (or any later date pursuant to paragraph 8 of Schedule 2 of the Agreement) is passed and the Infrastructure Works remain incomplete.”

In numbered paragraph 11 it was stated:-

“Finally, we should advise you that we are being instructed to review correspondence passing between our clients by which our clients raised issues with your client relating to the delivery of the Infrastructure Works, to which your client has failed to respond. We shall be looking at whether our client is consequently entitled to an extension of time for the completion of the Infrastructure Works in accordance with paragraph 8(2) of the Agreement. We shall respond to you on this point in due course”.

41. By letter dated 12 January 2024 HP requested consent to an anticipatory extension to the deadline of 14 March 2024 from Winckworths by return. In numbered paragraph 3 HP said their current understanding was that there might be a six months delay. In numbered paragraph 5 Howes Percival said

Our client does not deny that, if there is a breach of the Agreement and your client suffers loss as a consequence of that breach, your client may be entitled to damages.

In paragraph 5.5 HP said:-

Our client acknowledges that your client may face cash flow problems as a result of any delay, which may limit its ability to wait for the completion of the Infrastructure Works. To assist with that, provided your client can provide clear evidence of losses which it is guaranteed to suffer as a result of there being any delay to the completion of the Infrastructure Works, our client will consider making a payment to your client to assist on a goodwill basis and without prejudice to the threatened action.

42. On 18 January 2024 Richard Hush, in the absence of Mr Atton, sent an email on behalf of Persimmon to Mr Williams saying they were working to determine the anticipated commencement and completion date for the Infrastructure works as had been requested by Winkworths by letter 18 January 2024.

43. On 8 March 2024 Mr Williams asked Mr Atton to send the Highways Authority drawings relating to the Spine Road and the roundabout within the estate to join Stour Close.

44. On 11 March 2024 Mr Atton sent an email to Mr Williams attaching the Section 38 drawings for the Link Road at the Site. On 12 March 2024 Mr Williams asked Mr Atton to forward the CAD drawings.

45. On 15 March 2024 Mr Williams sent an email to Mr Atton saying that the details had now been reviewed by his highways consultants. He said each of his consultancy practices had responded and that the contents were “not only disturbing but especially disappointing to read”. The attachments included an email from Andrew Bell of Focus Transport Planning commenting on the Section 38 drainage elements.

46. Mr Atton responded by email dated 18 March 2024 stating:-

“Whilst appreciate that your recently appointed consultants may have highlighted some amendments that you are now unhappy with, obviously your colleague Edward Saunders, who was the point of contact for these infrastructure works during contractual negotiations, would have been aware of the changes and iterations through the process, please see attached emails dated 9th March 2022, 6th October 2022, 10th March 2023 & 18th October 2023. I would have hoped if he was unhappy with the direction of travel he would have communicated this. Given that he has never responded or communicated to us given our timescales we have looked to progress this. Appreciate late last year, you picked this up when you were seeking to claim for losses however, obviously there was ample opportunity gifted by the attached correspondence to try and assist this process”

The four emails sent by Mr Doran to Mr Saunders were attached to Mr Atton’s email to Mr Williams.

47. Mr Williams replied by email on the same day stating that the delay in completing the Infrastructure Works was not of his making or choosing:-

The delay in completing the infrastructure works is not of my making or choosing in any way whatsoever and as you know very well, I have tried endlessly to establish a pragmatic outcome for both of us. This remains my wish today and it is the only way matters between us can be resolved expeditiously.

48. Mr Atton replied to Mr Williams by email on 19 March 2024:-

As far as I am aware, until now we have never said any of the delays were as a result of your making/choosing however, as discussed on our call it seems surprising to me that as of Friday evening issues with the s.278 and s.38 drawings were raised (as I had been told that Ed was being kept updated) and even more so now following your below email where you are saying your transport consultants have had the Essex Highways Drawings since November 2023. As you know I have not been personally involved in trying to obtain technical approval from the highways authority and was only brought back into this once you contacted me late last year and begun work on recovering your alleged losses.

Also until our conversation earlier today I have not been made that Ed is no longer within your organisation and I have specifically asked Jamie and he has advised he has no record on any bounce back emails being received or of Ed no longer working for your organisation

49. An all-parties call then took place on 5 April 2024. Mr Atton states in paragraph 3.56 of his 1st witness statement that by that point, the main focus was on the location of the Attenuation Pond. Mr Atton says in paragraph 6.1 of his 1st witness statement that:-

“To put the matter beyond any doubt Mr Williams confirmed both during the meeting of 5 April 2024 and via Winckworth Sherwood’s letter dated 11 April 2024 that the S.38 Application was not approved.”

50. A letter of claim was sent by Winckworths on 11 April 2024 to HP. Under the heading ‘Breach of the Sale Agreement’ the letter made three claims:-

Claim 1:-

In breach of Paragraphs 2.1.1 and 2.2.4 Persimmon has failed to:

a. use all its reasonable endeavours to obtain the Requisite Consents for the Works; and

b. as soon as reasonably practicable following the Completion Date use all its reasonable endeavours to enter into an agreement with the Highway Authority pursuant to Section 38 and/or Section 278 of the Highways Act 1980.

Claim 2:-

In breach of Paragraph 2.2.1(e), Persimmon has failed to procure that Practical Completion of all of the Works shall occur on or before the date 2 years from the Completion date (i.e., by 14 March 2024).

Claim 3:-

In breach of Paragraphs 2.1.2, 2.2.8 and 2.5, Persimmon has failed to keep Harding/HIM informed of progress in obtaining the Requisite Consents, entering into any required Planning Agreements, the progress of the Works and any material problems or delays affecting the Works.

51. In the letter of claim Winckworths stated:-

“Harding is not prepared to consent to Persimmon’s proposed scheme given the interference it will have with Harding’s own development initiatives, as Persimmon is aware. It will therefore be necessary for Persimmon to re-design the scheme and submit revised drawings to the relevant highways authorities (as Harding will not enter into the relevant Section 38 and Section 278 Agreements on the basis of the Persimmon’s drawings ), which will inevitably cause further delay.”

52. HP wrote in response to the letter of claim by letter dated 30 May 2024. In response to Claim 1 HP referred to and relied on the four emails sent by Mr Doran to Mr Edwards. They referred to these emails as “Update Emails” 1, 2, 3, and 4. They said:-

The Update Emails included updates as to the progress of the applications for approval, as well as copies of the latest drawings for the Works. Your clients were invited to comment on those drawings and/or be involved in design meetings.

53. On 20 March 2025 Walker Morris (“WM”) were appointed to act for Persimmon in place of HP. In its letter dated 4 April 2025 WM asserted that the Emails sent to Ed Saunders were requests for approval pursuant to the terms of the SPA. They said that if this was not accepted this was another matter which their client might need to have determined by an Expert in accordance with clause 8 of the SPA either as part of or separately from a determination of the length of the extension.

54. Correspondence continued between the parties until Persimmon issued this claim on 17 February 2026.

55. By its Particulars of Claim Persimmon seeks negative declarations that the Defendants have no claim by way of Claim 1, 2 or 3; a declaration that Persimmon is entitled to locate the Attenuation Pond with no further consent of the Defendant required; a declaration that Persimmon is entitled to an extension to the date for Practical Completion under paragraph 8.2 of Schedule 2 to the SPA and an injunction restraining the Defendants from engaging the step-in rights under paragraph 7.2 of Schedule 2 to the SPA.

56. A Defence and Counterclaim was filed on behalf of the Defendants on 16 March 2026. A Reply and Defence to Counterclaim was filed on behalf of Persimmon on 30 March 2026.

57. The Defendants issued their application for summary judgment on 17 April 2026. The order sought is that

1. The Court makes the declarations referred to at paragraph 47 of the Particulars of Counterclaim

2. The Defendants be awarded summary judgment on the Claim

3. The Defendants be awarded summary judgment on liability on the Counterclaim (with damages to be assessed)

4. The Defendants be granted an interim payment on account of damages pursuant to CPR 25.20 such damages to be in the sum of £15,150,000.00 or otherwise in a sum to be assessed by the Court.

In paragraph 47 of the Counterclaim:-

The Defendants seek a declaration that:

a. The Emails were not requests for approval which required approval under clause

8.2 of Schedule 2 of the SPA.

b. Harding has not unreasonably withheld its consent in relation to any matter raised

in the Emails.

c. The Emails had not been received by Harding and therefore the Emails were not

requests for approval which required approval under clause 8.2 of Schedule 2 of

the SPA.

d. The Defendants are entitled to exercise the Step-In Rights.

58. Mr Williams accepts in paragraph 17 of his 1st witness that Claims 1 and 3 would not be susceptible to an application for summary judgment. He says in paragraph 2 that the application for summary judgment is based on the Claimant’s breach of the SPA in failing to complete certain works that ought to have been completed by 14 March 2024. This is Claim 2. Notwithstanding the Defendants in their application notice without qualification sought summary judgment on the “Claim”, it was clearly understood by both sides before me that summary judgment was being sought by the Defendants against Persimmon on the basis of Claim 2 alone.

59. On 29 June 2026 Persimmon filed its evidence in answer to the summary judgment application. This consisted of the 1st witness statement of Mr Atton dated 3 July 2026 and the witness statement of Mr Paul Wright dated 29 June 2026. Mr Atton’s statement annexed an expert report from Mr Brian Cafferkey of Ardent Consulting Engineers an expert in the field of flood risk and drainage engineering.

60. By application dated 29 June 2026 Persimmon sought permission to rely on this expert report pursuant to CPR 35.4 at the summary judgment hearing on the basis that the summary judgment application raised issues which could not be determined by the Court without the assistance of expert evidence, namely the requirements of the Highway Authority regarding the provision of an Attenuation Pond and the viability of the potential locations for such a pond. Claim 2. The granting of such permission was not opposed by the Defendants. I granted it.

61. A 2nd witness statement in reply was filed by Mr Williams on 22 July 2026. I gave permission to Persimmon to rely on a 2nd witness statement made by Mr Atton on 27 July 2026 whose purpose was to introduce into evidence overlay plans prepared by him showing the original and proposed locations of the Attenuation Pond. Mr Atton says that it is clear from both a cursory visual inspection and his calculations that Persimmon’s proposed Attenuation Pond is approximately 65%of the size of the Attenuation Pond in its original location.

62. CPR 24.3 states:-

The court may give summary judgment against a claimant or defendant on the whole claim or on an issue if-

(a)it considers that the party has no real prospect of succeeding on the claim, defence or issue; and

(b) there is no other compelling reason why the case or issue should be disposed of at trial.

The principles applicable to applications for summary judgment were set out by Lewison J. in EasyAir Limited (Trading as OpenAir) v Opal Telecom Limited [2009] EWHC 339(Ch) at paragraph 15. These principles were approved by the Court of Appeal in AC Ward & Sons Ltd v Catlin (Five) Ltd [2009] EWCA Civ 10.

63. These principles have been more recently restated by Nicklin J. in Amershi v Leslie [2023 EWHC 168 (KB) at 142:-

“The, now familiar, principles governing summary judgment were summarised in Easyair Ltd -v- Opal Telecom Ltd [2009] EWHC 339 (Ch) [15] per Lewison J (and approved by the Court of Appeal in AC Ward & Sons Ltd -v- Catlin (Five) Ltd [2009] EWCA Civ 1098 ). Drawing upon other relevant authorities the following can be stated:

(1) The court must consider whether the claimant has a ‘realistic’ as opposed to a ‘fanciful’ prospect of success: Swain -v- Hillman [2001] 1 All ER 91. The criterion is not one of probability; it is absence of reality: Three Rivers DC -v- Bank of England (No.3) [2003] 2 AC 1 [158] per Lord Hobhouse.

(2) A " realistic " claim is one that carries some degree of conviction. This means a claim that is more than merely arguable: ED & F Man Liquid Products -v- Patel [2003] EWCA Civ 472 [8]

(3) In reaching its conclusion the court must not conduct a " mini-trial ": Swain -v- Hillman. This does not mean that the court must take at face value and without analysis everything that a claimant says in his statements before the court. In some cases it may be clear that there is no real substance in factual assertions made, particularly if contradicted by contemporaneous documents: ED & F Man Liquid Products -v- Patel [10]; Optaglio -v- Tethal [2015] EWCA Civ 1002 [31] per Floyd LJ.

(4) However, in reaching its conclusion the court must take into account not only the evidence actually placed before it on the application for summary judgment, but also the evidence that can reasonably be expected to be available at trial: Royal Brompton Hospital NHS Trust -v- Hammond (No.5) [2001] EWCA Civ 550 ; Doncaster Pharmaceuticals Group Ltd -v- Bolton Pharmaceutical Co 100 Ltd [2007] FSR 63 .

(5) Nevertheless, to satisfy the requirement that further evidence " can reasonably be expected " to be available at trial, there needs to be some reason for expecting that evidence in support of the relevant case will, or at least reasonably might, be available at trial. It is not enough simply to argue that the case should be allowed to go to trial because something may " turn up ". A party resisting an application for summary judgment must put forward sufficient evidence to satisfy the court that s/he has a real prospect of succeeding at trial (especially if that evidence is, or can be expected to be, already within his/her possession). If the party wishes to rely on the likelihood that further evidence will be available at that stage, s/he must substantiate that assertion by describing, at least in general terms, the nature of the evidence, its source and its relevance to the issues before the court. The court may then be able to see that there is some substance in the point and that the party in question is not simply playing for time in the hope that something will turn up: ICI Chemicals & Polymers Ltd -v- TTE Training Ltd [2007] EWCA Civ 725 [14] per Moore-Bick LJ; Korea National Insurance Corporation -v- Allianz Global Corporate & Speciality AG [2008] Lloyd's Rep IR 413 [14] per Moore-Bick LJ; and Ashraf -v- Lester Dominic Solicitors & Ors [2023] EWCA Civ 4 [40] per Nugee LJ. Fundamentally, the question is whether there are reasonable grounds for believing that disclosure may materially add to or alter the evidence relevant to whether the claim has a real prospect of success: Okpabi -v- Royal Dutch Shell Plc [2021] 1 WLR 1294 [128] per Lord Hamblen.

(6) Lord Briggs explained the nature of the dilemma in Lungowe -v- Vedanta Resources plc [2020] AC 1045 [45]:

“… On the one hand, the claimant cannot simply say, like Mr Micawber, that some gaping hole in its case may be remedied by something which may turn up on disclosure. The claimant must demonstrate that it has a case which is unsuitable to be determined adversely to it without a trial. On the other, the court cannot ignore reasonable grounds which may be disclosed at the summary judgment stage for believing that a fuller investigation of the facts may add to or alter the evidence relevant to the issue…”

(7) The Court may, after taking into account the possibility of further evidence being available at trial, and without conducting a 'mini-trial', still evaluate the evidence before it and, in an appropriate case, conclude that it should " draw a line " and bring an end to the action: King -v- Stiefel [2021] EWHC 1045 (Comm) [21] per Cockerill J.”

64. In Anan Kasei Co Ltd v Neo Chemicals and Oxides (Europe) Ltd [2021] EWHC 1035 (Ch) Fancourt J. at [82] stated:-

“The “issue” to which rule 24.2 (“the claimant has no real prospect of defending the claim or issue”) and PD24 refers is a part of the claim, whether a severable part of the proceedings (e.g. a claim for damages caused by particular acts of infringement or non-payment of several debts) or a component of a single claim (e.g. the question of infringement, or the existence of a duty, breach of a duty, causation or loss). It is not any factual or legal issue that is one among many that would need to be decided at trial to resolve such a claim or part of a claim. If the determination of an issue before trial has no consequences except that there is one fewer issue for trial then the court has not given summary judgment and the application was not for summary judgment. If it were otherwise, parties would be able to pick and choose the issues on which they thought their cases were strong and seek to have them determined in isolation, in an attempt to achieve a tactical victory and cause the respondent to incur heavy costs liability at an early stage.”

65. It is accepted by Persimmon that the Works were not completed on or before 14 March 2024 or on or before 28 March 2024. Persimmon claims that it is entitled to an extension of time pursuant to paragraph 8.2 of Schedule 2 to the SPA:

“The Buyer shall be entitled to an extension of time for completion of the relevant Works where it is delayed from carrying out and completing the same by reason of the Seller unreasonably withholding or delaying its approval to any matter which requires the Seller’s approval (including but not limited to the location of any Attenuation Ponds…”

66. Harding submits that Persimmon has no realistic prospect of being able to establish a case for an extension of time under paragraph 8.2 of Schedule 2.

67. Harding submits that neither the provision of attenuation ponds nor the change of location for the Attenuation Ponds were ever requested or required by any Relevant Body. It submits that therefore the requirement for Persimmon to seek Harding’s consent to their location simply does not arise. This submission arises from the opening words of paragraph |2.1.4 which states:-

Where the Highway Authority shall reasonably require the provision of Attenuation Ponds…”

68. Mr Williams at paragraph 43 of his 1st witness statement says that after the dispute arose he made am enquiry as to whether Essex Highways had asked for the Attenuation Pond to be moved. He exhibits an exchange of emails between Winckworths and Essex Highways on 16th-17th September 2025:

“Please confirm if ECC Highways or any other authority have advised Persimmon Homes for any reason, why there is a need for an enlarged attenuation pond to be provided and why this is sought/proposed to be sited on part of my clients land which was intended for commercial development in accordance with the existing planning permission. You will appreciate this is a material change to what was envisaged in the approved planning drawings. I/Essex Highways have not made any comments in relation to the attenuation pond such as the location or size of it.”

69. In response to this point, Mr Atton says in his 1st witness statement that the requirement in paragraph 2.1.4 of Schedule 2 is not that the Highway Authority must issue an express direction as to where the Attenuation Pond is to be located. He says Mr Williams’ suggestion demonstrates a lack of understanding of the detailed technical requirements of the Highways Authority that need to be satisfied in order for Persimmon to acquire their technical approval and agreement to enter into a Section 38 Agreement and how those requirements are implemented. Persimmon says that it must first obtain technical approval by demonstrating compliance with the Highway Authority’s detailed requirements. It says those are contained in the Essex Highways Development Construction Manual and the Essex Design Guide. Persimmon.

70. In my view this is not an issue which it is appropriate for the Court to determine on an application for summary judgment. It requires the Court to investigate whether the proposed location of the attenuation pond was “required” or “reasonably required” by the Highways Authority. This may be an issue on which expert evidence is required.

71. In order for Persimmon to be entitled to an extension of time under paragraph 8.2 it has to show that it was delayed from carrying out the relevant Works “by reason of [Harding] unreasonably withholding or delaying its approval to any matter which requires [Harding’s] approval (including but not limited to the location of any Attenuation Pond).

72. Harding submits that in order for it to be found to have unreasonably withheld or delayed its approval to any matter which requires its approval there must have been a request made to it for approval by or on behalf of Persimmon.

73. Persimmon’s case is that it requested Harding’s approval to the relocation of the Attenuation Pond by means of the emails sent by Mr Doran to Mr Saunders on 9 March 2022, 6 October 2022, 10 March 2023 and 18 October 2023 and thereafter orally and in correspondence following a meeting on 5 April 2024.

74. Harding submits that these emails cannot be viewed as a request for consent to any variation of the Drainage Specification. The Drainage Specification is defined in the SPA as:-

“the specification for the Drainage Works annexed to this Agreement at Part 2 of Annexure 4 and so marked subject to such variations thereto as the Buyer shall reasonably specify insofar as is necessary in order to secure any relevant Requisite Consent appliable thereto and which the Seller shall previously approve Provided That the Seller shall not withhold such approval where such revisions are reasonably required by any such authority and there is no viable or reasonable alternative specification;”

75. Persimmon’s case is that the location of the Attenuation Pond forms part of the Infrastructure Works and not the Drainage Specification. It points out that the definition of “Infrastructure Works” refers to the works of construction of the Infrastructure. Infrastructure includes the Attenuation Pond.

76. Harding submits in any event that as a matter of construction the Emails cannot be read as asking for consent or approval. Harding submits this is an issue of construction on which the Court at the summary judgment stage is as well placed as the trial judge to come to a conclusion.

77. I remind myself that this is a summary judgment application. In reaching its conclusion the Court must not conduct a mini-trial. I must take into account not only the evidence before me but also the evidence that could reasonably be expected at trial.

78. On the other hand, as Lewison J. stated under sub-paragraph vii:-

“it is not uncommon for an application under Pt 24 to give rise to a short point of law or construction and, if the court is satisfied that it has before it all the evidence necessary for the proper determination of the question and that the parties have had an opportunity to address it in argument, it should grasp the nettle and decide it.”

79. The express purpose of the first email sent by Mr Doran to Mr Saunders was to “keep you in the loop with the progress on the A120 roundabout and Link Road”. The subject of the email was ‘Harwich A120 Roundabout and Link Road’. Mr Doran included a link to all the working drawings but asked Mr Saunders to be aware these were subject to change throughout the technical approval process. The email concluded “If you have any questions, or want to be involved in the design meetings, just let me know”.

80. On its face the purpose of the first email was twofold. It was to keep Harding informed of progress in obtaining the Section 38 and Section 278 agreements and to give Harding the opportunity to raise questions or make comments. The purpose of the email was to fulfil Persimmon’s contractual obligations to keep Harding informed of the progress of the Works and to give Harding the opportunity to raise questions or make comments.

81. The subsequent emails were sent at roughly six monthly intervals. Their purpose in each case was to update and provide an opportunity for questions or comments. Against the background of Persimmon’s contractual obligations in Schedule 2, the Emails had a commercial and contractual purpose.

82. The Emails do not expressly ask for Harding’s approval to the location of the Attenuation Pond. They do not contain either in the subject heading or in the text any reference to the Attenuation Pond. Their subject matter is stated to be the A120 Roundabout and Link Road.

83. On their natural and ordinary meaning and viewed against their contractual and commercial background I do not consider that the Emails, either alone or taken together, can or should be read as seeking approval for the relocation of the Attenuation Pond.

84. The fact (which I must assume to be the case) that the proposed location of the Attenuation Pond was shown on the workings drawings is not sufficient in my view to convert the Emails into a request for approval of that location.

85. The working drawings were described in the first email as being subject to change throughout the technical process. Although both the third and fourth emails referred to the packages as “nearing technical approval”, approval of the location of the Attenuation Pond was not sought.

86. On behalf of Persimmon it was submitted that the proper construction of the Emails falls to be assessed in their commercial and contractual context. I was referred to paragraph 10 of the judgment of Lord Bingham of Cornhill in Homburg Houtimport BV v Agrosin Private Ltd (‘The Starsin’) [2004] 1 A.C. 715 at 737:-

“10. First is the rule to which Lord Halsbury alluded in Glynn v Margetson & Co [1893] AC 351 at 359, ‘that a business sense will be given to business documents’. The business sense is that which businessmen, in the course of their ordinary dealings, would give the document. It is likely to be a reasonably straightforward sense since, as Lord Mansfield famously observed (Hamilton v Mendes (1761) 2 Burr 1198 at 1214, 97 ER 787 at 795), ‘The daily negotiations and property of merchants ought not to depend upon subtleties and niceties; but upon rules, easily learned and easily retained, because they are the dictates of common sense, drawn from the truth of the case’.

87. It was submitted it is clear from the correspondence that the parties were accustomed to communicating informally. It was submitted that the parties were not lawyers and did not couch their correspondence in the language of the relevant contractual provisions and nor should they be expected to do so. It was submitted that read against that background the natural and ordinary meaning of the Emails is that they were requests for approval.

88. I accept that the Emails should be construed in their commercial and contractual context but I do not accept that the Emails would have been understood by a person with knowledge of their commercial and contractual background as seeking consent or approval to the relocation of the Attenuation Pond. In my view, it was incumbent on Persimmon if seeking approval to the relocation of the Attenuation Pond to make clear that in order to meet the requirements of the local Highway Authority, Harding’s approval to the relocation of the Attenuation Pond was sought.

89. The re-location of the Attenuation Pond was not a routine matter. The parties to the SPA contemplated that the location of the Attenuation Pond might impact development on the Retained Land or on the HIM Land. Paragraph 2.1.4 includes an obligation on the Buyer:-

“[to] use reasonable endeavours to limit the extent of the HIM Land and/or the Retained Land as may be required for any such Attenuation Ponds”

90. The need for the Buyer to obtain the Seller’s prior approval to the location of the Attenuation Pond is referred to expressly in the definition of “Attenuation Pond(s), in clause 2.1.4 of Schedule 2 and in clause 8.2 of Schedule 2 itself.

91. It was in my view open to Persimmon to make that request by email but such a request needed to be made expressly in writing and not to be implied by providing links to road designs. Clause 1.3 of the SPA makes express provision for requests for consent or approval. Clause 1.3.2(d) provides

“And for the avoidance of doubt requests for consent and responses to such requests may be sent by email in accordance with the provisions of this Agreement”.

92. On behalf of Harding, it was argued that “in accordance with the provisions of this Agreement” required compliance with Clause 7.3 which provides:-

Service of a notice by e-mail shall not be good service of such notice for the purposes of this Agreement unless the proposed recipient of any such notice shall have confirmed by e-mail to the proposed server of such notice (before such notice is served by e-mail) that it is willing to accept service of such notice to the e-mail address from which such confirmation is being issued in which case the service of that particular notice shall be capable of being served by e-mail for the purposes of this Agreement.”

93. The seeking of consent or approval under Clause 1.3 did not involving the serving of a notice within Clause 7.3. Other provisions in the SPA expressly refer to the Buyer being entitled to serve notice on the Seller, as in Clause 25.2.4.

94. Clause 1.3 does however, in my view, require that requests for consent or approval be made expressly and in writing. It sets out a machinery under which where approval has been requested pursuant to the terms of the Agreement approval is deemed to have been given. That machinery under clause 1.3.2(b) provides that:-

“if the party to whom a request has been made for their consent or approval pursuant to the terms of this Agreement shall not provide such response within 5 Working Days the party requesting the other party’s request or approval shall be entitled to serve a further request upon the other party requesting their consent or approval in relation to any matter included in the previously unanswered request and in respect of which consent or approval is required pursuant to the terms of this Agreement;”(emphasis added).

95. In my view the fact that consent or approval is deemed to have been given under clause 1.3.2 (c) if a party to whom a further request is made fails to respond is an indication in itself that the seeking of consent or approval was regarded under the SPA as a formal matter requiring a specific procedure to be followed.

96. It was submitted on behalf of Persimmon that there would be no commercial purpose in Persimmon repeatedly sending Harding’s nominated contact the evolving working drawings, showing the proposed relocation of the Attenuation Pond, other than to obtain Harding’s approval to that relocation. Nor, it was submitted, would a request for comments be made if the purpose of the Emails was simply ‘for information’. Such a request for comment it was submitted invites either dissent whether by way of proposed modification or improvement, acquiescence or acceptance.

97. I do not accept that submission. The SPA required Persimmon to keep Harding informed of progress in obtaining Requisite Consents (paragraph 2.1.2 of Schedule 2) and to have due regard to any comments that the Seller might make with regard to the Requisite Consents from time to time (paragraph 2.1.3 of Schedule 2). In addition, paragraph 2.2.4 provided:-

“The Buyer shall as soon as reasonably practicable following the Completion Date use all its reasonable endeavours to enter into an agreement with the Highway Authority pursuant to Section 38 and/or Section 278 of the Highways Act 1980 in relation to the future adoption of the Spine Road as a highway maintainable at the public expense and keep the Seller fully informed in relation to its progress in connection with the same and upon entry into such a Planning Agreement the Buyer shall observe and perform its obligations contained in the same and shall use all reasonable endeavours to procure that the Highway Authority shall observe its obligations contained in the same” (emphasis added).

98. In my view the Emails cannot be read as requests for approval under the SPA for the relocation of the Attenuation Pond. Their stated purpose was to keep Harding informed as to progress and to invite any comments on the A120 roundabout and link road designs. It was in my view incumbent on Persimmon to make clear on the face of any request that it was seeking approval to the relocation of the Attenuation Pond in order to meet the requirements of the local highway authority.

99. Furthermore, and as a separate point, I do not consider that Persimmon has any realistic prospect of being able to establish at trial that it was delayed from carrying out the relevant Works by reason of Harding unreasonably withholding or delaying its approval to any matter that required its approval. In his email to Mr Williams on 18 October 2023 at 09.55 Mr Atton said:-

“Since that time we have been trying to get Highways England technical approval for the s.278 works (the proposed new roundabout on the A120). As you are aware, this has been a long drawn out process but we are close to obtaining technical approval, we just need to get a contractor placed for this work.”

100. In his email to Mr Williams on 18 October 2023 at 16.40 Mr Atton again referred to “the delays we have suffered through the s.278 Highways England approval process since legal completion of the site in March 2022”. At that time Mr Atton was still hopeful that there was sufficient time to get the Works completed.

101. In March 2024 Mr Williams asked Mr Atton to send him the highway drawings. These were reviewed by Harding’s consultants on 15 March 2024 after the CAD drawings were provided. On 15 March 2024 Mr Williams described the responses he had received from Harding’s consultants as being “not only disturbing but disappointing to read”. In response in his email dated 18 March 2024 Mr Atton referred to the Emails sent to Mr Saunders. He said:-

“I would have hoped that if he was unhappy with the direction of travel he would have communicated this. Given that he never responded or communicated to us given our timescales we have looked to progress this.”

102. In an email sent on 19 March 2024 Mr Williams responded:-

“The delay in completing the infrastructure works is not of my making or choosing in any way whatsoever as you know very well, I have tried to establish a pragmatic outcome for both of us.”

103. In his email in response on 19 March 2024 Mr Atton said:-

As far as I am aware, up until now we have never said any of the delays were as a result of your making/choosing however, as discussed on our call, it seems surprising to me that as of Friday evening issues with the s.278 and s.38 drawings were raised (as I had been told that Ed was being kept updated) and even more so now following your below email where you are saying your transport consultants have had the Essex Highways Drawings since November 2023. As you know I have not been personally involved in trying to obtain technical approval from the highways authority and was only brought back into this once you contacted me last year and begun work on recovering your alleged losses.”(Emphasis added).

104. Mr Atton’s complaint is that it was very late in the process for Harding to ask for changes to be made. Mr Atton is accepting that up until then the delays were not of Harding’s making or choosing.

105. On behalf of Persimmon reliance was placed on Clause 27.4 1 of the SPA which provides:-

“The Seller and the Buyer are to act in good faith towards each other in relation to matters which are subject to this Deed;”

106. In paragraph 7.2 of the Particulars of Claim it is alleged that the Letter of Claim was not written in good faith and that all three claims ought to be barred as an attempt by Harding to take advantage of its own wrong. In my view Persimmon’s failure to complete the Works on or before the date 2 years from the Completion Date was not brought about by any wrong on the part of Harding and Persimmon has no realistic prospect of showing at trial that this breach was brought about by any such wrong.

107. In my view Persimmon’s failure to carry out the Works in accordance with paragraph 2.2.1(e) was a distinct and separate breach for which Harding was not responsible.

108. In my view Persimmon does not have a realistic prospect at trial of being able to establish that it was not in breach of paragraph 2.2.1 (e) because it was entitled to an extension of time under paragraph 8.2 of Schedule 2.

109. Nor in my view is there any other compelling reason why that liability issue should be disposed of at trial.

110. There will of course need to be a trial on quantum to determine what if any loss was caused by this breach to Harding. In addition, Harding’s application for an interim payment will need to be determined at a further hearing.

111. I will hear counsel on the relief that should be granted consequential upon this Judgment and the form of order. I would be grateful if counsel would let me know whether a hearing consequential upon this judgment is needed in addition to the hearing of the interim payment part of the application.

112. I propose to hand this judgment down remotely without attendances being required on Wednesday 30 September 2026 at 10.30am. I would be grateful to receive typographical corrections in one combined letter by 4pm on Monday 28 September 2026.


Open Justice Licence (The National Archives).

Neighbouring decisions

Preliminary case review

Send your documents. Receive an analysis.

Send us the documents in your case. Hassan KOHEN reviews them personally and sends you a first written analysis of your situation within 24 working hours.

  • Written analysis by the lawyer, €80 incl. VAT
  • Personal reply within 24 working hours
  • 100% confidential, legal professional privilege guaranteed
  • Up to 1 GB of documents in total, folders and sub-folders accepted
80 €incl. VAT

Preliminary review of your case. Review of your documents and a first written analysis by Hassan KOHEN within 24 working hours. Payment is made online after this form is submitted.

  • Up to 1 GB of documents in total, folders and sub-folders accepted
  • Secure payment, no card details stored
  • Terms and fee agreement

Click or drag your files here
All formats accepted (PDF, Word, images, etc.)

Sending...

Payment constitutes a request for immediate performance of your analysis. Your data is used solely to process your request.
Terms · Privacy policy.

IA juridique gratuite

Une question de droit ? Demandez à Judith.

Judith cherche dans les codes, la Constitution, la Convention européenne des droits de l’homme et les décisions des juges, puis vous montre les textes et les passages d’arrêts qui pourraient répondre à votre question, avec leur source officielle. Gratuite, sans compte, elle ne rédige rien à votre place. Découvrir Judith, l’IA juridique gratuite du cabinet.

Trois recherches par jour, sans compte. Votre question est enregistrée et relue par le cabinet pour améliorer l’outil : n’y mettez ni nom ni information sensible.